Serving Notice of Nonpayment Under Miller Act
January 20, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the federal Miller Act, if a claimant is NOT in privity with the prime contractor, it needs to serve a “notice of nonpayment” within 90 days of its final furnishing. In this manner, 40 U.S.C. 3133 (b)(2) states:
A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made. The action must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. The notice shall be served–
(A) by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor’s residence; or
(B) in any manner in which the United States marshal of the district in which the public improvement is situated by law may serve summons.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
#9 CDJ Topic: Vallagio at Inverness Residential Condominium Association, Inc. v. Metropolitan Homes, Inc., et al.
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFDavid M. McClain of
Higgins, Hopkins, McLain & Roswell, LLC reported on the Colorado Court of Appeals ruling in the above mentioned case regarding the Vallagio condominiums developed by Metro Inverness, LLC. McClain concluded, “As a builder, the moral of the story here is that you need not rely on the Colorado Legislature to protect your ability to arbitrate construction defect claims asserted against you by homeowners associations. All you need to do is to include within your declaration a valid and enforceable declarant consent provision requiring your consent to amend out of the declaration the arbitration requirement for construction defect claims.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
It’s Not What You Were Thinking!
December 10, 2024 —
Daniel Lund III - LexologyAt least it is not what the lower court was thinking… but the same result for a general contractor seeking to have its comprehensive general liability insurer pay the GC’s defense related to claims for physical damage on a construction project.
In reviewing the Massachusetts federal district court’s ruling in favor of the insurer, the United States First Circuit Court of Appeals posited: “The principal question is whether a general contractor’s CGL insurance policy covers damage to a non-defective part of the contractor’s project resulting from a subcontractor’s defective work on a different part of that project.”
The district court had held under Massachusetts law that the insurer had no duty to defend because the lawsuit “did not allege ‘property damage’ caused by an ‘ occurrence,’ as required for coverage” under the policy (a defense that was urged by the insurer). The Court of Appeals affirmed, “albeit for different reasons.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Wisconsin High Court Rejects Insurer’s Misuse of “Other Insurance” Provision
March 04, 2019 —
Michael S. Levine & David M. Costello - Hunton Andrews KurthThe Wisconsin Supreme Court held last week in Steadfast Ins. Co. v. Greenwich Ins. Co. that two insurers must contribute proportionally to the defense of an additional insured under their comprehensive liability policies.
In 2008, torrential rainstorms battered the Milwaukee area for two days. The downpour overwhelmed the city’s sewer system, causing significant flooding in homes throughout the region. Out of those floods sprang several lawsuits against the Milwaukee Metropolitan Sewerage District (“MMSD”) for negligent inspection, maintenance, repair, and operation of Milwaukee’s sewage system.
MMSD was an additional insured under liability policies covering two other water service providers responsible for the city’s sewer systems. The first policy was issued by Greenwich Insurance Company for United Water Services Milwaukee, LLC, and the second was issued by Steadfast Insurance Company for Veolia Water Milwaukee, LLC. After learning of the lawsuits, MMSD tendered its defense of the sewage suits to both insurers. Steadfast accepted the defense; but Greenwich refused, claiming that its policy was excess to Steadfast’s based on an “other insurance” clause in Greenwich’s policy.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
David Costello, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Costello may be contacted at dcostello@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
CDJ’s #3 Topic of the Year: Burch v. The Superior Court of Los Angeles County, 223 Cal.App.4th 1411 (2014)
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFIn 2013, the case Liberty Mutual Insurance Company v. Brookfield Crystal Cove, LLC received a great deal of attention for its possible ramifications to how California’s Right to Repair Act (also known as SB 800) could be applied. However, 2014 had its share of SB 800 policy trends, most notably caused by the ruling in Burch.
In their article, “Construction Law Client Alert: California’s Right to Repair Act (SB 800) Takes Another Hit, Then Fights Back,” authors Steven M. Cvitanovic and Whitney L. Stefco, of Haight Brown & Bonesteel, analyzed Burch as well as KB Home Greater Los Angeles v. The Superior Court of Los Angeles County, et al., both cases that had ramifications on how California’s Right to Repair Act is applied.
Read the full story...
Karen L. Moore of Low, Ball & Lynch discussed the Liberty Mutual and Burch cases in her article, “California’s Right to Repair Act is Not a Homeowner’s Exclusive Remedy when Construction Defects cause Actual Property Damage.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Philadelphia Voters to Consider Best Value Bid Procurment
May 10, 2017 —
Wally Zimolong - Supplemental ConditionsMy friend and colleague,
Chris McCabe, recently
published an opinion piece on Philly.com concerning the May 16 ballot question that asks Philadelphia voters to approve a change in the way Philadelphia awards public contracts.
Currently, Philadelphia, like all municipalities in Pennsylvania, uses an objective lowest responsible bidder standard in the award of public contracts. Under this approach, public contracts must be awarded to a bidder that responds to all of the criteria of the request for bids and offers the lowest price. Under this traditional approach the award of public contracts is completely transparent.
The May 16 ballot initiative seeks to change this. If approved, Philadelphia could award public contracts using a host of subjective factors. What those factors would be are unknown because the policies are not yet written.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Understand the Dispute Resolution Provision You Are Agreeing To
September 20, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen negotiating a contract, do not overlook the dispute resolution provision. It is one of the more important provisions in your construction contract. This provision will come into play and have ramifications if there is a dispute, which is certainly not uncommon on a construction project.
In dispute resolution provisions in subcontracts on federal projects, it is not unusual for that provision to include language that requires the subcontractor to STAY any dispute that concerns actions or inactions of the owner pending the resolution of any dispute between the owner and prime contractor relating to that action or inaction. A provision to this effect should be included for the benefit of the prime contractor. For instance, the provision may say the subcontractor agrees to stay any such claim against the prime contractor or prime contractor’s surety pending the outcome of any pass-through claim (or otherwise) submitted under the Contract Disputes Act.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Nomos LLP Partner Garret Murai Recognized by Super Lawyers
September 05, 2023 —
Garret Murai - California Construction Law BlogNomos LLP Partner Garret Murai has been selected to the 2023 Northern California Super Lawyers list in the area of Construction Litigation. This is the tenth consecutive year that he has been recognized by Super Lawyers.
Garret was also also featured in this year’s Northern California Super Lawyer’s magazine’s 20th anniversary cover story “Built Different” where he talks a bit about his practice and changes he has seen over the past 20 years as a construction lawyer. The following is an excerpt from the article:
“The New Reality of Work”
Garret Murai, whose father was an architect, is a founding partner of Nomos LLP, an Oakland-based construction law firm. Concentrating in both commercial and public works, Murai’s clients run the gamut from contractors and subcontractors to owners and developers.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com