Architects Group Lowers U.S. Construction Forecast
July 30, 2014 —
Nadja Brandt – BloombergSpending on non-residential construction in the U.S. will be less than initially projected as state and local governments scale back investments in such properties as schools and health-care buildings, the American Institute of Architects said.
Total spending on commercial and institutional development probably will increase 4.9 percent this year, down from an earlier estimate of 5.8 percent, according to a semi-annual survey by the Washington-based group.
A slowdown in funding for institutional projects, which include education, health-care, religious and public-safety facilities, has been a drag on the recovery of the wider industry, according to Kermit Baker, the AIA’s chief economist. The group expects institutional-construction spending to fall 0.1 percent this year, compared with January’s projection for an increase of 3.4 percent, Baker said.
Read the court decisionRead the full story...Reprinted courtesy of
Nadja Brandt, BloombergMs. Brandt may be contacted at
nbrandt@bloomberg.net
U.S. Codes for Deck Attachment
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFTed Cushman in Big Builder explained how “decks often collapse when the ledger attachment to the main house fails.” Now, codes require “positive attachment…a solid connection with closely spaced lag screws (or better yet, bolts)." Cushman demonstrated this pictorially in a detail. He also stated to make sure to fasten securely, remove siding, and install flashing.
Read the court decisionRead the full story...Reprinted courtesy of
Can a Receiver Prime and Strip Liens Against Real Property?
September 20, 2021 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogCourts overseeing receivers generally enjoy broad discretion in directing and approving a receiver’s proposed actions. But does that authority extend to a receiver not only granting a super-priority lien ahead of existing liens, but also selling the real property free and clear of all liens? In County of Sonoma v. Quail, 56 Cal.App.5th 657 (Ct. App. 2020), the California Court of Appeals answered that question in the affirmative.
Quail involved a 47,480 square-foot lot with two houses, a few garages, several outbuildings, and numerous trailers surrounded by a veritable junk yard. Despite many of these structures being uninhabitable, unsanitary, and dangerous, multiple families resided on the lot. Although Sonoma County (the “County”) ordered the owner to remediate the property several times, he failed and refused to do so. After several years of these violations going unabated, the County ultimately sought and obtained the appointment of a receiver over the real property.
To obtain funds necessary to repair the property, the receiver asked the court for permission to borrow money through the issuance of a receivership certificate to be secured by a super-priority lien—i.e., a lien ahead of all other liens—against the real property. Although the trial court initially declined to prime existing liens, when the receiver could find no one to lend money (since the land lacked equity), the trial court relented and approved a super-priority lien despite the senior secured lender’s objection (the “lender”).
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Insuring Lease/Leaseback Projects
August 19, 2024 —
David G. Jordan & Jeffrey J. Vita - Saxe Doernberger & Vita, P.C.Overview
Several states utilize a unique statutory mechanism to allow school districts to finance the construction of public-school facilities. This arrangement (known as a “lease-leaseback agreement”) allows a school district to lease property to a contractor/developer, who then constructs or renovates a school facility on the property. Once the work is completed, the contractor/developer leases the school building back to the school district. The school district then makes lease payments over time, often many years, which can be structured in various ways to spread out the cost of construction. The arrangement typically requires a site lease for the land leased to the contractor/developer, a facilities lease for the lease-back of the school building to the school district and a traditional construction agreement. In some ways, the arrangement resembles a Public-Private Partnership (PPP) whereby a public entity collaborates with a private entity for the purpose of financing and delivering a project traditionally provided solely by the public sector.
Reprinted courtesy of
David G. Jordan, Saxe Doernberger & Vita, P.C. and
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C.
Mr. Jordan may be contacted at DJordan@sdvlaw.com
Mr. Vita may be contacted at JVita@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Gut Feeling Does Not Disqualify Expert Opinion
July 06, 2011 —
CDJ STAFFThe New Jersey Supreme Court issued a ruling in June on the case of Nevins v. Toll in which they reversed an earlier decision and remanded the case to a lower court for retrial. At issue in the case was the testimony of the plaintiff’s expert, J. Anthony Dowling. In depositions, Mr. Dowling said that his estimates for repair were based on a “gut feeling.” Dowling said he had “very little” experience in cost estimates for single-family homes. The defendants sought to bar Dowling’s testimony which was granted by the judge. Without an expert, Ms. Nevin’s case was dismissed.
Describing Dowling’s report as “far from a model of how an expert’s opinion in a construction case should be presented,” the court noted that Dowling is not a professional expert witness. However, the court did note that Dowling is a professional cost estimator. Despite Mr. Dowling using his “gut feeling” to construct his estimate, the New Jersey Supreme Court felt that whether his estimate is convincing is “a question for the jury.”
Read the court’s opinion…
Read the court decisionRead the full story...Reprinted courtesy of
Payment Bond Claim Notice Requires More than Mailing
August 04, 2015 —
Christopher G. Hill – Construction Law MusingsIt’s been a while since I posted something new relating to Virginia’s “Little Miller Act” and its various notice requirements for a subcontractor to make a payment bond claim.
I have posted on the basics of a Virginia payment bond claim previously here at Musings. One of these basics is the 90 day notice requirement for suppliers or second tier subcontractors with no direct contractual relationship to the general contractor. A recent case from the Norfolk, Virginia Circuit Court examined when notice is “given” under the Little Miller Act.
In R T Atkinson Building Corp v Archer Western Construction, LLC the Court looked at the question of whether mailing of the notice of claim is enough to constitute notice being “given” in a manner that would satisfy the statutory requirements. In that case, the supplier mailed the notice within the 90 day window, but the defendant argued on summary judgment that it did not receive the notice until 2 days after the 90 day window had closed. In support of this contention, the defendant provided tracking information showing delivery by the USPS on the non-compliant date.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Privilege Is All Mine: California Appellate Court Finds Law Firm Holds Attorney Work Product Privilege Applicable to Documents Created by Formerly Employed Attorney
June 29, 2017 —
David W. Evans & Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Tucker Ellis LLP v. Superior Court (A148956 – Filed 6/21/2017), the First Appellate District held that (1) the holder of the attorney work product privilege is the employer law firm rather than the former employee attorney who created the privileged documents while a firm employee, and (2) as a result, the firm did not owe a duty to obtain the former attorney’s permission before disclosing the subject documents to third parties.
In Tucker Ellis LLP, the attorney, while still employed by Tucker Ellis, exchanged a series of e-mails with a consultant retained by the firm to assist in asbestos litigation for a client. The firm also entered into an agreement with the consultant to summarize scientific studies on the causes of mesothelioma in a published review article. After the attorney departed the firm, Tucker Ellis was served with a subpoena in connection with a matter pending in Kentucky for the production of communications with the consultant regarding the article. In response, Tucker Ellis, in relevant part, produced the work product e-mails authored by the former attorney. The e-mails eventually ended up on the Internet and reached over 50 asbestos plaintiffs’ attorneys, resulting in the attorney’s termination from his new firm. After Tucker Ellis ignored the attorney’s “claw-back” letter, he filed suit against the firm for negligence, among other causes of action. The trial court granted the former attorney’s motion for summary adjudication on the issue of duty, reasoning that the firm owed the attorney a legal duty to prevent the disclosure of the work product. Tucker Ellis filed a petition for a writ of mandate with the Court of Appeal challenging the trial court’s decision on the duty issue.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Ensuring Efficient Arbitration of Construction Disputes Involving Mechanic’s Liens
February 18, 2020 —
Robert G. Campbell & Trevor B. Potter - Construction ExecutiveThere may be tension between the enforcement of statutory mechanic’s lien claims when a contractual dispute resolution provision calls for arbitration. Once the parties are in arbitration, it may not be clear whether the arbitrator has authority to make factual determinations regarding amount and validity of mechanic’s liens, and whether courts are bound by these determinations. This uncertainty stems from the fact that in most states a mechanic’s lien can only be enforced by a court of competent jurisdiction. Indeed, many mechanic’s liens statutes define foreclosure as a “judicial process,” and courts generally have exclusive jurisdiction to issue orders foreclosing on real property1.
The risk for contractors and owners is that they will spend time and money re-litigating factual issues related to proving elements of a mechanic’s lien claim, including the proper lien amount, timeliness and other prerequisites. Without a clear understanding of what issues and elements are arbitrable, the parties run the risk that an arbitrator will rule on certain elements only to find out during post-arbitration lien foreclosure proceedings that the arbitrator lacked authority to make determinations on those elements. Questions therefore arise whether a court will enforce the arbitrator’s determinations and whether the parties must relitigate mechanic’s lien issues creating a further risk of inconsistent rulings.
These risks can be minimized through arbitration provisions which address these issues, express requests in arbitration demands and by ensuring that arbitration awards contain explicit determinations of mechanic’s liens issues.
Reprinted courtesy of
Robert G. Campbell & Trevor B. Potter, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Potter may be contacted at tpotter@coxcastle.com
Mr. Campbell may be contacted at rcampbell@coxcastle.com
Read the court decisionRead the full story...Reprinted courtesy of