The Texas Supreme Court Limits the Use of the Economic Loss Rule
September 03, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to David Fisk of Kane Russell Coleman & Logan PC, in an article published by JD Supra Business Advisor, “[T]he Texas Supreme Court issued a per curium opinion limiting the application of the economic loss doctrine or rule, as it is referred to in Texas, in the context of residential construction defect claims.”
In Chapman Custom Homes, Inc. v Dallas Plumbing Co., the court “ruled that a plumbing subcontractor assumes an implied duty not to flood or otherwise damage a home while performing its contract with a builder” and that “the economic loss rule does not apply in this context.”
Read the court decisionRead the full story...Reprinted courtesy of
Clearly Determining in Contract Who Determines Arbitrability of Dispute
April 26, 2021 —
David Adelstein - Florida Construction Legal UpdatesAs you know from prior postings: “Arbitration provisions are creatures of contract and must be construed ‘as a matter of contract interpretation.’ ” Fallang Family Limited Partnership v. Privcap Companies, LLC, 46 Fla.L.Weekly D639e (Fla. 4th DCA 2021) (citation omitted). Thus, if you prefer to arbitrate potential disputes, instead of litigating potential disputes, you want to include an arbitration provision in your contract. While there are positives and negatives to arbitration, no different than litigation, these positives and negatives should be considered during the contract negotiation process when dealing with the dispute resolution process in the contract.
Generally, under the law, the arbitrability of a dispute is determined by the court. However, this can be deferred to the arbitrator with clear and unmistakable language in the contract.
By way of example, the American Arbitration Association includes a rule that allows an arbitrator to rule on the arbitrability of the dispute, i.e., the claims asserted are subject to the governing arbitration provision in the contract. Recent law has suggested that if the objective is to authorize an American Arbitration Association arbitrator to make this determination, the contract clearly and unmistakably needs to state this intent and generally referring to the American Arbitration Association rules is not good enough. For this reason, I have included in arbitration provisions language that specifically states, “In the event of any dispute as to the arbitrability of any claim or dispute, the parties agree that an appointed arbitrator within the American Arbitration Association shall make this determination.” I have also included in arbitration provisions the converse so that if there is a dispute as to the arbitrability of a claim or dispute, the court, and not the arbitrator, will make this determination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Working Safely With Silica: Health Hazards and OSHA Compliance
January 17, 2022 —
Rick Pedley - Construction ExecutiveAbout 2.3 million American workers are exposed to silica, including those in construction, oil and gas, agriculture and manufacturing. Silica is commonly found in a range of construction materials and when this material breaks apart, small particles are released into the air, creating what’s known as respirable crystalline silica. These particles can get into a person’s respiratory tract, which can lead to a range of serious and potentially fatal illnesses including silicosis, lung cancer, chronic obstructive pulmonary disease and kidney diseases.
The Occupational Safety and Health Administration has set clear regulations for working with this substance, so construction workers and managers can know the risks of inhaling this substance and protect themselves on the job site.
What is Silica?
Crystalline silica is a mineral that forms naturally in the earth. Raw construction materials such as sand, stone, concrete and mortar often contain deposits of crystalline silica, which can put employees at risk. Silica becomes a danger to workers when it is released into the air and breathed in.
Reprinted courtesy of
Rick Pedley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mixed Reality for Construction: Applicability and Reality
July 22, 2019 —
A. Vincent Vasquez - Construction ExecutiveOne technology available to the digital contractor for mapping what’s happening in the physical world with the 3D models is mixed reality. Mixed reality often includes both augmented reality and virtual reality.
Preconstruction Phase
During the preconstruction design phase, mixed reality can be used for a number of tasks, such as:
- conducting design iterations;
- communicating designs to owners;
- visualizing the impact of design changes;
- discovering design and coordination clashes; and
- mocking up virtual interior designs.
Marketing
Mixed reality can also be used to create marketing material, such as a virtual showroom. Imagine being able to show a potential client what the building will look like. For example, the client, wearing mixed-reality glasses, can see the physical neighborhood with the building or can take a virtual “walk” through of an apartment before it it is even completed.
Reprinted courtesy of
A. Vincent Vasquez, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Waiving The Right to Arbitrate Under Federal Law
November 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf there is an arbitration provision in your contract that you want to enforce, you do not want to take action inconsistent with those rights as this could give rise to a waiver argument, i.e., that you waived your rights to arbitrate, particularly if the other party has been prejudiced.
Under federal policy and law, establishing waiver requires the party arguing waiver to “bear a heavy burden of proof.” U.S. f/u/b/o John Wayne Construction, G.S.A. Division, LLC v. Federal Ins. Co., 2021 WL 4526727 (M.D.Fla. 2021) quoting Stone v. E.F. Hutton & Co., 898 F.2d 1542, 1543 (11th Cir. 1990).
“To determine whether the right to arbitrate has been waived, courts apply a two part test: i) whether, “‘under the totality of the circumstances,’ the party ‘has acted inconsistently with the arbitration right’”; and ii) “whether, by doing so, that party ‘has in some way prejudiced the other party.’” Id. quoting Ivax Corp. V. B. Braun of Am., Inc., 286 F.3d 1309, 1315-16 (11th Cir. 2002). Substantial participation in litigation prior to invoking the right to arbitrate supports a party acting inconsistent with the right to arbitrate. Id. And, “‘[p]rejudice has been found in situations where the party seeking arbitration allows the opposing party to undergo the types of litigation expenses that arbitration was designed to alleviate.’” Id. quoting Morewitz v. W. of Eng. Ship Owners Mut. Prot. & Indem. Ass’n (Luxembourg), 62 F.3d 1356, 1366 (11th Cir. 1995).
Hence the heavy burden for a party to support to prove waiver– establishing both substantial participation in litigation that is inconsistent with the right to arbitrate AND prejudice.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
America’s Factories Weren’t Built to Endure This Many Hurricanes
November 05, 2024 —
Brooke Sutherland - BloombergAmerica’s factories aren’t built for the current cascade of extreme weather events.
Dozens of
industrial sites were in the zone of impact as Hurricane Milton slammed into Florida’s West Coast this week, including several concrete plants, speed boat manufacturing operations and facilities owned by
Honeywell International Inc., Johnson Controls International Plc,
General Electric Co. and Illinois Tool Works Inc., among others. Meanwhile, a Baxter International Inc. facility in Marion, North Carolina, that makes 60% of the intravenous fluids used in hospitals around the country was
shuttered because of damage from Hurricane Helene just two weeks ago. Mines responsible for producing more than 80% of the world’s supply of commercial high-purity quartz in nearby Spruce Pine
were also affected by severe flooding, raising the risk of disruptions to semiconductor production, which relies on the material.
Read the court decisionRead the full story...Reprinted courtesy of
Brooke Sutherland, Bloomberg
Construction Law Client Alert: California Is One Step Closer to Prohibiting Type I Indemnity Agreements In Private Commercial Projects
June 15, 2011 —
Haight Brown & Bonesteel, LLPOn June 1, 2011 by majority vote, the California Senate passed Senate Bill 474, which would amend Civil Code section 2782, and add Civil Code section 2782.05. The passage of this new law is a critical development for real estate developers, general contractors and subcontractors because it will affect how these projects are insured and how disputes are resolved.
Civil Code section 2782 was amended in 2007 to prohibit Type I indemnity agreements for residential projects only. Since 2007, various trade associations and labor unions have lobbied to expand those very same restrictions to other projects. These new provisions apply to contracts, entered into after January 1, 2013, that are not for residential projects, and that are not executed by a public entity. The revisions provide that any provision in a contract purporting to indemnify, hold harmless, and defend another for their negligence or other fault is against public policy and void. These provisions cannot be waived.
A provision in a contract requiring additional insured coverage is also void and unenforceable to the extent it would be prohibited under the new law. Moreover, the new law does not apply to wrap-up insurance policies or programs, or a cause of action for breach of contract or warranty that exists independently of the indemnity obligation.
The practical impact of this new law is that greater participation in wrap-up insurance programs will likely result. While many wrap-up programs suffer from problems such as insufficient limits, and disputes about funding the self-insured retention, the incentive for the developer or general contractor to utilize wrap-up insurance will be greater than ever before because they will no longer be able to spread the risk of the litigation to the trades and the trade carriers.
Read the full story…
Reprinted courtesy of Steve Cvitanovic of Haight Brown & Bonesteel, LLP.
Read the court decisionRead the full story...Reprinted courtesy of
The Construction Project is Late—Allocation of Delay
November 17, 2016 —
David Adelstein – Florida Construction Legal UpdatesThe construction project is late. Very late. The owner is upset and notifies the contractor that it is assessing liquidated damages. The contractor, in turn, claims that the project is late because of excusable, compensable delays and, perhaps, excusable, noncompensable delays. This is a common and unfortunate story between an owner and contractor on any late construction project. Now the fun begins regarding the allocation of the delay!
Through previous articles, I discussed that in this scenario the burden really falls on the contractor to establish that the liquidated damages were improperly assessed against it and, thus, it is entitled to additional time and/or extended general conditions as a result of excusable delays. Naturally, this requires the contractor to develop a critical path analysis (time impact analysis) allocating the impacts / delays (and the reasons for the impacts/ delays) to the project completion date. The reason the burden really falls on the contractor is because the owner’s burden is relatively easy – the project was not complete on time pursuant to the contract and any approved changed orders.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at