Specification Challenge; Excusable Delay; Type I Differing Site Condition; Superior Knowledge
January 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesAn Armed Services Board of Contract Appeals dispute, Appeal of L.S. Black-Loeffel Civil Constructors JV, ASBCA No. 62402, 2023 WL 5827241 (ASBCA 2023), involved which party bore liability for delay—the federal government or the prime contractor–based on various legal theories. Without detailing the factual details, a number of interesting legal issues were raised in this dispute including (1) a defective specification challenge, (2) excusable delay, (3) Type I differing site condition, and (4) superior knowledge. These legal issues are discussed below.
1. Specification Challenge (Defective Specifications)
The contractor claimed that the government’s specifications were defective in regard to a thermal control plan. The government countered that the specifications were not design specifications but performance specifications. The specifications were performance based because they did not tell the contractor how to achieve the performance-based criteria.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Business Risk Exclusions Dismissed in Summary Judgment Motion
November 09, 2020 —
Tred R. Eyerly - Insurance Law HawaiiWhile the court denied summary judgment on whether the alleged damage was due to faulty workmanship and not covered, it granted summary judgment for dismissal of several business risk exclusions the insurer asserted against the developer. United Specialty Ins. Co. v. Dorn Homes, 2020 U.S. Dist. LEXIS 138431 (D. Ariz. Aug. 4, 2020).
Dorn, a residential home developer, developed a 350 single family residential home division. Dorn did not perform the actual construction, but contracted with various subcontractors.
After completion, Dorn began to receive complaints from homeowners about interior damage to some of the homes. Inspections showed interior cracking, wall separation and foundation movement. Dorn ultimately installed an unvented foam insulated roof system to address these issues. Therefore, it did not repair the faulty workmanship of its subcontractors because it would not have been efficient or as effective. Dorn paid for the repairs to the 87 homes at issue.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Endorsement Excludes Replacement of Undamaged Property with Matching Materials
August 20, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court approved the insurer's endorsement which stated the insured would not pay for undamaged property in order to match damaged property. Noonan v. Am. Family Mut. Ins. Co., 2019 U.S. App. LEXIS 15545 (May 24, 2019).
After hail and wind damaged part of the roof in the insureds' home, American Family inspected the roof and determined that it had suffered $12,000 in damage. The insureds disputed this amount and demanded an appraisal to provide a binding estimate of the amount of loss. American Family asked the appraisers to divide their estimate into two categories - one for replacing damaged shingles and another for replacing undamaged shingles that would not match those needed to replace the damaged ones. The appraisers did not do so. They instead found that replacing the entire roof would cost $141,000 and noted there was a matching issue because alternative products did not match the current shingles on the roof.
Of the $141,000 needed to replace the entire roof, American Family estimated that $87,232.98 was due to the costs of matching. The insureds sued. The district court remanded the case to the appraisers to clarify the award by differentiating the costs attributable to the actual roof damage from those attributable to shingle matching. The appraisers clarified the award and reported that actual damages were $66,619, meaning that $74,381 was attributable to matching. American Family then paid the actual damages, less the deductible, but refused to pay the rest.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Formal Opinion No. 2020-203: How A Lawyer Is to Handle Access to Client Confidential Information and Anticipation of Potential Security Issues
December 07, 2020 —
Bremer Whyte Brown & O'Meara LLPRecently, the California Bar Association (“CBA”) published Formal Opinion No. 2020-203[1] concerning a lawyer’s ethical obligations with respect to unauthorized access to electronically stored client information. The onset of the COVID-19 pandemic greatly accelerated the growing trend of storing and maintaining data and information online so that employees and clients can access the data from anywhere in the world at any time. Now, in today’s working world, the reality is nearly all information and data is stored and shared digitally online for ease of access, use, and dissemination.
Unfortunately, a major draw-back of this switch to a cyber paradigm is serious exposure to data breaches as a result of hacking, inadvertence, or theft. Formal Opinion No. 2020-203 outlines how a lawyer is to handle access to client confidential information and anticipation of potential security issues. This article will briefly cover the key aspects addressed in Formal Opinion No. 2020-203.
What is the duty owed by a lawyer to his or her client regarding the use of technology?
At the outset, the CBA reminds lawyers of the ongoing duty of competence (Rule 1.1) and the duty to safeguard clients’ confidences and secrets (Rule 1.6; Cal. Bus. & Prof. Code, § 6068(e)) which impose the requirement that a lawyer must have a basic understanding of the risks posed when using a given technology and (if necessary) obtain help from appropriate experts to assess those risks and take reasonable steps to prevent data breaches.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Ongoing Operations Exclusion Bars Coverage
December 09, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer denied the insured contractor's claim seeking a defense for faulty workmanship based upon the ongoing operations exclusion. PJR Constr. of N.J. v. Valley Forge Ins. Co., 2019 U.S. Dist. LEXIS 127973 (D. N. J. July 31, 2019).
PJR Construction was the general contractor to build a swim club and pavilion building for Cambridge Real Property, LLC. PJR began construction on May 29, 2012, and was to complete the construction by March 1, 2013. The project took much longer than anticipated. PJR was denied access to the site on November 13, 2014. Cambridge contended PJR tolerated shoddy workmanship and breached the terms of the contract documents. Cambridge estimated that the project was between 55% and 74.3% complete.
PJR and Cambridge went to arbitration. PJR sought a defense from the insurers. Coverage was denied based upon exclusions j (5) and j (6). Exclusion j (5), which the court referred to as the "Ongoing Operations Exclusion," provided the policy did not apply to,
Property Damage to . . . [t]hat particular part of real property on which you or any contractors or subcontractors working directly or indirectly on your behalf are performing operations, if the property damage arises out of those operations.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contractor Side Deals Can Waive Rights
October 02, 2023 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, we are quite fond of the Federal Miller Act and it’s Virginia counterpart, the “Little” Miller Act. Both of these statutes allow a subcontractor or supplier on a government construction project the security to perform their work with the knowledge that a bonding company will back their claim for payment. These acts are necessary because a construction company cannot file a mechanic’s lien on a government owned piece of property.
As a general rule the Miller Acts impose almost strict liability on a contractor and its surety to pay for work performed by a downstream supplier or subcontractor. However, as a recent case out of the Fourth Circuit Court of Appeals makes clear, this rule is not without exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Recording a Lis Pendens Is Crucial
January 04, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf you are in a construction dispute where you are pursuing a construction lien foreclosure action, recording a lis pendens is crucial. Did I say crucial? “[O]ne purpose of a notice of lis pendens is to alert all others that title to the property is involved in litigation and that ‘future purchasers or encumbrancers of that property’ are at risk of being bound by an adverse judgment.” Henry v. AIM Industries, LLC, 47 Fla.L.Weekly D653b (Fla. 2d DCA 2022). There really is never a reason not to record a
lis pendens when pursing a construction lien foreclosure. Please remember that – don’t forget to record the lis pendens!
There are times a lis pendens is recorded when the lis pendens is NOT based on a duly recorded instrument (e.g., construction lien or mortgage). A
lis pendens, however, is recorded because the dispute is tied to the property in which the lis pendens is being recorded. The lis pendens is recorded to best safeguard the plaintiff’s interest in the real property without fear that the real property will be sold impacting the purpose (and, of course, security) of the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Keep It Simple: Summarize (Voluminous Evidence, That Is...)
October 02, 2023 —
Steve Swart - The Dispute Resolver"The most complex analyses grow beautifully simple as they become public objects.” Philip Rieff, Fellow Teachers (1973), quoted in JOHN BARTLETT, BARTLETT’S FAMILIAR QUOTATIONS 800 (Geoffrey O’Brien gen. ed., 18th ed. 2012)
In a recent ABA Forum on Construction Law Webinar, a panelist with substantial experience as an arbitrator explained that documents are the most important evidence in a construction dispute. Fact-finders, she said, focus on contemporaneous project records more than witness testimony to vet what happened.
But, even a small to mid-sized construction project can generate millions of pages of documents. That is particularly true when disputes involve loss of productivity, delay, acceleration, and disruption. The volume of records related to entitlement and damages (e.g., timesheets, accounting, equipment logs, schedule files, meeting minutes, etc.) can overwhelm and confuse — not to mention bore — the fact finder.
Read the court decisionRead the full story...Reprinted courtesy of
Steve Swart, Williams MullenMr. Swart may be contacted at