Does Arbitration Apply to Contemporaneously Executed Contracts (When One of the Contracts Does Not Have an Arbitration Provision)?
January 10, 2018 —
David Adelstein - Florida Construction Legal UpdatesBinding arbitration is an alternative to litigation. Instead of having your dispute decided by a judge and/or jury, it is decided by an arbitrator through an arbitration process. Arbitration, however, is a creature of contract, meaning there needs to be a contractual arbitration provision requiring the parties to arbitrate, and not litigate, their dispute. Just like litigation, there are pros and cons to the arbitration process, oftentimes dictated by the specific facts and legal issues in the case.
What happens when a person executes two (or more) contemporaneous contracts, one with an arbitration provision and one without? Are the parties required to arbitrate the dispute arising out of the contract that does not contain the arbitration provision?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Denial of Coverage For Bodily Injury After Policy Period Does Not Violate Public Policy
May 12, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Rhode Island Supreme Court agreed that the insurer had no coverage obligations for bodily injury occurring after the policy had been canceled. Hoesen v. Lloyd's of London, 2016 R.I. LEXIS 41 (R.I. March 24, 2016).
The plaintiff, Mark Van Hoesen, was seriously injured on July 23, 2012, when he fell from a deck of his house. He sued his contractor, Brian Leonard, alleging that the deck had been negligently constructed. Lloyd's, Leonard's insurer, was later named as a defendant. Lloyd's admitted it issued the policy to Leonard, but it was cancelled on August 29, 2007. Even if it had not been canceled, the policy had expired long before the injuries alleged in plaintiff's complaint occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
World Cup May Pull Out of Brazil because of Construction Delays
January 28, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in October of last year, CNN reported that a judge suspended construction at one of the stadiums being built for this summer’s World Cup in Brazil. The judge stated that the dangers for construction workers included "being buried, run over, falling from heights and being hit by material, among other serious risks,” according to CNN.
Recently, the Los Angeles Times reported that FIFA is threatening to pull out of Brazil because of construction delays: “We cannot organize a match without a stadium,” Jerome Valcke, FIFA’s secretary general, as quoted in the Los Angeles Times. “This has reached a critical point.”
The deadline for completion of the 12 World Cup stadiums was January 1st, but various delays—including “fatal construction accidents at stadiums in Sao Paulo, Brasilia, and Manaus” as well as worker walk offs over pay—forced FIFA to “relax” the deadline.
Read the full story at CNN...
Read the full story at the Los Angeles Times... Read the court decisionRead the full story...Reprinted courtesy of
Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
District Court Allows DBE False Claims Act Case to Proceed
February 23, 2017 —
Wally Zimolong – Supplemental ConditionsLast week, I posted about how whistleblowers continue to receive large settlements related to DBE fraud. A somewhat recent case from the federal court in Maryland shows how whistleblowers are ferreting out DBE fraud on construction projects receiving any form of federal funding.
The Case
The case involves a bridge painting project in Maryland that was let by the Maryland State Highway Administration. The contract required the prime contractor to meet a 15% DBE participation goal. The prime contractor submitted a bid stating it would have 15.12% DBE participation. After it was awarded the contract, the prime contractor – as is typical – submitted additional forms certifying to the MSHA that 15.12% of its contract price would be performed by a DBE firm. The prime contractor indicated that one DBE subcontractor, Northeast Work and Safety Boats, LLC (“NWSB”), would perform the 15.12% of the work.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Is There a Conflict of Interest When a CD Defense Attorney Becomes Coverage Counsel Post-Litigation?
September 01, 2011 —
Chad Johnson of Higgins, Hopkins, McLain & Roswell, LLCIn Weitz Co., LLC v. Ohio Cas. Ins. Co., the U.S. District Court for the District of Colorado was asked to rule on a motion to disqualify counsel in an insurance coverage action. 11-CV-00694-REB-BNB, 2011 WL 2535040 (D. Colo. June 27, 2011). Motions to disqualify counsel are viewed with suspicion, as courts “must guard against the possibility that disqualification is sought to ‘secure a tactical advantage in the proceedings.’” Id. at *2 (citing Religious Technology Center v. F.A.C.T. Net, Inc., 945 F. Supp. 1470, 1473 (D. Colo. 1996).
Weitz Company, LLC (“Weitz”) is a general contractor and defendant in an underlying construction defect suit which had concluded before the action bringing rise to this order. In the underlying action, Weitz made third-party claims against subcontractors, including NPW Contracting (“NPW”). Weitz was listed as an additional insured under NPW’s policies with both Ohio Casualty Insurance Company and Mountain States Mutual Casualty Company (collectively “the Carriers”). The Carriers accepted Weitz’s tender of defense under a reservation of rights. However, neither insurance carrier actually contributed to Weitz’s defense costs in the underlying action. At the conclusion of the construction defect action, the parties unsuccessfully attempted to apportion the attorney’s fees and costs. Eventually, Weitz brought suit against the recalcitrant carriers. The Lottner firm, which had previously represented Weitz in the underlying construction defect action, continued to represent Weitz in this coverage action.
Read the full story…
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. Johnson can be contacted at johnson@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Wendel Rosen’s Construction Practice Group Welcomes Quinlan Tom
January 06, 2016 —
Garret Murai – California Construction Law BlogThere’s been more cheer than usual at Wendel Rosen’s Construction Practice Group this holiday season.
Earlier this month, Quinlan Tom, a construction and business attorney, joined us from McInerney & Dillon, a venerable and well-respected construction boutique firm (we know a lot of folks there) with local roots like us in Oakland, California. We’ve all known Quinlan for a while, so when he decided to join our band of merry legal practitioners, we were quite thrilled.
Being lawyers though, and better at asking than answering questions, we decided to pose a few questions to Quinlan:
Q. So, you’ve just been sworn to tell the truth, the whole truth, and nothing but the truth, under penalty of perjury. So, tell us about your practice.
A. Let me just start with it’s quite an honor to appear in your blog; I’ve been a reader for a while (in secret of course before I got to Wendel Rosen). I’m also excited to join you and the other members of Wendel Rosen’s Construction Practice Group; as you mention, I’ve known each of you professionally for quite some time and respect each of you tremendously.
I started as a construction litigator right out of law school. I completed three years of mechanical engineering at UC Davis and put that on my resume when I was looking for a job after law school. (In addition, my dad retired after 40 years in the trenches as a union electrician). McInerney & Dillon (“M&D”) and a couple of other firms found that interesting and I ended up starting with M&D. I did find that my engineering studies helped with my acclimation to construction disputes. While I never pretend to be an engineer, it has provided me with a foundation of how the construction process works and how the projects are designed. 26 years later, I continue to enjoy counseling my clients in their construction disputes/issues and still find each construction project I am involved with fascinating.
I have tried, arbitrated and litigated cases for 26 years, from the United States District Court to the California Superior Court and the California Office of Administrative Hearings. I have argued cases before the Ninth Circuit Court of Appeals and the California Court of Appeal. I counsel my clients into hopefully making the best business decisions available melding the knowledge I have gleaned from my litigation experience with their financial and personal goals.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Contractor Prevailing Against Subcontractor On Common Law Indemnity Claim
June 29, 2020 —
David Adelstein - Florida Construction Legal UpdatesCommon law indemnity is not an easy claim to prove as the one seeking common law indemnity MUST be without fault:
Indemnity is a right which inures to one who discharges a duty owed by him, but which, as between himself and another, should have been discharged by the other and is allowable only where the whole fault is in the one against whom indemnity is sought. It shifts the entire loss from one who, although without active negligence or fault, has been obligated to pay, because of some vicarious, constructive, derivative, or technical liability, to another who should bear the costs because it was the latter’s wrongdoing for which the former is held liable.
Brother’s Painting & Pressure Cleaning Corp. v. Curry-Dixon Construction, LLC, 45 Fla. L. Weekly D259b (Fla. 3d DCA 2020) quoting Houdaille Industries, Inc. v. Edwards, 374 So.2d 490, 492-93 (Fla. 1979).
Not only must the one seeking common law indemnity be without fault, but there also needs to be a special relationship between the parties (indemnitee and common law indemnitor) for common law indemnification to exist. Brother’s Painting & Pressure Cleaning Corp., supra (citation omitted). A special relationship has been found to exist between a general contractor and its subcontractors. Id. at n.2.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at