Protect Your Right To Payment By Following Nedd
August 03, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogIn order to preserve your right to payment, you must satisfy the contractual requirements supporting a change order for the increased costs or time due to the delay. The key to the successful presentation of change order claims is educating your team on the following:
1. NOTICE
- Review the change order and notice provisions of your contracts. Make your contract searchable and insert the term “Noti” and look for the items listed below.
- Who: Check the designated representative for notice.
- It may not be the project manager.
- Confirm who can authorize the change order.
- Is owner approval required?
- Ensure that the party approving the change order has authority to do so.
- What: Check for specific information required by the contract.
- Provide ALL information available.
- If certain information is not yet available, state that the information will be provided when available.
- Reserve all rights to amend and submit additional information.
- Request both an increase to the Contract Sum and Contract Time.
- Make the request even if you do not believe the delay or time necessary will cause a significant impact.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com
Construction Litigation Roundup: “Apparently, It’s Not Always Who You Know”
December 16, 2023 —
Daniel Lund III - LexologyA respondent party in a pair of international arbitrations on the losing end of roughly $285,000,000 in adverse awards attacked the awards based upon arbitrator bias.
“If there is one bedrock rule in the law of arbitration, it is that a federal court can vacate an arbitral award only in exceptional circumstances. … The presumption against vacatur applies with even greater force when a federal court reviews an award rendered during an international arbitration.”
Applying the Federal Arbitration Act (according to the court, the international arbitrations were “seated” in the United States and fell under the New York Convention, such that the FAA is required to be the basis for vacatur efforts), the court examined assertions that certain alleged non-disclosures by the panel “concealed information related to the arbitrators’ possible biases and thereby ‘deprived [respondent] of [its] fundamental right to a fair and consensual dispute resolution process.’” The aggrieved party urged that one arbitrator’s undisclosed nomination of another arbitrator to serve as president of another arbitral panel – “a position that sometimes pays hundreds of thousands of dollars” – possibly influenced the second arbitrator to side with the first. Assertions were also levied that the arbitrators’ undisclosed work with the attorneys for the claimant in other arbitrations “allowed them to become familiar with each other, creating a potential conflict of interest.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Want to Make Your Jobsite Safer? Look to the Skies.
October 10, 2022 —
Rory San Miguel - Construction ExecutiveNew York Gov. Kathy Hochul is set to sign Carlos’ Law for worker protection. The law would set a national precedent for construction site safety, substantially raising the minimum fines for construction companies found liable for onsite injuries.
Worksites are very complex, and many factors go into creating a safe space. Following suit, innovative operators are looking at advanced technologies to boost onsite safety, including drone data visualization, which involves flying a drone over a site to capture a highly accurate 3D model of current conditions in close to real time. Using drones can't solve every problem, but it can help not only protect workers but also encourage new ones to join your team.
How drone surveying improves jobsite safety
3D mapping a worksite with a drone keeps workers out of harm’s way, helping surveyors avoid potentially dangerous areas filled with constantly moving heavy equipment and machinery. Drone mapping also means surveyors can stay out of the heat, avoiding the risk of excess sun exposure by sending the drone out in their stead to traverse the terrains and slopes of the site.
Reprinted courtesy of
Rory San Miguel, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Top Five Legal Mistakes in Construction
April 04, 2022 —
Jonathan A. Cass, Nicholas F. Morello & John A. Greenhall - Construction ExecutiveMany contractors repeatedly make the same mistakes in negotiating contracts. Here are the most common mistakes contractors make—and how they can be avoided.
1. Not Being Careful With Force Majeure Clauses
To protect themselves from liability in the event of unforeseen circumstances like fires, floods, wars, unusual delays in deliveries, strikes, pandemics or acts of God, contractors should ensure their contracts contain robust force majeure provisions. These provisions state that in the event of any extenuating circumstances outside of its control, the contractor is not liable for any damages that result from a delay to the project completion date and is entitled to a time extension. This clause has been critical in addressing COVID-19-related disruptions and the current material shortages. Contractors should be wary, however, of “no damage-for-delay” language, which often appears in conjunction with these clauses.
Reprinted courtesy of
Jonathan A. Cass, Nicholas F. Morello and John A. Greenhall, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Cass may be contacted at jcass@cohenseglias.com
Mr. Greenhall may be contacted at jgreenhall@cohenseglias.com
Mr. Morello may be contacted at nmorello@cohenseglias.com
Read the court decisionRead the full story...Reprinted courtesy of
Ninth Circuit Resolves Federal-State Court Split Regarding Whether 'Latent' Defects Discovered After Duration of Warranty Period are Actionable under California's Lemon Law Statute
December 17, 2015 —
Laura C. Williams & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Daniel v. Ford Motor Company (filed 12/02/15), the Ninth Circuit resolved a federal and state court split on the issue of whether consumers can sustain a breach of implied warranty claim under California’s Song Beverly Consumer Warranty Act (aka the “lemon law” statute) for “latent” defects discovered after the warranty period has expired. Answering this question in the affirmative, the Ninth Circuit followed the holding in the California state appellate decision of Mexia v. Rinker Boat Co. 95 Cal.Rptr.3d 285 (2009), which definitively determined there is nothing in California’s lemon law that requires a consumer to discover a latent defect during the duration of the warranty.
The underlying class action lawsuit was brought in federal district court by purchasers of Ford Focus vehicles. The plaintiffs alleged Ford was aware of, but failed to disclose, a rear suspension defect in the Focus that resulted in premature tire wear which can cause decreased vehicle control, catastrophic tire failure and drifting on wet or snowy roads. The plaintiffs alleged a number of claims including violations of California’s Song Beverly Consumer Warranty Act and Magnuson Moss Warranty Act. Ford successfully moved for summary judgment on all claims prompting an appeal.
Reprinted courtesy of
Laura C. Williams, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Ms. Williams may be contacted at lwilliams@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Fix for Settling Millennium Tower May Start This Fall
August 17, 2020 —
Nadine M. Post - Engineering News-RecordWith the lengthy and complex permitting and approval process complete and almost all the other details worked out, construction could begin in mid-November on the estimated $100-million shoring fix for the 645-ft-tall Millennium Tower in San Francisco. The perimeter pile upgrade for the 58-story residential condominium building, which has settled more than 17 in. toward the northwest since its completion in 2009, was originally expected to begin earlier this year.
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Ensuing Loss Provision Salvages Coverage for Water Damage Claim
September 16, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Court of Appeals for the D.C. Circuit reversed the district court's finding of no coverage and found that the ensuing loss provision provided coverage for water damage. 3524 East Cap Venture, LLC, et al. v. Weschester Fire Ins. Co., et al., 104 F. 4th 193 (D.C. Cir. 2024).
Plaintiff 3534 East Cap Venture, LLC, a real-estate developer, hired plaintiff McCullough Construction, LLC, to build a residential and retail complex. Defendants Westchester Fire Insurance Company and Endurance American Insurance Company issued identical builders' risk policies, which covered the building while it was under construction. Each insurer was responsible for half of any qualifying losses.
The policies covered loss caused by or resulting from water damage. The policies, however, excluded loss caused by "dampness of atmosphere" or by "[e]xtremes or changes in temperature." But the exclusions contained an exception if "loss by an insured peril ensues."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Adobe Opens New Office Tower and Pledges No Companywide Layoffs in 2023
April 18, 2023 —
Edward Ludlow & Brody Ford - BloombergAdobe Inc., breaking ranks with an industry cutting costs and laying off workers, has opened a new office tower in its home city, adding new capacity for staff and pledging no companywide job cuts in 2023.
The Founders Tower is an 18-story, 1.25 million-square-foot shimmering glass addition to San Jose, California, a city Adobe has called home since the early ’90s. The software company’s fourth tower has capacity for 3,000 employee workstations, Adobe said Wednesday in a statement. Despite opening a new office with amenities, the company remains supportive of hybrid and flexible work arrangements.
“We’re actually committed to continuing to grow here,” Adobe Chief People Officer Gloria Chen said in an interview with Bloomberg Television to air Wednesday. “We are committed to not having companywide layoffs.”
Reprinted courtesy of
Edward Ludlow, Bloomberg and
Brody Ford, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of