Be Sure to Bring Up Any Mechanic’s Lien Defenses Early and Often
November 27, 2023 —
Christopher G. Hill - Construction Law MusingsAs those of you who regularly read Musings are aware, mechanic’s liens are a big part of my law practice and a big issue here at this construction law blog. I’ve discussed the picky requirements of the mechanic’s lien statutes in Virginia and how the 90 and 150-day rules are strictly enforced. However, a recent case out of the City of Norfolk Virginia Circuit Court cautions that while failure to meet these strict requirements may invalidate a lien, it only does so if the owner or general contractor seeking to invalidate the lien argues the invalidity and/or presents evidence of that invalidity either pretrial or during trial.
In Premier Restoration LLC v. Barnes, the Court considered the following facts. The defendant homeowners had a house fire and the resulting damage was the subject of an insurance claim that was paid and checks sent to the homeowners. Premier filed a mechanic’s lien in response to Barnes’s failure to pay for Premier’s restoration construction services after Barnes’s home was destroyed by fire. Premier seeks a decree to enforce the lien, asking the court to order the sale of Barnes’s property to recover its damages or, alternatively, a judgment in its favor. With the Complaint seeking enforcement of the lien and damages for breach of contract, and this is a key point, Premier provided a copy of the mechanic’s lien along with the affidavit that is part of the statutory form swearing that the Owner was justly indebted to Premiere. The homeowners filed a counterclaim for unfinished work, including unfinished punch list work. After a trial during which no evidence regarding either the timeliness of the lien recording or whether any of the work sought to be encompassed in the lien was performed outside of the statutory 150-day window was presented by either side, the defendants filed a post-trial motion seeking to invalidate the lien as including sums for work outside of the 150-day window.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Valerie A. Moore and Christopher Kendrick are JD Supra’s 2020 Readers’ Choice Award Recipients
July 13, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPHaight is thrilled to announce that Valerie A. Moore and Christopher Kendrick are receiving JD Supra’s 2020 Readers’ Choice Awards. The award acknowledges top authors and firms for their thought leadership in key topics during 2019. This is Valerie’s third JD Supra Readers’ Choice Award and Christopher’s second.
Specifically, Valerie and Chris receive the following recognition for the level of visibility and engagement our firm and authors attained in 2019, from among thousands of others, with readers of these topics:
Valerie Moore – a top author in Insurance
Christopher Kendrick – a top author in Insurance
JD Supra’s Readers Choice Awards
The Readers’ Choice Awards recognize top authors and firms who were read by C-suite executives, in-house counsel, media and other professionals across the JD Supra platform during 2019.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Reform Dies in Nevada Senate
May 10, 2013 —
CDJ STAFFNevada’s SB161 has failed to move out of the Senate Judiciary Committee. The bill would have reduced the time in which homeowners could file suits and also would have forbidden the inclusion of attorney’s fees as damages. A similar bill remains active in the Nevada House.
Read the court decisionRead the full story...Reprinted courtesy of
Contractual Waiver of Consequential Damages
January 02, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
A Court-Side Seat: May Brings Federal Appellate Courts Rulings and Executive Orders
June 29, 2020 —
Anthony B. Cavender - Gravel2GavelHere are a few interesting new rulings from the federal appellate courts.
COURT ORDERS
Like a Good Neighbor …? —
State of Maryland v. EPA
On May 19, 2020, the D.C. Circuit decided a Clean Air Act case involving the use of the “Good Neighbor Provision” of the Act, which is triggered when one state has a complaint about emissions generated in a neighboring upwind state that settle in the downwind state. Here, Maryland and Delaware filed petitions with EPA seeking relief from the impact of emissions from coal-fired power plants that allegedly affect their states’ air quality. EPA largely denied relief, and the court largely upheld the agency’s use and interpretation of the Good Neighbor Provision. The opinion is valuable because of its clear exposition of this complicated policy.
A Volatile Underground Issue —
Wayne Land and Mineral Group v. the Delaware River Basin Commission
Also on May 19, 2020, the U.S. Court of Appeals for the Third Circuit issued a ruling involving the Delaware River Basin Commission. Established in 1961, the Commission oversees and protects the water resources in the Basin. Not long ago, the Executive Director of the Commission, citing a rule of the Commission, imposed very strict limitations on fracking operations in the Basin. This decision has been very controversial with the Third Circuit opining that the Commission’s authority to regulate fracking operations—thought to be a province of state authority—was not clear-cut. In this case, three Pennsylvania state senators filed motions to intervene in the case, but the lower court rejected their request. The Third Circuit has directed the lower court to take another look at their standing to participate in this litigation. This is a volatile issue in Pennsylvania.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Dynamics of Managing Professional Liability Claims for Design Builders
February 21, 2022 —
Eric M. Clarkson - Saxe Doernberger & Vita, P.C.Nearly half of America’s construction projects are now design-build in a continuing shift. As a result, contractors are taking on more professional liability (“PL”) risk than ever before, and the risk management landscape is changing. There are unique challenges to managing PL risks and claims. Specifically, PL coverage requires proactive claim management and project coordination. As a result, design-build projects should involve significant collaboration amongst all of the parties involved in the project.
Claims Made Coverage Considerations
PL policies typically provide three types of coverage:
- Professional Liability covers defense and indemnity against claims arising out of acts or omissions of the insured in rendering a defined set of professional services –including construction management, project management, and design work in the design build context.
Read the court decisionRead the full story...Reprinted courtesy of
Eric M. Clarkson, Saxe Doernberger & Vita, P.C.Mr. Clarkson may be contacted at
EClarkson@sdvlaw.com
SAFETY Act Part II: Levels of Protection
June 21, 2024 —
Lorelie S. Masters, Kevin W. Jones & Charlotte Leszinske - Hunton Insurance Recovery BlogPart I of this series,
SAFETY Act is Powerful Protection Against Emerging Liabilities, addressed the benefits of obtaining SAFETY Act coverage, including:
- From a reputational perspective, SAFETY Act protection provides benefits even absent a security incident: it demonstrates that a knowledgeable federal agency has examined the relevant technology and determined that it is both safe and effective.
- SAFETY Act protection can benefit companies taking steps to enhance the security of their physical premises and operations, or their cybersecurity defenses, to reduce their potential liability and enhance their reputation.
- Other benefits include—depending on the level of protection—powerful liability protections including exclusive federal jurisdiction and choice of law for the venue where the incident occurred, caps on liability, prohibitions on punitive damages, and government contractor immunity.
This post will explain the levels of protection that a company can seek under the SAFETY Act.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth,
Kevin W. Jones, Hunton Andrews Kurth and
Charlotte Leszinske, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Jones may be contacted at kjones@HuntonAK.com
Ms. Leszinske may be contacted at cleszinske@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Keep It Simple: Summarize (Voluminous Evidence, That Is...)
October 02, 2023 —
Steve Swart - The Dispute Resolver"The most complex analyses grow beautifully simple as they become public objects.” Philip Rieff, Fellow Teachers (1973), quoted in JOHN BARTLETT, BARTLETT’S FAMILIAR QUOTATIONS 800 (Geoffrey O’Brien gen. ed., 18th ed. 2012)
In a recent ABA Forum on Construction Law Webinar, a panelist with substantial experience as an arbitrator explained that documents are the most important evidence in a construction dispute. Fact-finders, she said, focus on contemporaneous project records more than witness testimony to vet what happened.
But, even a small to mid-sized construction project can generate millions of pages of documents. That is particularly true when disputes involve loss of productivity, delay, acceleration, and disruption. The volume of records related to entitlement and damages (e.g., timesheets, accounting, equipment logs, schedule files, meeting minutes, etc.) can overwhelm and confuse — not to mention bore — the fact finder.
Read the court decisionRead the full story...Reprinted courtesy of
Steve Swart, Williams MullenMr. Swart may be contacted at
sswart@williamsmullen.com