Real Case, Real Lessons: Understanding Builders’ Risk Insurance Limits
August 12, 2024 —
David McLain - Higgins, Hopkins, McLain & Roswell, LLCIn the recent case of 5333 Mattress King LLC v. Hanover Insurance Company, the United States District Court for the District of Colorado provided significant insights into the limits of builders’ risk insurance policies. Mattress King LLC, a warehouse owner, faced a substantial loss when a subcontractor drove a crane over and damaged the warehouse’s concrete floor slab during construction. Despite having a builders’ risk insurance policy with Hanover Insurance Company, coverage was denied, leading to litigation.
Applicable Policy Provisions
The policy in question was a Commercial Marine/Commercial Lines Builders’ Risk insurance policy. Builders’ risk insurance is designed to cover direct physical loss to covered property during construction unless the loss is excluded or limited by the policy. Key exclusions of the policy at issue included losses caused by faulty, inadequate, or defective:
- Planning, zoning, surveying, or development
- Design, specifications, workmanship, repair, construction, renovation, remodeling, grading, or compaction
- Materials used in construction or renovation
- Maintenance of the covered property
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Re-Thinking the One-Sided Contract: Considerations for a More Balanced Approach to Contracting
November 21, 2022 —
William Underwood - ConsensusDocsConstruction projects can be inherently risky – often there are multiple parties (owners, architects, engineers, contractors, subcontractors, consultants, vendors, government officials, sureties, insurers, and many others), unforeseen site conditions, tangled supply chains, acts of God, inadequate funding, site safety matters, and a whole host of other issues that can make even a relatively straight-forward job complex. Parties necessarily want to minimize their individual risk to the greatest extent possible on construction projects. And to do so, they may seek to push as much risk as possible onto the other side through one-sided terms in their construction contract.
But is an entirely one-sided contract the best way to mitigate risk? In many instances, the answer is no. Every contract is different – and many considerations should be taken into account when drafting and negotiating contracts – but entirely one-sided can often have unintended consequences and create risks that otherwise might not exist in a contract that allocates and balances risk more equally across the parties.
This article reviews several considerations (although it is not an exhaustive list) for avoiding one-sided contracts, including some of the benefits created through the use of equitable contract clauses. And for context, some examples of one-sided contract clauses include no relief for other contractor/owner-caused delays; no relief for force majeure events; no relief for unforeseen site conditions; and broad form indemnification clauses (i.e. one party assumes the obligation to pay for another party’s liability even if the other party is solely at fault). Again, this is a non-exhaustive list, and many other standard contract provisions can be altered to become one-sided. But the general premise of a “one-sided contract clause” is that it shifts all risk, obligation, and liability to one party. And this article examines why that might not be the best idea.
Read the court decisionRead the full story...Reprinted courtesy of
William Underwood, Jones Walker LLPMr. Underwood may be contacted at
wunderwood@joneswalker.com
NLRB Broadens the Joint Employer Standard
September 17, 2015 —
Craig Martin – Construction Contractor AdvisorPerhaps in anticipation of Labor Day, the National Labor Relations Board issued its ruling in Browning-Ferris Indus. of Cal. d/b/a BFI Newby Island Recyclery, establishing an easier standard for unions to prove that a joint employer relationship exists. This will make it easier for unions to make the upstream company, like a parent company, liable for unfair labor practices, even if the upstream company had no direct involvement.
Some Background
BFI runs a recycling plant and contracts with Leadpoint to provide workers to sort garbage in the recycling plant. The staffing agreement specifically stated that Leadpoint was the sole employer of the personnel it supplied and Leadpoint handled supervision of the employees, not BFI.
Leadpoint’s employees sought to unionize and an election was held. The union filed a petition seeking a determination that Leadpoint and BFI were a joint employers.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Traub Lieberman Attorneys Lisa M. Rolle, Eric D. Suben, and Justyn Verzillo Secure Dismissal of All Claims in a Premises Liability Case
November 16, 2023 —
Lisa M. Rolle, Eric D. Suben & Justyn Verzillo - Traub LiebermanOn an appeal of an order denying Defendant’s motion to dismiss the complaint in a slip-and-fall action commenced in Kings County Supreme Court, Traub Lieberman attorneys Lisa M. Rolle, Eric D. Suben, and Justyn Verzillo successfully secured dismissal of all claims by the Appellate Division, Second Department, on behalf of Traub Lieberman’s client.
The lawsuit sought to recover damages arising out of injuries the Plaintiff allegedly sustained when she slipped and fell in the shower of a rental property owned by the Defendant, a limited liability company. Plaintiff alleged that the subject shower was defective, and the Defendant negligent, based on the absence of non-slip surfacing and grab bars in the shower. Aside from premises liability (negligence), Plaintiffs asserted eight other causes of action, including gross negligence, breach of warranty of habitability, intentional infliction of emotional distress, negligent infliction of emotional distress, alter-ego liability, loss of consortium, and for declaratory judgment.
The judge in Supreme Court denied Traub Lieberman’s motion to dismiss on behalf of Defendant, citing as the sole reason that the affidavits submitted with the motion were unsigned, and ignoring Traub Lieberman’s arguments pointing out the glaring facial deficiencies of Plaintiff’s pleading and that the signed affidavits were in fact submitted before the return date.
Reprinted courtesy of
Lisa M. Rolle, Traub Lieberman,
Eric D. Suben, Traub Lieberman and
Justyn Verzillo, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Mr. Suben may be contacted at esuben@tlsslaw.com
Mr. Verzillo may be contacted at jverzillo@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers & Cressman’s Top 10 Construction Industry Contract Provisions
July 02, 2014 —
Beverley BevenFlorez-CDJ STAFFJames R. Lynch of Ahlers & Cressman, PLLC, has published the first two parts of the four-part “Top 10 Construction Contract Provisions” series: “As a powerful mechanism to control contract risk, increase predictability, and reduce the cost and complexity of potential disputes, we frequently recommend that our clients’ contracts include a mutual waiver of consequential damages.”
The first part “explains the significance of such a clause and the risk a contractor assumes without it,” while the second part discusses “the various categories of damages flowing from a breach of contract and conclude[s] with examples of how parties can limit these damages to reflect their agreed allocation of risk.”
Read the full story, Part 1...
Read the full story, Part 2... Read the court decisionRead the full story...Reprinted courtesy of
Don’t Overlook Leading Edge Hazards
May 20, 2019 —
Baxter Byrd - Construction ExecutiveLeading edge hazards are often misunderstood and overlooked on today’s highly visible jobsites. Evidence is readily available via images shared on construction-related social media accounts.
In the context of people showing pride for the hard work they do or the extreme conditions under which they work, posts offer glimpses into the methods employed to mitigate fall hazards. Alarmingly, many of these methods do not adhere to industry-accepted standards, especially in the case of leading edge applications.
Mincing Words
The definition of “leading edge” itself has undergone somewhat of a transformation since its introduction by OSHA to its current use by ANSI in the Z359.14-2014 “Safety Requirements for Self-Retracting Devices for Personal Fall Arrest and Rescue Systems” standard. OSHA defines a leading edge as an “unprotected side or edge during periods when it is actively or continuously under construction,” giving many the impression that a leading edge was a temporary condition found only during the construction of a structure.
Reprinted courtesy of
Baxter Byrd, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Byrd may be contacted at
info@puresafetygroup.com
White and Williams Obtains Reversal on Appeal of $2.5 Million Verdict Against Electric Utility Company
September 03, 2014 —
Edward Koch, Mark Paladino, Luke Repici, & Andrew Susko – White and Williams LLPPPL Electric Utilities successfully argued on appeal that the $2.5 million plaintiff’s molded verdict awarded to an injured painting subcontractor should be vacated because the alleged evidence was legally insufficient and therefore the utility was not liable.
In Nertavich v. PPL Electric Utilities, the plaintiff argued that although the utility was a landowner out of possession of the worksite, the utility was liable because it controlled the work of the subcontractor both by contract and by conduct. PPL argued on appeal before the Superior Court of Pennsylvania that the alleged evidence of the utility company’s control was insufficient as a matter of law to constitute control over the means and methods of the subcontractor’s work, and thus, PPL was not liable as a landowner out of possession.
Reprinted courtesy of White and Williams LLP attorneys
Edward Koch,
Mark Paladino,
Luke Repici and
Andrew Susko
Mr. Koch may be contacted at koche@whiteandwilliams.com;
Mr. Paladino may be contacted at paladinom@whiteandwilliams.com;
Mr. Repici may be contacted at repicil@whiteandwilliams.com;
and Mr. Susko may be contacted at suskoa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects Lead to “A Pretty Shocking Sight”
October 14, 2013 —
CDJ STAFFWalls black with mold. Grass growing on carpets. The board chair of the Penhorwood condos, Christine Burton, describes the photos as “a pretty shocking sight.” The residents were all evicted in 2011 and given only fifteen minutes to gather what possessions they could after the buildings were found to be structurally unsound. An attempt was made to stabilize the buildings, but they kept shifting and cracking, exposing the interiors to the elements.
The owners of the Fort McMurray condominium complex are suing the developer, contractor, and others for $60 million. Fort McMurray has ordered that the buildings be torn down, although the condo owners don’t have the funds for this. Even the funds for continuing the lawsuit are hard to come by. Ms. Burton notes “because of the evacuation and the cost of stabilizing the building so that we could go in and get people’s furniture and personal effect out has pretty much depleted our funds.” The owners “have no more money.”