Construction Costs Must Be Reasonable
May 17, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to proving a construction cost, particularly a cost in dispute, the cost must be REASONABLE. Costs subject to claims must be reasonably incurred and the party incurring the costs must show the costs are reasonable.
An example of the burden falling on the contractor to prove the reasonableness of costs is found in government contracting.
“[T]here is no presumption that a [government] contractor is entitled to reimbursement ‘simply because it incurred…costs.’” Kellogg Brown & Root Services, Inc. v. Secretary of Army, 973 F.3d 1366, 1371 (Fed. Cir. 2020) (citation omitted). Stated differently, a federal contractor is not entitled to a presumption of reasonableness just because it incurs costs. Id.
In government contracting, the Federal Acquisition Regulations (known as “FAR”) puts the burden of reasonableness on the contractor that incurred the costs. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
City of Sacramento Approves Kings NBA Financing Plan
May 21, 2014 —
Beverley BevenFlorez-CDJ STAFFSacramento, California’s city council recently approved a financing plan that will enable the construction of the $477 million downtown arena project to move forward, reported KNOE News. Sacramento will now be responsible for a $223 million subsidy, and “the Kings would contribute $254 million to construct the arena and develop surrounding land with a hotel, office tower and shopping.”
“Kings President Chris Granger called it a historic day for the team and Sacramento region, saying the arena would serve as a hub for economic development,” according to KNOE News. “The project would bring 11,000 construction jobs and 4,000 permanent jobs, [Granger] said.”
Read the court decisionRead the full story...Reprinted courtesy of
Ahead of the Storm: Preparing for Dorian
September 16, 2019 —
Adam P. Handfinger, Stephen H. Reisman & Gary M. Stein - Peckar & Abramson, P.C.While Hurricane Dorian churns in the Atlantic with its sights currently set on the east coast of Florida, storm preparations should be well underway. As you are busy organizing efforts to secure your job sites, we at Peckar & Abramson offer some quick reminders that may prove helpful:
- Review your contracts, particularly the force majeure provisions, and be sure to comply with applicable notice requirements
- Even if not expressly required at this time, consider providing written notice to project owners that their projects are being prepared for a potential hurricane or tropical storm and that the productivity and progress of the work will be affected, with the actual time and cost impact to be determined after the event.
- Consult your hurricane plan (which is often a contract exhibit) and confirm compliance with all specified safety, security and protection measures.
- Provide written notice to your subcontractors and suppliers of the actions they are required to take to secure and protect their portions of the work and the timetable for completion of their storm preparations.
Reprinted courtesy of Peckar & Abramson, PC attorneys
Adam P. Handfinger,
Stephen H. Reisman and
Gary M. Stein
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Mr. Reisman may be contacted at sreisman@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
US Homes Face Costly Retrofits for Induction Stoves, EV Chargers
May 20, 2024 —
Kendra Pierre-Louis - BloombergBuyers of new homes in the US may find themselves saddled with electrical systems better suited to the 20th century than the 21st.
The International Code Council, which sets model construction standards for new homes, was expected to include building electrification measures in its 2024 energy code on March 20. But following appeals lodged by industry groups, the ICC board moved the measures to the code’s appendices, effectively making them optional, as first reported by the Huffington Post.
If new homes aren’t wired for increasing power needs from electric appliances and car chargers, it will bump the effort and cost of making such upgrades onto homeowners — a deterrent to going electric. Energy efficiency advocates say this could slow the pace of the energy transition, costing both jobs and the planet.
Read the court decisionRead the full story...Reprinted courtesy of
Kendra Pierre-Louis, Bloomberg
Las Vegas Sphere Lawsuits Roll On in Nevada Courtrooms
October 02, 2023 —
Richard Korman - Engineering News-RecordBig concerts have yet to start at Las Vegas’ distinctive new ball-shaped entertainment venue, but the legal noise over its construction has been heard in Clark County courtrooms for more than two years.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Is the Issuance of a City Use Permit Referable? Not When It Is an Administrative Act
January 10, 2018 —
Adam E. Lang - Real Estate Litigation BlogArizona’s Constitution gives electors in cities, towns, and counties the ability to refer legislation that was enacted by their local elected officials to the ballot for popular vote. Ariz. Const. art. IV, Pt. 1 § 1(8). But only legislative acts are referable; administrative acts are not. In general, a legislative act makes new law and creates policy, is permanent in nature, and is generally applied. On the other hand, an administrative act is one that executes and implements a law already in place. Wennerstrom v. City of Mesa, 169 Ariz. 485, 489-90, 821 P.2d 146, 150-51 (1991).
For more than fifty years, Arizona courts have been clear: zoning and rezoning ordinances are legislative acts and therefore referable to popular vote. City of Phoenix v. Fehlner, 90 Ariz. 13, 17, 363 P.2d 607, 609 (1961) (holding that “what constitutes an appropriate zone is primarily for the legislature”); Fritz v. City of Kingman, 191 Ariz 432, 432, 957 P.2d 337, 337 (1998) (noting “we reaffirm our view that zoning decisions are legislative matters subject to referendum”); Pioneer Trust Co. of Arizona v. Pima Cty., 168 Ariz. 61, 64–65, 811 P.2d 22, 25–26 (1991) (holding “that, in Arizona, zoning decisions are legislative acts subject to referendum” and that even a “conditional approval of . . . rezoning was a legislative act”); Cottonwood Dev. v. Foothills Area Coal. of Tucson, Inc., 134 Ariz. 46, 653 P.2d 694 (1982) (analyzing whether zoning referendum complied with statutory requirements); Wait v. City of Scottsdale, 127 Ariz. 107, 108, 618 P.2d 601, 602 (1980) (noting “that the enactment and amendment of zoning ordinances constitute legislative action”); City of Phoenix v. Oglesby, 112 Ariz. 64, 65, 537 P.2d 934, 935 (1975) (“The matter of zoning is appropriately one for the legislative branch of government.”); Queen Creek Land & Cattle Corp. v. Yavapai Cty. Bd. of Sup’rs, 108 Ariz. 449, 452, 501 P.2d 391, 394 (1972) (denying an attempt to enjoin referendum on county’s zoning decision).
Read the court decisionRead the full story...Reprinted courtesy of
Adam E. Lang, Snell & WilmerMr. Lang may be contacted at
alang@swlaw.com
Fewer NYC Construction Deaths as Safety Law Awaits Governor's Signature
July 25, 2022 —
Richard Korman - Engineering News-RecordThe hoped-for progress in New York City construction safety is coming too late for laborer Jose Fortina Armenta Hernandez. At 8:37 a.m. on May 27, 2021, while jackhammering a roof section on a Brooklyn building, the section on which Armenta stood gave way and he fell 60 ft. When last year his family sent his body from New York City to Mexico to be buried, they used a GoFundMe page to raise money for the laborer's funeral.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Understand Agreements in Hold Harmless and Indemnity Provisions
June 06, 2022 —
Jeffrey Cavignac - Construction ExecutiveOne of the most important provisions in a construction contract is the indemnity provision. An indemnity provision, which usually includes a requirement to hold harmless and defend another party, is included in nearly all construction contracts. Generally speaking, the upstream party (a general contractor or owner, for example) is attempting to shift risk to a downstream party (the general contractor or a subcontractor). In simple terms, subject to certain parameters, the downstream party is agreeing to be responsible for the upstream parties’ mistakes.
DEFINING INDEMNIFICATION
Insurance brokers focused on development and construction businesses get asked frequently: “If we sign this, are we insured?” It would be great if this could be answered “yes” or “no,” but life is rarely that straightforward. To understand whether a specific indemnification is insurable, we have to drill down on the actual provision. Let’s look at a typical indemnification below:
“To the fullest extent permitted by law the Contractor shall indemnify, defend and hold harmless the owner, architect, architect’s consultants and agents and employees of any of them from and against any claims, damages, losses and expenses, including but not limited to attorneys’ fees, arising out of or resulting from performance of the work whether caused in whole or in part by the contractor, a subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable.”
Reprinted courtesy of
Jeffrey Cavignac, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of