Connecticut Court Clarifies Construction Coverage
June 28, 2013 —
CDJ STAFFThe Connecticut Supreme Court has recently ruled on a case in which breach of contract and bad-faith claims were made against an insurer in an construction defect case. Joseph K. Scully of Day Pitney LLP discussed the case in a piece on Mondaq.
Mr. Scully noted that the background of the case was that Capstone Building was the general contractor and project developer of a student housing complex for the University of Connecticut. Unfortunately, the building had a variety of problems, some of which were violations of the building code. Mr. Scully noted that the building had “elevated carbon monoxide levels resulting from inadequate venting, improperly sized flues.” Capstone entered into mediation with the University of Connecticut. Capstone’s insurer, the American Motorists Insurance Company (AMICO), declined involvement in the participation. Afterward, Capstone sued AMICO. The issues the court covered involved the insurance on this project.
The court addressed three questions. The first was “whether damage to a construction project caused by construction defects and faulty workmanship may constitute ‘property damage’ resulting from an ‘occurrence.’” The court concluded that it could “only if it involved physical injury or loss of use of ‘nondefective property.’”
The second question dealt with whether insurers were obligated to investigate insurance claims. The court, “agreeing with the majority of jurisdictions,” did not find “a cause of action based solely on an insurer’s failure to investigate a claim.” Under the terms of the contract, it was up to AMICO to decide if it was going to investigate the claim.
Thirdly, the court examined whether “an insured is entitled to recover the full amount of a pre-suit settlement involving both covered and noncovered claims after an insurer wrongfully disclaims coverage.” The court concluded that the limits are that the settlement be reasonable, the policy limit, and the covered claims.
Mr. Scully concludes that the decision will limit “the scope of coverage for construction defect claims” and “also imposes reasonable requirements on an insured to allocate a settlement between covered and noncovered claims.
Read the court decisionRead the full story...Reprinted courtesy of
University of Tennessee’s New Humanities Building Construction Set to Begin
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFConstruction preparation of the Tennessee Volunteer’s $30.5 million new humanities building has begun, according to The Tennessean. The 80,000 square-foot facility will become the largest building on the university’s campus, and will feature 23 classrooms, 18 labs, 11 collaborative study areas, 56 offices, 20 adjunct faculty workrooms as well as an outdoor theater and courtyard.
“This is a significant milestone in the history of the college,” President Jerry Faulkner told The Tennessean. “This building has been on our wish list for about 12 years in terms of wanting to have this facility available, so for the first time our humanities division is going to have a home of its own.”
Read the court decisionRead the full story...Reprinted courtesy of
Builder Waits too Long to Dispute Contract in Construction Defect Claim
May 10, 2012 —
CDJ STAFFThe Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.
The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.
The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.
In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.
The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.
A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”
Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Index Demonstrates Increase in Builders’ Sentiment
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFThe National Association of Home Builders’ Eye on Housing reported that “[b]uilders’ sentiment jumped four points to 59, the highest level since November 2005, according to the September NAHB/Wells Fargo Housing Market Index.” Furthermore, builders mentioned “renewed interest by potential home buyers and higher traffic in their models and through their phone calls.”
Eye on Housing also reported that the “inventory of new home for sale has increased to over 200,000.” While still lower than the 300,000 typical in 1990s and early 2000s, “the steady increase has provided a better selection for consumers.”
Read the court decisionRead the full story...Reprinted courtesy of
Bought a New Vacation Home? I’m So Sorry
August 13, 2014 —
Ben Steverman – BloombergSummer is a time to relax, kick back and make dumb financial decisions.
That's how financial advisers see it, when their clients get a hankering for a summer house after returning from an idyllic trip. Sales of vacation homes in the U.S. rose 30 percent last year to 717,000, the National Association of Realtors estimates, based on a survey. But owning a second home is often far more expensive and stressful than buyers, or dreamers, imagine.
Start with the dark side to beautiful weather. Sun, salt and wind are cruel to houses. One owner in Virginia Beach was shocked to learn he'd need new windows every six years. That alone wiped out an entire summer of rental income, says David O’Brien, his adviser. Storms take out roofs, docks and sea walls, replaceable only at exorbitant rates. "These properties are for family memories, not capital appreciation," O'Brien says sunnily.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Steverman, BloombergMr. Steverman may be contacted at
bsteverman@bloomberg.net
Construction Worker Dies after Building Collapse
November 18, 2011 —
CDJ STAFFA Bronx construction worker died when the pillars gave way in the basement where he was working. The two-story commercial building collapsed, burying Mr. Kebbeh under about six feet of rubble. The New York Times reports that firefighters dug him out with their bare hands. Mr. Kebbeh was taken to Jacobi Medical Center where he died. Two other construction workers escaped unharmed.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
UCF Sues Architects and Contractors Over Stadium Construction Defects
October 19, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.The University of Central Florida (UCF) filed suit over alleged construction defects of their 45,000-seat arena including the claim of “premature wear of the steel,” spokesman Chad Binette stated, according to the Orlando Sentinel.
Bid documents suggest that rust may be an issue. UCF recently sought contractors for “Stadium Emergency Rust Repairs.” The Orlando Sentinel reported that the university stated “the word ‘emergency’ reflects deadlines for the football season instead of safety concerns.” Other documents also claimed ongoing rust remediation.
The UCF stadium had earned the nickname “Bounce House” from the arena “subtly swaying as fans jumped together to the song ‘Kernkraft 400’ by Zombie Nation. UCF spent hundreds of thousands of dollars in 2008 stiffening the underpinnings of the stadium by bolting additional steel to about 160 beams,” according to the Orlando Sentinel. Officials claim that the stadium was never unsafe.
Read the court decisionRead the full story...Reprinted courtesy of
Liquidated Damages Clause Not Enforced
October 02, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA liquidated-damages clause was not enforced in a recent case before the Georgia Court of Appeals. The clause did not contain standard provisions that would normally allow a trial court to enforce the clause as written. As a result, the trial court looked beyond the contract to determine whether the City satisfied the requirements for enforcement of the liquidated-damages clause. Below are the relevant excerpts.
City of Brookhaven v. Multiplex, LLC, A23A0843, 2023 WL 4779591 (Ga. Ct. App. July 27, 2023)
Here, the Contract provides for “Liquidated Damages at the rate of $1,000.00 per calendar day” in the last paragraph of the Scope of Work addendum. The Contract lacks, however, any language indicating that the liquidated damages were not intended to be a penalty. See Fuqua Const. Co. v. Pillar Dev., Inc., 293 Ga. App. 462, 466, 667 S.E.2d 633 (2008) (rejecting use of parol evidence where the parties “explicitly agreed” in “unambiguous contract language” that the liquidated damages were not a penalty). Absent such language, the court can look to parol evidence in the record to determine the effect the provision was intended to have. See J.P. Carey Enterprises, 361 Ga. App. at 391-392 (1) (b), 864 S.E.2d 588 (looking to “extrinsic evidence” such as emails, documents, and deposition testimony to determine whether the damages provision at issue was a penalty); see also Gwinnett Clinic, Ltd. v. Boaten, 340 Ga. App. 598, 602-603, 798 S.E.2d 110 (2017) (“Shah’s testimony also suggested that one purpose of the liquidated damages provision was to deter employees from breaching the agreement”).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com