Michael L. DeBona - The Subrogation StrategistSeven months ago, the Florida Supreme Court declined to adopt Daubert as the standard for admitting expert testimony in Florida state courts. In DeLisle v. Crane Co., 258 So. 3d 1219 (2018), the court reaffirmed that “Frye, not Daubert, is the appropriate test in Florida.” On May 23, 2019, however, Florida’s high court did an about-face. In In Re: Amendment to the Florida Evidence Code, No. SC19-107, the Florida Supreme Court overruled its decision in DeLisle and declared that Florida will now apply the Daubert standard to determine whether scientific evidence is admissible.
The Daubert standard comes from the case of Daubert v. Merrell Dow Pharm., Inc., 509 U.S. 579 (1993), which held that the longstanding Frye test[1] for admitting expert testimony was superseded by Rule 702 of the Federal Rules of Evidence. Daubert instructed that federal judges should act as “gatekeepers” to ensure expert testimony is rooted in scientifically valid principles and that those principles are properly applied to the facts at issue. In determining whether scientific evidence should be admitted, Daubert sets forth several factors to consider: the testability of the theory or technique; the peer review and publication of the theory or technique; the error rate for the technique; the standards controlling the technique’s operation; and the general acceptance of the theory or technique.[2] The Daubert standard is generally considered a more onerous test than Frye, precluding expert testimony that might otherwise go to the jury under Frye.[3] Whereas Frye is a single factor test that applies only to new or novel science, Daubert is a multifactor test that applies to all expert testimony.
Since Daubert, a growing number of states have moved away from the Frye test in favor of the Daubert standard; it is now followed by a majority of jurisdictions in the country. In 2013, the Florida State legislature attempted to move Florida in this direction by amending the Florida Evidence Code to codify the Daubert standard. But because the Florida Supreme Court is vested with the power to make procedural rules and it was unclear whether the Daubert standard was a procedural or substantive rule, it was uncertain whether the 2013 Daubert amendments were controlling law. Then in 2017, in In Re: Amendment to the Florida Evidence Code, No. SC16-181, the Florida Supreme Court expressly declined adopting the Daubert amendments to the extent they were procedural. This decision signaled that, if faced with the Daubert standard on appeal from a litigated case, the Florida Supreme Court would reaffirm that Frye – not Daubert – controlled the admissibility of expert testimony in Florida state courts.
Read the court decisionRead the full story...Reprinted courtesy of
Michael L. DeBona, White and Williams LLPMr. DeBona may be contacted at
debonam@whiteandwilliams.com
Colorado Senate Bill 13-052 Dies in Committee
May 10, 2013 —
David M. McLainOn April 17, 2013, the Colorado Senate Judiciary Committee voted, along party lines, to postpone indefinitely SB 52. Here is a link to the Denver Business Journal's story regarding the bill and its untimely demise: "Lawmakers kill lawsuit limits on condo defects."
Unfortunately, it will be at least another year before the legislature will have the ability to provide some much needed relief to the Colorado construction industry.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainMr. McLain can be contacted at
mclain@hhmrlaw.com
Is The Enforceability Of A No-Damage-For-Delay Provision Inappropriate For Summary Judgment
February 24, 2020 —
David Adelstein - Florida Construction Legal UpdatesIs the enforceability of a no-damage-for-delay provision inappropriate for resolution on a summary judgment? The recent decision in U.S. f/u/b/o Kingston Environmental Services, Inc. v. David Boland, Inc., 2019 WL 6178676 (D. Hawaii 2019), dealing with Florida law, suggests that it is inappropriate for a summary judgment resolution, particularly when there is a right to a jury trial.
In this case, a prime contractor was hired on a federal construction project in Hawaii. The prime contractor hired a subcontractor and the subcontractor sued the prime contractor and its surety under the Miller Act. Of interest, the subcontractor was seeking to recover for the costs it incurred due to construction delays. The prime contractor moved for summary judgment as to the no-damage-for-delay provision in the subcontract. The no-damages-for-delay provision read as follows (and it is a well-written no-damage-for-delay provision):
The Subcontractor expressly agrees that the Contractor shall not be liable to the Subcontractor for any damages or additional costs, whether foreseeable or unforeseeable, resulting in whole or in part from a delay, hindrance, suspension, or acceleration of the commencement or execution of the Work, caused in whole or in part by the acts or omissions, whether negligent or not, of the Contractor including other subcontractors or material suppliers to the Project, its agents, employees, or third parties acting on behalf of the Contractor. The Subcontractor’s sole remedy for any such delay, hindrance, suspension, or acceleration shall be a noncompensable time extension.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Coverage Denied Where Occurrence Takes Place Outside Coverage Territory
December 11, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe court held there was no coverage for construction defect claims that occurred outside the coverage territory. Foremost Signature Ins. Co. v. Silverboys, 2018 U.S. Dist. LEXIS 154524 (S.D. Fla. Sept. 11, 2018).
Solo Design, LLC, a Miami-based design company, entered into a contract with Silverboys, LLC (Owner) to provide interior design services in conjunction with the renovation of the Owner's vacation home in the Bahamas. Solo retained Whittingham, a Bahamian architect, as a subcontractor to serve as project manager.
Owner sued Solo, Whittingham and others in Florida for breach of contract, fraud, conversion and negligence when the project did not go as planned. The underlying complaint alleged intentional misconduct, lying about qualifications and the progress of the project, submitting false invoices, requesting money for services that were not performed, etc. Owner alleged that the damages included: (a) the cost to repair substandard work; (b) loss of use of the home due to delay; and (c) overcharges for furnishings, contract fees, and expenses. The underlying complaint set forth only a few instances of physical injury to the home, including mold on the ceiling in the master shower, faulty millwork on the children's playroom bookshelf, and a defective front door and resysta facade.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Appraisal May Include Cause of Loss Issues
March 21, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court determined that an appraisal can include causation issues when determining the amount of loss. B&D Inv. Grp., LLC v. Mid-Century Ins. Co., 2021 U.S. Dist. LEXIS 246853 (N.D. Ill. Dec. 28, 2021).
B&D commercial building was damaged by hail. B&D submitted a claim to Mid-Century, but the parties disagreed as to the damage. Mid-Century found there was hail damage to metal vents on the roof and estimated the repair costs to be $4,271.95. Mid-Century found no hail damage to the roof itself. B&D disagreed and insisted that there was additional damage to the property, specifically the roof.
B&D requested an appraisal, but Mid-Century denied the request. Mid-Century found that the condition of the roof was due to wear and tear and therefore constituted an excluded cause under the policy. B&D filed suit seeking a declaratory judgment compelling the parties to proceed with an appraisal.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Gloria Gaynor Sues Contractor over Defective Deck Construction
October 22, 2013 —
CDJ STAFFGloria Gaynor, known for her 1978 disco hit, “I Will Survive” is suing the firm that renovated her second-floor deck, alleging that the work lead to water intrusion into her home. Ms. Gaynor also accuses the company of consumer fraud, alleging that Diaz Landscape Design & Tree Service LLC lacked registration as a home improvement contractor and failed to obtain a building permit for the structure.
Ms. Gaynor paid about $38,000 for the replacement of her deck and other renovations to her property in 2007. Subsequently, the singer noticed “ponding of water on the deck, water damage to wood sills and supports, and the formation of mold,” according to the lawsuit. Diaz Landscape attempted repairs, but “the problems persisted and continue to persist causing further damage.”
The lawsuit claims that the cost of replacing the defective deck construction would cost about $120,000.
Read the court decisionRead the full story...Reprinted courtesy of
Indemnity Provision Prevails Over "Other Insurance" Clause
December 06, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Second Circuit predicted that the New York appellate courts would find the contractual indemnity provision prevailed over the application of an "other insurance" provisions. Cent. Sur. Co. v. Metro. Transit Auth., 2021 U.S. App. LEXIS 29860 (2nd Cir. Oct. 5,2021).
Long Island Railroad (LIRR) contracted with general contractor Rukh Enterprises, Inc. to complete a railroad bridge lead paint removal and repainting project on Metropolitan Transit Authority property. Rukh hired subcontractor, East Coast Painting & Maintenance to complete certain lead-related work on the project.
An employee of East Coast suffered an injury while working on the project. The employee sued LIRR and Rukh. A settlement in the underlying case was reached, implicating three of four policies - Admiral (primary for LIRR), Arch (CGL for Rukh), and Harleysville (primary for East Coast). Century Surety (excess liability for Rukh) did not contribute to the settlement and disclaimed all coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Congratulations to BWB&O’s Las Vegas Team on Obtaining Summary Judgment for the Firm’s Landowner Client!
August 03, 2022 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce Partner Anthony Garasi, Senior Associate Madeline Arcellana, and Associate Laura Rios successfully won a Motion for Summary Judgment (“MSJ”), while also defeating two competing MSJs filed by Plaintiff, and ultimately obtaining a full dismissal of their landowner client against claims of premises liability.
Plaintiff, who sued both BWB&O’s client (the landowner) and its tenant, alleged injury when he slipped and fell, while utilizing a temporary wooden board as a ramp that was placed on the subject property by the tenant, who was occupying the property subject to a lease-to-own arrangement with BWB&O’s client.
In this Motion practice, the BWB&O team successfully obtained a ruling from the Court to find that BWB&O’s client had effectively contracted to delegate its maintenance responsibilities to its tenant, and also that the tenant owed BWB&O’s client full indemnity for Plaintiff’s alleged losses.
Read the court decisionRead the full story...Reprinted courtesy of