Tips for Drafting Construction Contracts
May 04, 2020 —
Stuart Rosen - Construction ExecutiveWhen negotiating a construction contract, a contractor and its advisers must first determine the areas of greatest concern.
For example, if the contractor believes that the drawings that were prepared by the architect and other design professionals are deficient, the contractor may want to reference those deficiencies in the contract. The contractor should emphasize that it is not responsible for the drawings and to the extent the project schedule is extended to allow the parties to address such issues with the drawings, the contractor would be entitled to additional compensation.
This article provides contractors with additional tips, with a broad focus on project delays, for their protection when negotiating and drafting construction contracts, and helps contractors understand the rationale for such tips to better prepare contractors in such negotiations.
Contractor’s liability to the owner for delay damages
It is imperative that the contract include a waiver of claims for consequential damages. AIA Document A201TM – 2017 includes such a waiver, which provides, in pertinent part, “The Contractor and Owner waive Claims against each other for consequential damages arising out of or relating to this Contract … This mutual waiver is applicable, without limitation, to all consequential damages due to either party’s termination in accordance with Article 14.”
Reprinted courtesy of
Stuart Rosen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Rosen may be contacted at
srosen@proskauer.com
Water Leak Covered for First Thirteen Days
April 11, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeals recently held the policy's exclusion for repeated water seepage over a period of fourteen days or more does not exclude loss caused by the seepage for the first thirteen days.
Hicks v. Am. Integrity Ins. Co. of Florida, 2018 Fla. App. LEXIS 2616 (Fla. Ct. App. Feb. 23, 2018). Read the court decision
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii
Mr. Eyerly may be contacted at te@hawaiilawyer.com
Research Project Underway to Prepare Water Utilities for Wildfire Events
January 23, 2023 — Brown and Caldwell
PORTLAND, Ore., January 17, 2023 — A multi-disciplinary team of utilities, academia, and consultants have convened to develop a study and publish guidance to improve water treatment resilience against the impacts of forest fires.
Critical to water security, forested watersheds provide 75 percent of the world’s accessible freshwater (Food and Agriculture Organization of United Nations 2021) and supply drinking water for more than two-thirds of North American consumers (EPA 2019). The frequency and severity of forest fires have been increasing globally with warming temperatures and shifting precipitation patterns due to climate change. Wildfires can cause costly, long-term water treatment issues that push water treatment processes beyond their design and operational response capabilities.
Such issues include filtration effectiveness, disinfection efficacy, the elevation of disinfection by-product formation, and increased bioavailable phosphorus leading to problematic cyanobacterial/algal blooms.
Led by a principal research team of Lynn Stephens (Brown and Caldwell), Dr. Mac Gifford and Yone Akagi (Portland Water Bureau), and Dr. Monica Emelko (University of Waterloo), Water Research Foundation (WRF) project #5168 is funded by the foundation’s Emerging Opportunities Program and the Portland Water Bureau (PWB).
About The Water Research Foundation
The Water Research Foundation (WRF) is the leading research organization advancing the science of all water to meet the evolving needs of its subscribers and the water sector. WRF is a nonprofit, educational organization that funds, manages, and publishes research on the technology, operation, and management of drinking water, wastewater, reuse, and stormwater systems—all in pursuit of ensuring water quality and improving water services to the public. For more information, visit www.waterrf.org
About Brown and Caldwell
Headquartered in Walnut Creek, Calif., Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and more than 1,700 professionals across North America and the Pacific. For over 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients’ expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decision
Read the full story...
Reprinted courtesy of
Harmon Towers to Be Demolished without Being Finished
October 02, 2013 — CDJ STAFF
Engineering.com looks at why the Harmon Tower in Las Vegas will be coming down at some point in the future. Construction stopped, unfinished in 2008. Taking the building down will cost about $400 million, which the building’s owner feels that the developer should pay.
Inspectors concluded that the building did not meet the earthquake specifications for Las Vegas. The contractor claimed that the fault was due to the design specifications and that the supports were further weakened during destructive testing.
Read the court decision
Read the full story...
Reprinted courtesy of
Tenth Circuit Finds Appraisal Can Decide Causation of Loss Under Colorado Law
November 29, 2021 — Tred R. Eyerly - Insurance Law Hawaii
The Tenth Circuit determined that the Colorado Supreme Court would agree with other state courts that appraisers can decide the causation of a loss. Bonbeck Parker, LLC v. The Travelers Indem. Co. of Am., 2021 U.S. App. LEXIS 29607 (10th Cir. Oct. 1, 2021).
A hailstorm damaged three buildings owned by BonBeck. A claim was submitted to Travelers under BonBeck's commercial property policy. Travelers acknowledged that some hail damage occurred to all the buildings except for the roofs. Travelers paid $34,200 for damage to the buildings. Coverage for the roof damage was denied because it resulted not from the hail damage but from uncovered events like wear and tear, deterioration, and improperly installation.
BonBeck requested an appraisal. Travelers insisted that the appraisal would only determine the amount of loss of covered claims. BonBeck rejected these conditions and Travelers filed suit. Read the court decision
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Damon Key Leong Kupchak Hastert
Mr. Eyerly may be contacted at te@hawaiilawyer.com
Seattle’s Newest Residential Developer
March 13, 2023 — Michael J. Yelle - Ahlers Cressman & Sleight
On February 14, 2023, Seattle voters passed Initiative 135, creating the “Seattle Social Housing Developer” (“Public Developer” or “PD”) and the initiative was signed into law by Mayor Bruce Harrel on March 1, 2023.[1] With this initiative, voters created Seattle’s newest housing developer. The PD aims to develop, own, and maintain housing in the City of Seattle.[2] In addition, the PD also intends to retrofit acquired properties to increase energy efficiency and bring them into compliance with accessibility standards.[3] Contractors, subcontractors, and suppliers may see this as an opportunity to compete for and build everything from new multi-unit housing to handrail installation projects. This post will explore some of the basics of contracting with a public corporation like the Public Developer and what contractors may want to consider in their business planning.
What is the PD?
The Public Developer is a political subdivision of the State of Washington, like a port or fire district.[4] The Public Developer is not an agency or department of the City of Seattle. In this way, it is like Seattle Public Schools (SPS) because both SPS and the PD operate within the City of Seattle, but have (or will have) their own staff, procurement rules, and standard contracts distinct from the City’s. Like SPS, the PD can also enter construction and supply contracts, sue, and be sued. Read the court decision
Read the full story...
Reprinted courtesy of Michael J. Yelle, Ahlers Cressman & Sleight
Florida Insurance Legislation Alert - Part I
April 18, 2023 — Gregory D. Podolak & Holly A. Rice - Saxe Doernberger & Vita, P.C.
On March 24, 2023, Florida Governor Ron DeSantis signed into law House Bill 837 which significantly impacts several critical aspects of modern Florida civil litigation, particularly insurance disputes. SDV has actively monitored the evolution of this legislation, including substantial commentary from the legal and insurance communities that followed its enactment. In this multi-part series, we will explore the critical developments impacting policyholders and what to expect moving forward.
The insurance-related headlines overwhelmingly concentrate on one key area: the elimination of one-way attorney fee recovery for property insurance policyholders. This development represents a key change in longstanding Florida insurance law and is worthy of attention - but it doesn’t tell the whole story.
Reprinted courtesy of Gregory D. Podolak, Saxe Doernberger & Vita, P.C. and Holly A. Rice, Saxe Doernberger & Vita, P.C.
Mr. Podolak may be contacted at GPodolak@sdvlaw.com
Ms. Rice may be contacted at HRice@sdvlaw.com Read the court decision
Read the full story...
Reprinted courtesy of
Not so Fast – Florida’s Legislature Overrules Gindel’s Pre-Suit Notice/Tolling Decision Related to the Construction Defect Statute of Repose
May 11, 2020 — Rahul Gogineni - The Subrogation Strategist
As discussed in a prior blog post, in Gindel v. Centex Homes, 2018 Fla.App. LEXIS 13019, Florida’s Fourth District Court of Appeal held that when the plaintiffs provided a pre-suit notice in compliance with §558.004 of Florida’s construction defect Right-to-Cure statute, Fla. Stat. §§ 558.001 to 558.005, et. seq., they commenced a “civil action or proceeding,” i.e. an “action,” within the meaning of Florida’s construction defect Statute of Repose, Florida Statue § 95.11(3)(c). Thus, the court held that the plaintiffs commenced their action prior to the time Florida’s 10-year statute of repose period ended. In overturning the lower court’s dismissal of the action, the court found that because the Right-to-Cure statute, §558 of the Florida Statutes, sets out a series of mandatory steps that must be taken prior to bringing a judicial action, filing pre-suit notice of claim sufficiently constituted an “action” for purposes of Florida’s Statute of Repose.
For various reasons, the parties appealed the decision to the Supreme Court of Florida. In July of 2019, before the Florida Supreme Court could decide whether to hear the case, the Florida legislature passed legislation that effectively overruled the decision. To overrule the decision, the Florida Legislature modified § 558.004 of Florida’s Right-to-Cure statute to expressly state that a notice of claim served pursuant to the Right-to-Cure statute does not toll the 10-year statute of repose period for construction claims. See Fla. Stat.
§ 558.004(d). Read the court decision
Read the full story...
Reprinted courtesy of Rahul Gogineni, White and Williams LLP
Mr. Gogineni may be contacted at goginenir@whiteandwilliams.com