Pulled from the Swamp: EPA Wetland Determination Now Judicially Reviewable
September 15, 2016 —
CDJ STAFFLandowners and developers bogged in an EPA wetland determination were recently thrown a life line when the United States Supreme Court determined The Army Corps of Engineer’s (Corps) “jurisdictional determinations” (JD) regarding wetland designations are reviewable by the court. United States Army Corps of Engineers v. Hawkes Co. Inc.
Under the Clean Water Act (CWA) landowners and developers who do not have the proper permits can face severe criminal and civil penalties for releasing any pollutant into “the waters of the United States.” Anybody stuck wading through the permitting process will tell you it is difficult, time consuming, expensive, and may eventually prohibit the intended use of the property. Furthermore, there is yet to be a consensus on the definition or scope of the term “waters of the US”. Consequently, a landowners or developers may never be certain whether a permit is necessary before conducting any activity that may discharge a pollutant into a “water of the United States”.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Minahan, Lamson, Dugan and Murray, LLPMr. Minahan may be contacted at
sminahan@ldmlaw.com
New York Appellate Court Applies Broad Duty to Defend to Property Damage Case
January 03, 2022 —
Craig Rokuson - Traub Lieberman Insurance Law BlogIn the recent case of New York Marine and Gen. Ins. Co. v. Eastman Cooke & Associates, 153 N.Y.S.3d 840, 841 (N.Y. App. Div. 1st Dept. 2021), New York’s first department affirmed a duty to defend under New York law. In the underlying action, the plaintiff alleged property damages due to prolonged construction work in a different unit of the subject property. The underlying plaintiff sued the owner of the subject property, which in turn sued Eastman Cooke, the general contractor at the premises. New York Marine denied coverage to Eastman Cooke, asserting that the underlying suit did not seek damages occurring during the New York Marine policy period, and commenced a declaratory judgment action.
The trial court held—and the First Department affirmed—that New York Marine has a duty to defend Eastman Cooke. Initially, the court found that the underlying suit alleged property damage as required for coverage, because there were allegations regarding loss of use of the property. The court also found that the underlying suit alleged damages occurring during the New York Marine policy period. Although the underlying complaint alleged that the underlying plaintiffs were reimbursed for damages occurring during the New York Marine policy period by another insurer, the court held that the evidence was that the payments only covered a certain part of the damages sought. Accordingly, because there was a reasonable possibility that some unreimbursed damages may fall within the New York Marine policy period.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Conversations with My Younger Self: 5 Things I Wish I Knew Then
July 24, 2023 —
Steve Swart - The Dispute ResolverI remember the morning I became a construction law attorney. It was on my birthday several years ago when a partner called me into his office and asked me to review the A107 contract form for a large firm client. The assignment gave me a new language to speak and contract provisions that I came slowly to understand.
I quickly moved into construction litigation and would soon learn that a "fragnet" was not the newest social media app but an important part of a delay claim. I read Spearin's biography and learned how to assess recoverable damages for different claims—costs to repair, replacement and betterment, increased financing/carrying costs, and the like.
It took a lot of blood, sweat, and tears to get to where I am now. Echoing Rod Stewart’s sentiment—“I wish that I knew then, what I do now, when I was younger”—here are five tips I’d pass along to the younger me or anyone who is beginning their career as a construction lawyer:
Read the court decisionRead the full story...Reprinted courtesy of
Steve Swart, Williams MullenMr. Swart may be contacted at
sswart@williamsmullen.com
Creative Avenue for Judgment Creditor to Collect a Judgment
October 27, 2016 —
David Adelstein – Florida Construction Legal UpdatesI have a judgment against another entity. Now what? I want to briefly talk about this “now what?” in the context of the recent decision in MYD Marine Distributor, Inc. v. International Paint, Ltd., 41 Fla. L. Weekly D2364a (Fla. 4th DCA 2016). Although this case is not a construction case, it poses an interesting issue for any entity that has a judgment entered against it (known as the judgment debtor) while it is contemporaneously the plaintiff and pursuing monetary damages in an unrelated case or cases. This case also presents an avenue for any judgment creditor to pursue in the event other post-judgment collection efforts are unsuccessful.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Florida’s Construction Defect Statute of Repose
August 24, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.Butler Weihmuller of Katz Craig LLP discussed Florida’s 10-year statute of repose law: “Under § 95.11(3)(c), the action must commence within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.”
However, Weihmuller explains that parties may disagree on the specific date For instance, in Busch v. Lennar Homes, LLC, Florida’s 5th DCA recently “reversed a trial court’s dismissal of a homeowner’s construction defect claim that was filed just beyond 10 years after the closing date on the property.” The previous decision had been based on the notion that the contract had been completed upon the date of closing. The 5th DCA declared that “a contract is not completed until both sides of a contract have been performed” and “pointed to the ‘inspection and punch-list clause’ of the contract.” The clause indicated that “[a]ny remaining items that Seller has agreed to correct will be corrected by Seller at Seller’s sole cost and expense prior to closing or at Seller’s option within a reasonable time after closing.” Since not all punch-list items had been completed prior to closing, the 5th DCA held that the contract had not been completed at closing, and therefore the statute of repose did not begin until the punch-items had been accomplished.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer’s Confession Of Judgment Through Post-Lawsuit Payment
June 25, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe recent opinion in the property insurance coverage dispute, Bryant v. Geovera Specialty Ins. Co., 44 Fla.L.Weekly D1232a (Fla. 4thDCA 2019), discusses the doctrine known as an insurer’s “confession of judgment.” In this case, an insured suffered water damage from a pipe leak. The insurer paid the insured $6,000 because of sublimits in the property insurance policy. There was a $5,000 sublimit for mold and a $1,000 sublimit for water leakage that occurs over a period of 14 days or more. The insured sued the insurer for covered water damage arguing that the sublimits did not apply.
After the lawsuit was filed, an agreed order was entered that stayed the case pending an appraisal. The appraisal award did not apply the $1,000 sublimit to the water damage from the pipe leak and segregated out damage for mold. (The insurer already paid the mold sublimit). The insurer ended up paying the appraisal award for the water damage caused by the pipe leak after deducting its pre-lawsuit sublimit payment. The insurer paid the award and did NOT challenge the application of the $1,000 sublimit in court, although it could have since coverage issues are decided by courts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Pending Sales of U.S. Existing Homes Rise Most in Four Years
July 01, 2014 —
Jeanna Smialek – BloombergThe number of contracts to purchase previously owned U.S. homes jumped in May by the most in more than four years, a sign the residential-real estate market is rebounding after a slow start to the year.
The pending home sales index climbed 6.1 percent, the biggest advance since April 2010, after a revised 0.5 percent increase in April, the National Association of Realtors said today in Washington. The gain exceeded the most optimistic estimate in a Bloomberg survey of economists, whose median forecast called for a 1.5 percent gain.
Housing demand is benefiting from cheaper borrowing costs, a stronger employment outlook and easier access to credit for some households. At the same time, higher prices and limited income gains are keeping the improvement in the residential real estate from becoming more broad-based.
Read the court decisionRead the full story...Reprinted courtesy of
Jeanna Smialek, BloombergMs. Smialek may be contacted at
jsmialek1@bloomberg.net
Second Circuit Affirms Win for General Contractor on No Damages for Delay Provision
September 02, 2024 —
Bill Wilson - Construction Law ZoneIn NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a subcontractor’s delay claim against a general contractor on a public project in New York state. The Court enforced a typical no-damages-for-delay provision to bar the subcontractor’s breach of contract claim. The no-damages-for-delay provision in the subcontract at issue provided:
NO DAMAGE FOR DELAY. Except as otherwise provided …, Subcontractor agrees that it shall have no Claim against Contractor for any loss or damage it may sustain through delay, disruption, suspension, stoppage, interference, interruption, compression, or acceleration of Subcontractor’s Work (‘Delay Damages’) caused or directed by Contractor for any reason, and that all such Claims shall be fully compensated for by Contractor’s granting Subcontractor such time extensions as it is entitled to as a result of any of the foregoing.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com