Payment Bond Claim Notice Requires More than Mailing
June 18, 2019 —
Christopher G. Hill - Construction Law MusingsIt’s been a while since I posted something new relating to Virginia’s “Little Miller Act” and its various notice requirements for a subcontractor to make a payment bond claim.
I have posted on the basics of a Virginia payment bond claim previously here at Musings. One of these basics is the 90 day notice requirement for suppliers or second tier subcontractors with no direct contractual relationship to the general contractor. A recent case from the Norfolk, Virginia Circuit Court examined when notice is “given” under the Little Miller Act.
In R T Atkinson Building Corp v Archer Western Construction, LLC the Court looked at the question of whether mailing of the notice of claim is enough to constitute notice being “given” in a manner that would satisfy the statutory requirements. In that case, the supplier mailed the notice within the 90 day window, but the defendant argued on summary judgment that it did not receive the notice until 2 days after the 90 day window had closed. In support of this contention, the defendant provided tracking information showing delivery by the USPS on the non-compliant date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Judgment for Insurer Reversed Due to Failure to Establish Depreciation
August 01, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court erred in placing the burden on the policyholder to establish depreciation in determining the actual cash value of the loss. SFR Serv., LLC v. Tower Hill Prime Ins. Co., 2023 Fla. App. LEXIS 3570 (Fla. Ct. App. May 26, 2023).
The insureds' roof was damaged by Hurricane Irma. They submitted their claim to their insurer, Tower Hill. The cost of repair was assessed at $7,726.94, below the amount of the deductible. Therefore, there was no recovery under the policy. The insureds assigned their claim to SFR Services, LLC, their roofing contractor. SFR submitted a claim to Tower Hill for $162,083.84. Tower Hill refused to pay and SFR sued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pennsylvania Supreme Court’s Ruling On Certificates Of Merit And “Gist Of Action” May Make It More Difficult For An Architect Or Engineer To Seek An Early Dismissal
January 07, 2015 —
Jerrold P. Anders and Michael W. Jervis - White and Williams LLPIn Bruno v. Erie Ins. Co., the Pennsylvania Supreme Court clarified the gist of the action doctrine that distinguishes between tort and contract claims. In doing this, the Court also ruled that a Certificate of Merit in a professional liability claim is necessary only if the plaintiff is in a direct client relationship with the licensed professional. This clarification of the Certificate of Merit requirement may limit the ability of architects and engineers to obtain an early dismissal in lawsuits.
Bruno v. Erie Ins. Co. involves a common scenario. The Brunos filed a claim with their homeowners’ insurer after discovering mold in their home during remodeling. The policy included an endorsement providing coverage for mold. As part of the claim adjustment, Erie hired an engineer to inspect the mold and to provide an opinion on its severity to determine the extent of remediation required. The engineer hired by Erie reported to Mr. Bruno that the mold was harmless, that concern over health problems due to mold was merely a “media frenzy,” and that the Brunos should continue with their renovations.
Reprinted courtesy of
Jerrold P. Anders, White and Williams LLP and
Michael W. Jervis, White and Williams LLP
Mr. Anders may be contacted at andersj@whiteandwilliams.com
Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeal Shines Light on Collusive Settlement Agreements
October 21, 2015 —
Kristian B. Moriarty & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Diamond v. Reshko, (filed 8/20/2015, No. A139251) the California Court of Appeal, First District, held that a defendant was entitled to introduce evidence at trial reflecting amounts paid by co-defendants in settlement of a plaintiff’s claim.
Plaintiff, Christine Diamond, was injured during an automobile accident that occurred while she was a passenger in a taxi driven by Amir Mansouri. Christine, and her husband Andrew, filed suit against Mr. Mansouri, the Yellow Cab Collective (“Yellow Cab”), and the driver of the vehicle that collided with the taxi, Serge Reshko. Before trial, Mansouri and the Yellow Cab Collective settled with Plaintiffs, but agreed to appear and participate as defendants at the jury trial of the action. Mansouri and Yellow Cab paid a total of $400,000 to Plaintiffs in settlement.
Reshko filed a pre-trial motion seeking an order permitting Reshko to admit evidence of the settlement between Plaintiffs and the other defendants. The trial court refused to rule on the motion before trial. Ultimately, evidence of the settlement between Plaintiffs, Mansouri and Yellow Cab was excluded during trial. The jury returned a verdict in favor of Plaintiffs in the total amount of $745,778, finding Mansouri 40 percent at fault, and Reshko 60 percent at fault. The Trial Court entered judgment against Reshko in the sum of $406,698.
Reshko appealed the judgment. The First District Court of Appeal reversed, holding that evidence of the settlement should have been admitted at trial because the settling defendant’s position should be revealed to the court and jury to avoid committing a fraud on the court, and in order to permit the trier of fact to properly weigh the settling defendant’s testimony.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
United States Supreme Court Grants Certiorari in EEOC Subpoena Case
March 29, 2017 —
Jeffrey M. Daitz & Rashmee Sinha - Peckar & Abramson, P.C.On September 29, 2016, the United States Supreme Court granted certiorari in McLane Co. Inc. v. EEOC, case number 15-1248, a case that asks the Court to resolve a split in the Circuit Courts of Appeals on the proper standard of review applied to a district court decision to quash or enforce a subpoena issued by the United States Equal Employment Opportunity Commission ("EEOC"). The decision by our highest court on the correct standard of review will have important implications for businesses, because if a litigant is displeased with a lower court's decision, it may get two bites at the apple. Such an outcome will likely encourage more appeals, drawn-out investigations and increase legal fees.
On the other hand, if the Supreme Court decides that the Ninth Circuit was wrong and that a deferential standard of review (as opposed to a de nova standard) is appropriate, the losing side in future cases is more likely to accept the decision of the lower district court, knowing its chances of winning on appeal are slim.
Reprinted courtesy of
Jeffrey M. Daitz, Peckar & Abramson, P.C. and
Rashmee Sinha, Peckar & Abramson, P.C.
Mr. Daitz may be contacted at jdaitz@pecklaw.com
Ms. Sinha may be contacted at rsinha@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Will COVID-19 Permanently Shift the Balance between Work from Home and the Workplace?
April 13, 2020 —
Adam Weaver - Gravel2Gavel Construction & Real Estate Law BlogOn March 15, 2020, the Center for Disease Control and Prevention (CDC) issued formal guidance to combat the spread of the coronavirus by recommending against gatherings of 50 or more people for the next eight weeks (CDC guidance), which includes nearly every office building in America. Thus, began the most significant work from home experiment this country has ever seen.
With the majority of the workforce working from home, many employees see this as an opportunity to finally prove that, “yes, that meeting could have been an email.” However, while workers will not be distracted by constant (and potentially unnecessary) meetings, a number of issues and questions arise with working from home.
Most importantly, is this working from home experiment a temporary opportunity for businesses to test remote work ideas or is this the new normal? And how will this affect commercial real estate moving forward?
Read the court decisionRead the full story...Reprinted courtesy of
Adam Weaver, PillsburyMr. Weaver may be contacted at
adam.weaver@pillsburylaw.com
Traub Lieberman Partner Kathryn Keller and Associate Steven Hollis Secure Final Summary Judgment in Favor of Homeowner’s Insurance Company
April 02, 2024 —
Kathryn Keller & Steven A. Hollis - Traub LiebermanTraub Lieberman Partner Kathryn Keller and Associate Steven Hollis obtained summary judgment on behalf of a major homeowners’ insurer in a breach of contract action in the Ninth Judicial Circuit in and for Osceola County, Florida. The underlying claim involved a water loss in a bathroom of the Plaintiff’s property allegedly resulting in substantial damage to the home. The claim had been reported by Plaintiff’s counsel. The Plaintiff had retained counsel and two vendors before giving notice to the insurer. In addition, the insurer’s field adjuster was not provided the opportunity to inspect the plumbing parts that had been allegedly damaged. Specifically, the drainage system had been completely removed and replaced. The insurer retained an engineer, who concluded that the removal of the original plumbing components hindered the ability of the engineer to determine their conditions prior to removal. Meanwhile, the surface conditions of the white PVC pipe appeared bright and shiny as compared to other piping. The insured had also failed to provide a signed, sworn proof of loss within sixty days after the loss.
Reprinted courtesy of
Kathryn Keller, Traub Lieberman and
Steven A. Hollis, Traub Lieberman
Ms. Keller may be contacted at kkeller@tlsslaw.com
Mr. Hollis may be contacted at shollis@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Predicting Our Future with Andrew Weinreich
May 03, 2017 —
Aarni Heiskanen - AEC BusinessIn this podcast episode, my guest is Andrew Weinreich. We talk about the future of homebuilding against the backdrop of Andrew’s new podcast Predicting Our Future.
Is construction ripe for disruption? Andrew believes that homebuilding is much closer to a tipping point than ever before. In this interview, he explains why.
“In the United States, modular construction significantly lags behind what we see elsewhere around the world,” Andrew reminds. “When everything you can imagine today, from the paperclip to your smartphone is made in a factory, why is it that -certainly in this country- we associate homes made in factory with the lowest of low end homes.”
“The first question is: why is that? And the second question is: could that change? Could we be on the precipice of looking at the next Tesla; not for car-building, but for homebuilding.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi