Contractual Waiver of Consequential Damages
January 02, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Toll Plans to Boost New York Sales With Pricing, Incentives
December 10, 2015 —
Prashant Gopal – BloombergToll Brothers Inc. plans to use competitive pricing and offer buyers incentives to speed up sales at some of its New York City condominium projects.
“There are certain units in certain locations within a building that are hot, and then there are other units that may be in a dark, cold corner that you have to incentivize a bit more,” Chief Executive Officer Douglas Yearley said on the company’s earnings conference call Tuesday. While Toll “will not fire-sale it to move” units, “we will price to the market.”
Incentives would be offered for certain units at Pierhouse at Brooklyn Bridge Park and 400 Park Ave. South and 1110 Park Ave. in Manhattan, Yearley said. While the supply in New York City has grown most for condos selling for more than $7.5 million, most of Toll’s units are less expensive, he said.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, Bloomberg
DoD Issues Guidance on Inflation Adjustments for Contractors
August 15, 2022 —
Jennifer Harris & Abby Salinas - ConsensusDocsThe Department of Defense (“DoD”) recently issued a memorandum to contracting officers (“COs”) guiding the use of economic price adjustment (“EPA”) clauses to address inflation-related cost increases. The memorandum, entitled Guidance on Inflation and Economic Price Adjustments, comes as the year-over-year inflation rate rose to 8.6% in May, and contractors with fixed-price contracts seek ways to recover their rising costs. EPA clauses allow the parties to mitigate cost risks that present themselves as a result of circumstances beyond the contractor’s control, e.g., inflation and supply chain price fluctuations. Generally, an EPA clause will dictate that the Government bear the cost risk up to a mutually agreed-upon ceiling. EPA clauses apply to the cost portion of a contract, but do not normally apply to the profit. DFARS PGI 216.203-4.
Memorandum: No CO Authority to Grant Contractual Relief Absent an EPA Clause
The memorandum states that absent an existing EPA clause, COs do not have the authority to provide contractual relief for unanticipated inflation under a firm-fixed-price contract.
Reprinted courtesy of
Jennifer Harris, Peckar & Abramson, P.C. (ConsensusDocs) and
Abby Salinas, Peckar & Abramson, P.C. (ConsensusDocs)
Ms. Harris may be contacted at jharris@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Engineering, Architecture, and Modern Technology – An Interview with Dr. Jakob Strømann-Andersen
September 14, 2020 —
Aarni Heiskanen - AEC BusinessWe sat down with Dr. Jakob Strømann-Andersen of Henning Larsen’s Sustainability Engineering Department. Our talk covered the need for interdisciplinary research, sustainable practice, and how technology will lead change in the years ahead.
Can you tell us a bit about your professional background and what you’re currently working on?
I’m a partner with Henning Larsen and work with around 300 architects globally. We’re based in Copenhagen where we’re 200 people strong, with branches throughout the world. I’m a trained engineer with a civil engineering background – making me the first partner that’s not an architect. I’ve been with the company for 15 years and joined as an industrial research Ph.D. in Denmark. For my first three years here, I was employed as a researcher doing research and energy-efficient building design. And that’s where we started with our approach to sustainability.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
AAA Revises Construction Industry Arbitration Rules and Mediation Procedures
July 22, 2024 —
Patrick McKnight - The Dispute ResolverThe American Arbitration Association (AAA) recently revised its Construction Industry Arbitration Rules and Mediation Procedures (“the Rules”). Several notable changes went into effect March 1, 2024, involving the scope of confidentiality, regular and fast track procedures, and updates to certain monetary thresholds.
I. Revisions to Regular Track Procedures
Rule 45: Confidentiality
For the first time, confidentiality is now the default standard. Under Rule 45(a), arbitrators must keep all matters confidential unless otherwise required by law, court order or the agreement of the parties. Rule 45(b) allows a mediator to issue confidentiality orders and “take measures for protecting trade secrets and confidential information.”
Rule 7: Consolidation and Joinder
Under the new provisions, consolidation and joinder requests must be filed before confirmation of the Merits Arbitrator’s appointment. This language eliminates a previous option that allowed confirmation up to 90 days after filing of such requests. A failure to timely respond to a joinder request will result in a waiver of objections. Now, a party must establish both good cause and prejudice for a successful joinder request after confirmation of the arbitrator.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Home Prices in U.S. Rose 0.3% in August From July, FHFA Says
October 28, 2015 —
Prashant Gopal – BloombergU.S. home prices rose in August as low borrowing costs and sustained job growth fueled demand amid a tight inventory of properties on the market.
Prices climbed 0.3 percent on a seasonally adjusted basis from July, the Federal Housing Finance Agency said Thursday in a report from Washington. The average estimate of 16 economists was for a 0.5 percent increase, according to data compiled by Bloomberg. The gain was 5.5 percent from a year earlier.
Values have increased steadily as buyers, bolstered by an improving job market and easing mortgage standards, compete for a limited supply of existing homes. The number of listed properties in August was the second-lowest for that month since 2002, according to the National Association of Realtors.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, Bloomberg
Nevada Budget Remains at Impasse over Construction Defect Law
June 01, 2011 —
CDJ STAFFNegotiations for the Nevada state budget have stalled over proposals to amend the state’s construction defect laws. Assembly Republicans had offered changes to the law to make it friendlier to contractors; however, after a state Supreme Court ruling that the state could not move a local government entity’s funds into state coffers, pressure has increased on the governor to lift the expiration dates of taxes approved in 2009.
The Reno Gazette-Journal quotes John Madole, a construction industry lobbyist, “We agree with them that you have to address the issue of the attorney fees, and for all practical purposes, they are automatically awarded when anybody brings any kind of suit.”
Speaker of the Assembly, John Oceguera, a Democrat, has proposed a bill that “makes it absolutely crystal clear that the only time you get attorney's fees is if you're the prevailing party.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Private Project Payment Bonds and Pay if Paid in Virginia
January 05, 2017 —
Christopher G. Hill – Construction Law MusingsOne of the many items of construction law that has always been about as clear as mud has been the interaction between a contractual pay if paid clause and payment bond claims either under the Federal Miller Act or Virginia’s “Little Miller Act.” While properly drafted contractual “pay if paid” clauses are enforceable by their terms in Virginia, what has always been less clear is whether a bonding company can take advantage of such a clause when defending a payment bond claim. As always, these questions are very fact specific both under the Federal Act and the state statute. I wish that this post would answer this question, but alas, it will not.
A recent case from the City of Roanoke, Virginia looked at the interaction between a payment bond and a “condition precedent” pay if paid clause as it relates to a private project that is not subject to the Little Miller Act. In the case of IES Commercial, Inc v The Hanover Insurance Company, the Court examined a contractual clause between Thor Construction and IES Commercial in tandem with the bond language between Hanover Insurance Company and Thor as it related to a surprisingly familiar scenario. The general facts are these: IES performed, Thor demanded payment from the owner for the work that IES performed and the owner, for reasons that are left unstated in the opinion, refused to pay. IES sues Hanover pursuant to the payment bond and Hanover moves to dismiss the suit because Thor hadn’t been paid by the owner and therefore Hanover could take advantage of the pay if paid language.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com