Bailout for an Improperly Drafted Indemnification Provision
February 11, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion came out that held that even though an indemnification provision in a subcontract was unenforceable per Florida Statute s. 725.06, the unenforceable portion is merely severed out of the indemnification clause leaving the rest of the clause intact. In essence, an otherwise invalid indemnification clause is bailed out by this ruling (which does not even discuss whether this subcontract had a severability provision that states that if any portion of any provision in the subcontract is invalid, such invalid portion shall be severed and the remaining portion of the provision shall remain in full force and effect).
This opinion arose from a construction defect case, CB Contractxors, LLC v. Allens Steel Products, Inc.,43 Fla.L.Weekly D2773a (Fla. 5thDCA 2018), where the general contractor, sued by an association, flowed down damages to subcontractors based on the contractual indemnification provision in the subcontracts. Subcontractors moved to dismiss the contractual indemnification claim because it was not compliant with Florida Statute s. 725.06. The indemnification provision required the subcontractors to indemnify the general contractor even for the general contractors own partial negligence, but failed to specify a monetary limitation on the extent of the indemnification as required by Florida Statute s. 725.06. (The indemnification clause in the subcontract was the standard intermediate form of indemnification that required the subcontractor to indemnify the general contractor for claims regardless of whether the claims were caused in part by the general contractor.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Formal Request for Time Extension Not Always Required to Support Constructive Acceleration
April 25, 2022 —
David Adelstein - Florida Construction Legal UpdatesDoes a constructive acceleration claim require the contractor to always request an extension of time which is then denied by the owner? While this is certainly the preference and the contractor should be requesting an extension of time as a matter of course for an excusable delay, the answer is NO! in certain circumstances. This is conveyed in the factually detailed case discussed below where a formal request for an extension of time was not required for the contractor to support its constructive acceleration claim.
But first, what is constructive acceleration:
Constructive acceleration “occurs when the government demands compliance with an original contract deadline, despite excusable delay by the contractor.” The Federal Circuit in Fraser defined the elements of constructive acceleration as follows:
(1) that the contractor encountered a delay that is excusable under the contract; (2) that the contractor made a timely and sufficient request for an extension of the contract schedule; (3) that the government denied the contractor’s request for an extension or failed to act on it within a reasonable time; (4) that the government insisted on completion of the contract within a period shorter than the period to which the contractor would be entitled by taking into account the period of excusable delay, after which the contractor notified the government that it regarded the alleged order to accelerate as a constructive change in the contract; and (5) that the contractor was required to expend extra resources to compensate for the lost time and remain on schedule.
Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, *42 (Fed.Cl. 2022) quoting Fraser Constr. Co. v. U.S., 384 F.3d 1354, 1361 (Fed. Cir. 2004) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Joint Venture Dispute Over Profits
January 27, 2020 —
David R. Cook - AHC Construction and Procurement BlogA recent Georgia Court of Appeals case demonstrates the risk of joint ventures failing to carefully define accounting rules in their joint venture agreement. Two trade contractors teamed up to accomplish certain tasks on a job at a wastewater lift station at Fort Gordon. A joint venture agreement provided for an equal split of the profits and losses. Unfortunately, the parties did not define “profit,” and particularly did not define what cost would be deducted in calculating profit. They disputed in particular whether certain large payments to individuals and 15% overhead charges should be deducted in calculating profits.
One party presented the expert testimony of an accountant while the other did not. The party presenting expert testimony asked the court to dismiss the other party’s claim because it was not supported by expert testimony of an accountant. The trial court granted the motion and dismissed the claim.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Two Architecturally Prized Buildings May be Demolished
January 17, 2014 —
Beverley BevenFlorez-CDJ STAFFThe historic Portland Public Services Building, designed by Michael Graves, may be demolished after a report showed that “the 32-year-old building needs more than $95 million worth of repairs,” Dezeen Magazine reported. The Portland, Oregon building “is credited with being one of the first major buildings of postmodernism.” According to The Oregonian, the Portland city commissioners have differing opinions as to how to proceed. Council member Amanda Fritz commented that she “doesn’t think the problems at The Portland Building are all that bad compared to other city facilities,” while council member Nick Fish stated, “There’s got to be a better option than putting another $100 million into a white elephant.”
Dezeen Magazine also reported that the former American Folk Art Museum in New York is scheduled to be demolished to make room to extend the Museum of Modern Art (MoMA). Glenn Lowry, the MoMA director, stated that the decision came after a six-month study: “The analysis that we undertook was lengthy and rigorous, and ultimately led us to the determination that creating a new building on the site of the former American Folk Art Museum is the only way to achieve a fully integrated campus.”
The decision is being criticized by “architects, conservationists, and critics” reported Dezeen Magazine. Architects Tod Williams and Billie Tsien designed the former American Folk Art Museum. Williams and Tsien stated, “Demolishing this human-scaled, uniquely crafted building is a loss to the city of New York in terms of respecting the size, diversity and texture of buildings in a midtown neighborhood that is at risk of becoming increasingly homogenized."
Read the full story at Dezeen Magazine re The Portland Building...
Read the full story at The Oregonian re The Portland Building...
Read the full story at Dezeen Magazine re American Folk Art Museum... Read the court decisionRead the full story...Reprinted courtesy of
Case Alert Update: SDV Case Tabbed as One of New York’s Top Three Cases to Watch
January 10, 2018 —
Richard W. Brown - SDV BlogArgument before the Court of Appeals has now been scheduled for February 7, 2018, in
Gilbane Building Co. v. St. Paul Insurance, with a long anticipated decision by New York’s highest court to be issued shortly thereafter. In its September 18, 2017 edition, Law360.com highlighted three major cases with significant implications on insurance coverage that will soon be decided by the New York Court of Appeals. Gilbane presents an opportunity for the Court to address the growing number of divergent decisions regarding the prerequisites for qualifying as an additional insured, as it considers an Appellate Division’s holding that a construction manager is not entitled to coverage as an additional insured under a contractor’s policy because the two companies did not enter into a direct contract.
Read the court decisionRead the full story...Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. Mr. Brown may be contacted at
rwb@sdvlaw.com
MGM Begins Dismantling of the Las Vegas Harmon Tower
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFMGM has begun to dismantle the $8.5 billion, incomplete Harmon Hotel in Las Vegas, Nevada, according to the Las Vegas Review-Journal. The demolition process is expected to take up to a year.
The Las Vegas Review-Journal reported that construction of the tower was halted in 2008 after construction defects were allegedly discovered. Later, “the building was deemed structurally unsound.”
“Instead of blowing the building up in grand fashion, contractors hired by MGM Resorts are now removing scrap metal and other materials from the building, along with taking off the blue-tinged glass that has covered the structure for the last five years,” Howard Stutz wrote in the Las Vegas-Review Journal. “The process also includes installing pedestrian protection systems outside the structure above adjacent sidewalks and walkways.”
Read the court decisionRead the full story...Reprinted courtesy of
Employees Versus Independent Contractors
February 23, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPAre the workers you employ on the job site considered employees or independent contractors? This is an important distinction that contractors and subcontractors must understand for many purposes, including federal taxes. The classification of your workers can affect their federal income, social security, and Medicare taxes, and the type of benefits they can receive.
When determining whether workers should be classified as employees or independent contractors, courts generally look at three key factors: behavioral control, financial control, and the relationship of the parties.
Behavior Control
Behavior control concerns the business’s right to direct or control how the worker does its work. A worker is likely to be considered an employee when the business maintains behavior control. Such control can be exercised by giving instructions. This would include instructions on how, when, or where to do the work, what tools or equipment to use, who to hire to help with the work, or where to purchase the supplies to be used. Behavioral control can also occur through training. If the business provides training to tell the worker to do the work in a certain manner then the worker is more likely to be an employee.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
A Few Green Building Notes
December 02, 2019 —
Christopher G. Hill - Construction Law MusingsThis past week, the blogosphere (if that’s even the word these days) has been abuzz about green building and the value that green can add to a project. Three items in particular (among many) got my attention.
The first of these was the fact that a new private sustainability rating system is ready for launch. The Institute for Sustainable Infrastructure (or ISI) is seeking public comment on its proposed envISIon. This new system (aptly dubbed Version 1.0) will go “live” in July for comment. Why mention this new system? First of all, ISI’s founding members are the American Society of Civil Engineers (ASCE), the American Public Works Association (APWA) and the American Council of Engineering Companies (ACEC). This trio gives the new program some fairly heavy weight backing. Second, while there are rating systems aside from the ever present LEED, none have taken hold in any real way to compete with LEED. I am curious to see if the envISIon system has any better luck. Finally, this shows that sustainable building is of interest to more than the USGBC and those of us that discuss LEED on a daily basis. I find this to be a great thing that could lead to more societal acceptance of sustainable practices as a standard practice rather than a goal.
Hopefully such efforts will offset the other two notes that caught my eye recently.
The first of these is the foreclosure of the Chapel Hill, North Carolina Greenbridge project. This project is well documented at my friend Doug Reiser’s (@douglasreiser) Builders Counsel blog so I won’t further discuss the details here. However, the question that Doug asks is a good one, i. e. were the “green” elements of the project to blame?
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at