Specific Source of Water Not Relevant in Construction Defect Claim
June 28, 2013 —
CDJ STAFFThe Nebraska Court of Appeals has concluded that a lower court came to the correct conclusion in a construction defect case involving water intrusion. The Hiatts built a home in North Platte, Nebraska, in in 2004 which they sold to the Oettingers in May, 2006. Shortly thereafter, the Oettingers started experiencing problems with water intrusion and contacted the Hiatts. The Hiatts responded by replacing the septic lift. Subsequently, the Oettingers landscaped their yard, which they allege was done with the assistance of the Hiatts. The water problems continued and “the parties took substantial remedial measures, including excavating the sidewalk and inspecting the downspouts.” The water problems continued, getting worse and requiring increasingly aggressive responses.
The Oettingers then had a series of inspections, and they hired the last of these inspectors to actually fix the water intrusion problem. At that point, they filed a lawsuit against the Hiatts alleging that the Hiatts “breached their contact by constructing and selling a home that was not built according to reasonable construction standards,” and that they “were negligent in the repair of the home in 2009.”
During the trial, Irving Hiatt testified that they “tarred the outside of the basement and put plastic into the tar and another layer of plastic over the top of that.” He claimed that the problem was with the Oettingers’ landscaping. This was further claimed in testimony of his son, Vernon Hiatt, who said the landscaping lacked drainage.
The Oettingers had three experts testify, all of whom noted that the landscaping could not have been the problem. All three experts testified as to problems with the Hiatts’ construction. The court concluded that the Hiatts had breached an implied warranty, rejecting the claim that the water intrusion was due to the landscaping. The Hiatts appealed the decision of the county court to the district court. Here, the judgment of the lowest court was confirmed, with the district court again finding a breach of the implied warranty of workmanlike performance.
The Hiatts appealed again. They alleged that the district court should not have held a breach of implied warranty existed without proving the source of the water intrusion, and that damages should have been apportioned based on the degree to which the Oettingers’ landscaping and basement alterations were responsible. The appeals court dispensed with the second claim first, noting that “they do not argue this error in their brief nor do they explain how or why the trial court should have apportioned damages.” The court also noted that although the Oettingers made a negligence claim in their suit, the case had been decided on the basis of a breach of implied warranty.
The appeals court upheld the Oettingers’ claim of a breach of implied warranty. In order to do this, the court noted that the Oettingers had to show that an implied warranty existed, that the Haitts breached that warranty, damage was suffered as a result, and that no express warranty limited the implied warranty. That court noted that “the record is sufficient to prove that the Hiatts breached the implied warranty in the method in which they constructed the basement” and that “this breach was the cause of the Oettingers’ damages.”
The court concluded that the Oettingers “provided sufficient evidence that the Hiatts’ faulty construction allowed water, whatever its source, to infiltrate the basement.” The court rejected the Hiatts’ claim that the Oettingers’ repairs voided the warranty, as it was clear that the Hiatts were involved in carrying out these repairs. The court’s final conclusion was that “the evidence in the record supports the trial court’s factual finding that the Hiatts’ flawed construction caused water damage to the Oettingers’ basement.”
Read the court decisionRead the full story...Reprinted courtesy of
Survey: Workers Lack Awareness of Potentially Hazardous Nanomaterials
December 11, 2018 —
Scott Van Voorhis – Engineering News-RecordMicroscopic nanoparticles are part of the mix in nearly 600 construction products. The particles add strength, durability and other desired characteristics.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENRENR may be contacted at
ENR.com@bnpmedia.com
Unjust Enrichment Claims When There Is No Binding Contract
December 04, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate opinion starts off, “This is a typical South Florida construction dispute.” (See case citation at the bottom) Let’s see, is it? No. It’s a garden variety payment dispute where the parties did NOT have a binding contract. Why? That’s for a different day (because the smart practice is ALWAYS to have a contract!) but it touches on the equitable, unjust enrichment claim. And it touches on competing unjust enrichment claims and the apportionment of those claims. In other words, can both parties be right on their unjust enrichment claims?
An owner hired a general contractor for home renovations. Work started but the relationship soured and the general contractor did not complete the work. The general contractor filed a payment dispute against the owner based on unpaid invoices. It pled alternative theories of recovery against the owner: breach of contract and unjust enrichment. The owner filed a counterclaim against the general contractor for the same claims. During the non-jury trial, the general contractor presented unpaid invoices along with testimony that the invoices represented the value of services rendered. The owner presented evidence of the completion of work damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Bats, Water, Soil, and Bridges- an Engineer’s dream
December 31, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaWant to know how bats may affect your engineering plans? Want to hear about cool new bridges? Read on.
Over the past month, I’ve had the pleasure of attending two events hosted by the North Carolina Chapter of the ACEC (American Council of Engineering Companies). The first of these was the Joint Transportation Conference, held in conjunction with the NC DOT. The second was the annual ACEC Engineering Excellence Awards. At both events, I learned interesting information that engineers should know. Today, I will discuss the Transportation Conference, including some new regulations and unusual design methods. I will save the highlights from the Excellence Awards for later this week.
1. It’s a cave, it’s a bat, it’s bats, man!
Did you know that your future bridge project may be affected by the Northern Long-Eared Bat? It’s true. Right now, the federal government is considering listing the bat on the Endangered Species List, due to the 98-99% mortality rate the bats are experiencing due to “white nose syndrome”. Over 1,700 projects in North Carolina could be impacted, including work on bridges, culverts, abandoned buildings, and guardrails–essentially, any activity involving tree clearing, structure demolition/removal, or structure maintenance. On November 26th, 2014, the US Fish and Wildlife Service extended the comment period to discuss the implications of listing the bat on the endangered species list. If the bat is listed, there is no grandfathering of projects. All projects will immediately be required to engage in protective activities. Stay tuned, but be aware that your transportation projects could be affected starting sometime next year.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
County Elects Not to Sue Over Construction Defect Claims
June 18, 2014 —
Beverley BevenFlorez-CDJ STAFFEven though repairs are expected to cost four million, the New Hanover County Board of Commissioners announced that they will not be pursuing litigation against Clancy and Theys Construction Company for their alleged construction defects of their work on the W. Allen Cobb Judicial Annex in North Carolina, according to Star News Online.
“The board stated that taxpayer money would be better spent on the repairs than on a lengthy court case,” reported Star News Online. “But as a result of the faulty work, the board removed the company from its list of prequalified bidders and stated that it would not be eligible to work on other county construction projects.”
Read the court decisionRead the full story...Reprinted courtesy of
Practical Advice: Indemnification and Additional Insured Issues Revisited
September 08, 2016 —
John P. Ahlers – Ahlers & Cressman PLLC Construction BlogLawyers love writing about indemnification. There are seventeen blog articles on our website alone that deal with the subject. Before you click out of this email in disgust that we are rehashing a stale topic, this post contains some practical advice for contractors and subcontractors dealing with the perplexing issues of indemnification and additional insured provisions.
The concept of indemnity is based on a contractual agreement made between two parties, in which one party agrees to pay for the potential losses or damages caused by the other party. To indemnify someone means to protect that person or entity by promising to pay the cost of possible future damage, loss, or injury. When signing a contract, you should identify the indemnity obligations that could cost your business money. Finding the words “hold harmless” or “indemnify” in a proposed contract is not enough. The terms “hold harmless,” “save harmless,” or “indemnify” are a big part of the indemnification obligation. Although insurance requirements (“additional insured” clauses) accomplish virtually the same thing as very broad, unfair, or unlimited indemnity terms do, they result in an “end run” around the effort to limit the indemnification obligation.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Metrostudy Shows New Subdivisions in Midwest
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFMetrostudy surveyed the Chicago, Indianapolis, and Minneapolis/St. Paul markets and found an increase in subdivisions—“[n]ot a re-hashing of existing communities or a re-configuring of existing developments, but new land, being newly developed,” according to Builder magazine.
Builder reported that in 2010 only 383 new lots were delivered to the Chicago market, but in just the first six months of 2014, 1,500 new lots have been delivered. Furthermore, the Twin Cities had a total of 964 lots delivered in 2010. “In 2013, there were 3,683 new lot deliveries. Indianapolis has seen a total of 1,400 new lots delivered in the first six months of 2014, compared to just 650 through the first half of 2010.”
Read the court decisionRead the full story...Reprinted courtesy of
Tallest U.S. Skyscraper Dream Kept Alive by Irish Builder
May 01, 2014 —
Brian Louis – BloombergGarrett Kelleher, the Irish developer trying to restore Chicago’s status as home to the tallest building in the U.S., has one last chance to keep his dream alive.
The planned lakefront skyscraper is nothing more than a hole in the ground six years after the financial crisis derailed Kelleher’s ambitions. To salvage the project, he must line up money to get out of bankruptcy, then obtain financing for the 2,000-foot (610-meter), Santiago Calatrava-designed Chicago Spire condominium tower, which would surpass New York’s 1 World Trade Center by 224 feet.
“I never understood how that project was going to work, frankly,” said Alan Lev, chief executive officer of Belgravia Group Ltd., a Chicago-based housing developer uninvolved in the project. “It’s a real eyesore sitting in the ground, so I hope somebody does something with it.”
Read the court decisionRead the full story...Reprinted courtesy of
Brian Louis, BloombergMr. Louis may be contacted at
blouis1@bloomberg.net