Court of Appeals Affirms Dismissal of Owner’s Claims Based on Contractual One-Year Claims Limitations Period
October 04, 2021 —
Cassidy Ingram - Ahlers Cressman & SleightIn a recent unpublished decision – Tadych v. Noble Ridge Construction, Inc.– the Washington State Court of Appeals, Division One, held that a one-year contractual claim limitations clause was valid and enforceable. The Tadych decision is important because it reiterates the strict approach courts will take to a claim limitations clause less than the statutory six years for breach of contract claims prescribed by RCW 4.16.040(1). In other words, when the parties agree to shorten the limitations period, the agreement will be enforced barring any procedural or substantive unconscionability.
In Tadych, plaintiff owners (the Tadychs) contracted with defendant contractor (Noble Ridge Construction, Inc., or NRC) for the construction of a custom home in 2012. The contract provided a one-year claim limitations clause in which claims could be raised, and that all claims not raised in the one-year period would be waived. In December 2013, as the project neared completion, the Tadychs met with NRC to identify any outstanding project issues. The Tadychs noted several, including rainwater pools at the landing at the bottom of the stairs and several nicks and cracks on the stucco exterior walls.
Read the court decisionRead the full story...Reprinted courtesy of
Cassidy Ingram, Ahlers Cressman & SleightMs. Ingram may be contacted at
cassidy.ingram@acslawyers.com
Claims Against Broker Dismissed
June 20, 2022 —
Tred R. Eyerly - Insurance Law HawaiiClaims that the broker failed to secure adequate coverage for condominium owners were dismissed. Ting Lin v. Mountain Valley Indemn. Co., 2022 N.Y. Misc. LEXIS 1254 (N.Y. Sup. Ct. March 10, 2022).
The amended complaint alleged the agent, Century Max Inc., breached its duty to advise and sell to plaintiffs a homeowners and fire policy far in excess of $100,000 for their condominium unit, which was worth in excess of $600,000. Century moved to dismiss
A fire in the building forced all owners to vacate their units. The entire building was thereafter declared unsafe for habitation by the City of New York. The condominium owners met and voted to not restore the building, but to sell the burnt-out shell and distribute the sales proceeds and the condominium's insurance among the unit owners. There was no indication that the owners would not be made whole once the funds were distributed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New Braves Stadium Is Three Months Ahead of Schedule, Team Says
September 03, 2015 —
Michael Buteau – BloombergConstruction of the new $1.1 billion home of Major League Baseball’s Atlanta Braves is about three months ahead of schedule, according to team executives.
“We’ve built a really solid, aggressive, efficient plan,” Mike Plant, head of the team’s business operations, said in an interview Thursday during a brick-laying ceremony. “No one has ever built a ballpark of this scale and scope in 39 months, and we’re going to do it in 36.”
The 41,500-seat stadium, 14 miles northwest of Turner Field and known as SunTrust Park, will be about 20 percent smaller than the existing ballpark and could be completed by mid-November 2016, Plant and Braves Chairman Terry McGuirk said. The complex will include a 250-room Omni hotel, a nine-story corporate office for Comcast Corp. and the Roxy Theatre, a 4,000-seat music venue.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Buteau, Bloomberg
Navigating Complex Preliminary Notice Requirements
March 30, 2016 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back a good friend, Scott Wolfe. Scott is the founder of zlien, a cloud-based platform that gives construction industry participants control over their financial risk and payment processes. The zlien platform manages the mechanics lien compliance process for all parties in the contracting chain, automating and optimizing the exchange of preliminary notices, monitoring lien rights and exposure, and exchanging lien waivers. zlien empowers over 10,000 companies to optimize their credit and financial risk management, and works to promote a fair and transparent construction payment process, improve B2B relationships, facilitate faster payments, and reduce legal and financial risk.
Sending preliminary notice is the most important step in mechanics lien compliance. A majority of states require preliminary notice (sometimes called a pre-lien notice or notice to owner) from contractors, material suppliers, and other construction parties. Even if preliminary notice is not required, however, it is best practice to send this document on all projects for a variety of reasons.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Ensuing Loss Provision Salvages Coverage for Water Damage Claim
September 16, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Court of Appeals for the D.C. Circuit reversed the district court's finding of no coverage and found that the ensuing loss provision provided coverage for water damage. 3524 East Cap Venture, LLC, et al. v. Weschester Fire Ins. Co., et al., 104 F. 4th 193 (D.C. Cir. 2024).
Plaintiff 3534 East Cap Venture, LLC, a real-estate developer, hired plaintiff McCullough Construction, LLC, to build a residential and retail complex. Defendants Westchester Fire Insurance Company and Endurance American Insurance Company issued identical builders' risk policies, which covered the building while it was under construction. Each insurer was responsible for half of any qualifying losses.
The policies covered loss caused by or resulting from water damage. The policies, however, excluded loss caused by "dampness of atmosphere" or by "[e]xtremes or changes in temperature." But the exclusions contained an exception if "loss by an insured peril ensues."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York’s Comprehensive Insurance Disclosure Act Imposes Increased Disclosure Requirements On Defendants at the Beginning of Lawsuits
February 07, 2022 —
Craig Rokuson & Lisa M. Rolle - Traub Lieberman Insurance Law BlogOn December 31, 2021, New York Governor Kathy Hochul signed into law the Comprehensive Insurance Disclosure Act, which amends Section 3101(f) of the Civil Practice Law & Rules (CPLR) to require the automatic disclosure of insurance-related items within sixty days of the filing of an answer in a civil suit. For lawsuits pending as of the effective date of the Act, the disclosures required by Section 3101(f) must be provided by March 1, 2022.
Pursuant to amended Section 3101(f), defendants (including third-party defendants, cross-claim defendants, and counterclaim defendants) must provide the following information to plaintiffs within sixty days of answering the affirmative pleading, accompanied with a certification from both the defendant and his/her/their/its defense counsel that the disclosures are accurate and complete:
- Copies of all insurance policies that may be liable to satisfy a judgment in the lawsuit, including the insurance application.
- The contact information of any individuals responsible for adjusting the claim on each policy, including his/her/their phone number and email address. If a TPA is involved, his/her/their contact information must also be disclosed.
Reprinted courtesy of
Craig Rokuson, Traub Lieberman and
Lisa M. Rolle, Traub Lieberman
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Grants Motion to Dismiss Negligence Claim Against Flood Insurer
December 22, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer successfully moved to dismiss the insured's negligence claim and demand for jury trial, leaving only the insured's breach of insurance contract claim under the National Flood Insurance Program (NFIP). La Mirage Homeowners Association Inc. v. Wright National Flood Ins. Co., 2019 U.S. Dist. LEXIS 147667 (S.D. Tex. Aug 29, 2019).
Hurricane Harvey damaged three of insured homeowner's association condominium's buildings. Wright National Flood Insurance Company was the insurer pursuant to the NFIP when the hurricane damaged the insured's property. The insured alleged that Wright breached the policy by underpaying on the flood loss claims and by not initiating the appraisal the insured demanded. The insured sought recovery for negligence, consequential damage, statutory penalties, attorney's fees and pre-and-post judgment interest.
Wright moved to dismiss the extra-contractual claims and to strike the jury demand.
The NFIP's regulations allowed homeowners to purchase policies either directly from FEMA or from private insurers that functioned as Write Your Own (WYO) providers and fiscal agents of the United States. The Fifth Circuit had previously held that state law tort claims arising from claims handling by a WYO were preempted under federal law. The court, therefore, was faced with the issue of whether the insured's claims of negligence, attorney's fees, statutory penalties, and interest were policy-handling claims which were preempted by federal law.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ambiguity in Insurance Policy will be Interpreted in Favor of Insurance Coverage
July 19, 2017 —
David Adelstein - Florida Construction Legal UpdatesAn ambiguity in an insurance policy–after reading and interpreting the policy as a whole–will be construed against an insurer. This means an ambiguity will be construed in favor of insurance coverage (for the benefit of the insured) as opposed to against insurance coverage. This does not mean that every insurance policy contains an ambiguity. This also does not mean a court will interpret plain and ordinary words contrary to their conventional meaning or definition. But, as we all know, insurance policies are not the easiest of documents to decipher and ambiguities do exist relating to a particular issue or circumstance to the benefit of an insured. An insured that is dealing with specific insurance coverage issues should make sure they are working with counsel that looks to maximize insurance coverage, even if that means exploring ambiguities that will benefit an insured based on a particular issue or circumstance.
An example of an ambiguity in an insurance policy relating to a particular issue that benefitted an insured can be found in the Florida Supreme Court decision of Government Employees Insurance Co. v. Macedo, 42 Fla. L. Weekly S731a (Fla. 2017). This case involved an automobile accident and the interpretation of an automobile liability policy.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com