Federal Court Asks South Dakota Supreme Court to Decide Whether Injunction Costs Are “Damages,” Adopts Restatement’s Position on Providing “Inadequate” Defense
August 13, 2019 —
Anthony L. Miscioscia & Timothy A. Carroll - White and Williams LLPDo costs associated with complying with an injunction constitute covered “damages?” The U.S. District Court for the District of South Dakota recently certified that question to the South Dakota Supreme Court, in Sapienza v. Liberty Mutual Fire Insurance Company, No. 3:18-CV-03015-RAL, 2019 U.S. Dist. LEXIS 84973 (D.S.D. May 17, 2019). If the South Dakota Supreme Court takes on the question, it will become one of the few highest state courts to do so.[1] The Sapienza case is also notable because the court adopted § 12 of the Restatement of the Law of Liability Insurance (Restatement) regarding an insurer’s potential liability for providing an “inadequate” defense. In doing so, the Sapienza court joins a growing list of courts to rely upon or cite to the Restatement.
The Sapienza case arose out of an underlying dispute between residential neighbors over the size and location of the Sapienzas’ new house they built in a historic district in Sioux Falls, SD. The newly-built house allegedly prevented the neighbors from using their fireplace, blocked natural light the neighbors previously enjoyed, and decreased the value of the neighbors’ house. The neighbors sought a permanent injunction requiring the Sapienzas to modify or relocate the house. The Sapienzas’ homeowners’ insurer provided them with defense counsel, but the insurer instructed the Sapienzas that it would not cover any costs associated with an injunction as such costs did not constitute covered “damages.”
Reprinted courtesy of
Timothy Carroll, White and Williams LLP and
Anthony Miscioscia, White and Williams LLP
Mr. Schulman may be contacted at carrollt@whiteandwilliams.com
Mr. Anderson may be contacted at misciosciaa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Pandemic of Litigation Sure to Follow the Coronavirus
March 30, 2020 —
Aaron Lovaas - Newmeyer DillionAs the Coronavirus crisis persists, America’s richly diverse private business sector finds itself increasingly subject to unprecedented governmental orders and restrictions that were unheard of only a few weeks ago. While the various “shutdown,” “shelter in place,” and “non-essential business” orders all aim to protect the public health, there is no doubt that the wave of litigation to follow is already swelling.
Business interruption, civil authority, and cyber insurance coverages have already been widely discussed as issues certain to be litigated over the coming months and beyond. Additionally, breach of contract litigation is likely to spike as parties attempt to recoup their losses from canceled events, unfulfilled purchase commitments and other unmet obligations.
Moreover, regional and national businesses are now in the difficult position of managing their respective affairs to comply with a patchwork of executive orders that are inconsistent from state to state. And, as the pandemic wears on, many are questioning the authority under which some of these executive orders and emergency regulations are being issued in the first place. Indeed, constitutional challenges are almost certain to follow as the business community reframes the characterization of their losses into notions of unconstitutional takings of private property and governmental impairment of private contract rights.
Read the court decisionRead the full story...Reprinted courtesy of
Aaron Lovaas, Newmeyer DillionMr. Lovaas may be contacted at
aaron.lovaas@ndlf.com
Five Keys to Driving Digital Transformation in Engineering and Construction
January 02, 2019 —
Rob Phillpot - Construction ExecutiveEngineering and construction companies increasingly find themselves navigating an era of disruptive and transformative change driven by technology. And with the industry going strong and construction employment recently reaching a 10-year high, more companies recognize that it is time to embrace the efficiencies digital transformation brings, in large part to protect or enhance their competitive position.
A report from the Global Industry Council notes that modern technology is moving to the strategic center of E&C business models as part of an evolutionary process.
Reprinted courtesy of
Rob Phillpot, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
New Spending Measure Has Big Potential Infrastructure Boost
February 14, 2018 —
Tom Ichniowski – ENRConstruction and engineering companies find lots of good news in a newly enacted budget and appropriations package that keeps federal agencies open until late March, provides
$89 billion for post-disaster relief and rebuilding and also holds out the prospect of an additional $20 billion in infrastructure funding over the next two years.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, Engineering News-RecordMr. Ichniowski may be contacted at
ichniowskit@enr.com
Construction Defect Case Not Over, Despite Summary Judgment
November 07, 2012 —
CDJ STAFFThe Supreme Court of Oregon has concluded in an en banc decision that a motion to reconsider a summary judgment is not a motion for a new trial. In coming to their conclusion the court overturned an earlier Oregon Supreme Court case, Carter v. U.S. National Bank. Although the decision does not bear on construction defects, the underlying case did. Due to the decision, these claims can now be evaluated in a trial.
The case, Association of Unit Owners of Timbercrest Condominiums v. Warren, came about after an apartment complex was converted into condominium units. The developers hired Big Al’s Construction for some of the remodeling work. The condominium association later sued the developer and the contractor over claims of construction defects. The defendants filed a motion for summary judgment, which the court granted.
But that wasn’t the end of things. The plaintiff soon filed a “motion to reconsider,” noting that the summary judgment seemed to be in conflict with both law and other recent rulings, and additionally, the grounds for the decision were not in the order. The judge then notified the parties that the court had “pulled the trigger too quickly” and had seven questions for the parties to answer.
The court dismissed all claims against the defendants. The defendants filed their responses, objecting that that “‘there is no such thing’ as a motion for reconsideration.” Further, while “the rules do allow for post-judgment review of pre-judgment rulings through a motion for a new trial,” the plaintiffs had not filed for a new trial. But did they need one? They did file an appeal.
The judge in the case admitted that there was no such thing as a motion to reconsider, and felt bad about prematurely signing the judgment. The case was sent to the Court of Appeals to determine if the motion to reconsider was a request for a new trial. The Court of Appeals concurred.
In reviewing the decision, the Oregon Supreme Court concluded that there were a maximum of three questions to address. Was the motion for reconsideration a motion for a new trial? If so, was the later notice of appeal premature? And if so, was the plaintiff required to file a new appeal? The court determined that the answer to the first question was no.
Prior decisions pointed to the conclusion “that a motion for reconsideration of a summary judgment amounts to a motion for a new trial,” but here the court concluded that “our prior cases erred,” and turned to the summary judgment rule for clarification. The court noted that “the rule contemplates that summary judgment and trial are separate and distinct events.” With this conclusion, the Oregon Supreme Court remanded the case to the Court of Appeals for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Road Project to Improve Access to Peru's Machu Picchu Site
June 04, 2024 —
C.J. Schexnayder - Engineering News-RecordReaching the Incan citadel of Machu Picchu is historically famous for its difficulty. The site’s remote location was a factor in the Spanish conquistadors overlooking it as they swept Peru for its riches. Archaeologist and politician Hiram Bingham had been seeking another “lost” Incan city when he happened across it in 1911.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
Mr. Schexnayder may be contacted at schexnayderc@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Installation of Defective Steel Framing
June 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's holding that the insurer had no duty to defend claims arising out of the insureds' installation of defective steel framing in an apartment building. Regional Steel Corp. v. Liberty Surplus Ins. Corp., No. B245961(Cal. Ct. App. May 16, 2014) [decision here].
Regional Steel was a subcontractor for providing reinforced steel to the columns, walls, and floors of an apartment building under construction. Regional used 90 degree and 135 degree seismic hooks as approved by the general contractor, JSM Construction, Inc. The City building inspector issued a correction notice, however, requiring the exclusive use of the 135 degree hooks. Levels one through three had defective tie hooks and required repair. JSM refused to pay Regional's invoices and withheld $545,000. JSM had to make repairs that required opening up numerous locations in the concrete walls, welding reinforcements to the steel placed by Regional, and otherwise strengthening the inadequate installation.
Regional sued JSM for the withheld payment. JSM cross-claimed, asserting breach of contract and breach of express and implied warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pulling the Plug
December 13, 2022 —
Todd R. Regan - Construction ExecutiveAs a contractor, you may have wondered if your contract can be terminated by the owner for cause after the project has reached substantial completion. The answer is yes.
Under certain circumstances it may be permissible—or even necessary—for a project owner to terminate the contract for cause after the project has reached substantial completion. Although the rights of the parties in any case will depend in large part on the specific contract language, the fact that a project has reached substantial completion is not an absolute bar to termination for cause, particularly when the owner intends to pursue a performance-bond claim.
Completion Versus Performance
Following substantial completion, a contractor typically will have outstanding contractual obligations such as paying its subcontractors and suppliers, bonding off any mechanic’s liens, completing the punch list, remediating defective work, testing and commissioning equipment, providing manufacturer’s warranties and performing its own warranty obligations.
Reprinted courtesy of
Todd R. Regan, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of