Court Finds That $400 Million Paid Into Abatement Fund Qualifies as “Damages” Under the Insured’s Policies
November 21, 2022 —
Lorelie S. Masters & Yaniel Abreu - Hunton Insurance Recovery BlogIn
Sherwin-Williams Co. v. Certain Underwriters at Lloyd’s London, et al., the Court of Appeals for Ohio’s Eighth District reversed the lower court, finding that money paid by the insured into an abatement fund was “damages” as that undefined term was used in the policyholder’s insurance policies. 2022-Ohio-3031, ¶ 1. Sherwin-Williams is a cautionary tale about how insurers may try to narrow the meaning of undefined terms in their insurance policies.
The dispute in Sherwin-Williams focused on coverage for $400 million that the policyholder and other defendants were ordered to pay into an abatement fund to be used by California cities and counties to mitigate the hazards caused by lead paint in homes. Id. ¶ 1. Although the underlying litigation proceeded in California, Ohio law governed coverage, which raised issues of first impression in Ohio. Id. Among other things, the insurers argued that the money paid into the abatement fund did not qualify as “damages” under the policies. Id. ¶ 57. The insured argued that, because the insurers did not define “damages” in the policies, the term had to be given its ordinary meaning. Id. ¶ 56.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Yaniel Abreu, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Abreu may be contacted at yabreu@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Supreme Court Rules Labor Costs Not Depreciated to Determine Actual Cash Value
November 19, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Illinois Supreme Court determined that a homeowner insurer may not depreciate labor costs in calculating actual cash value (ACV) after a loss under the policy. Sproull v. State Farm Fire and Casualty Co., 2021 Ill. LEXIS 619 (Ill. Sept. 23, 2021).
Plaintiff was insured under a homeowner's policy that provided replacement cost coverage for structural damage. Under the policy, the insured would initially receive an ACV payment but then could receive replacement cost value (RCV) if repairs or replacement were completed within two years and the insurer was timely notified. The policy did not define "actual cash value."
Plaintiff suffered wind damage to his residence and timely submitted a property damage claim to State Farm. The adjuster determined that the building sustained a loss with RCV of $1711.54. In calculating ACV, State Farm began with the RCV and then subtracted plaintiff's $1000 deductible and an additional $394.36, including taxes, for depreciation. Plaintiff thus received an ACV payment of $317.18. Plaintiff claimed that he was underpaid on his ACV claim because State Farm depreciated labor, which is intangible and thus not subject to wear, tear, and obsolescence. Further, labor should not have been depreciated because it was not susceptible to aging or wearing and its value did not diminish over time.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Common Law Indemnity Claim Affirmed on Justifiable Beliefs
June 30, 2016 —
Rick Erickson – Snell & Wilmer Real Estate Litigation BlogYesterday, the Arizona Court of Appeals issued an interesting opinion in Hatch Development v. Solomon. Hatch illustrated two key points in real estate and construction litigation: (1) a contractor’s indemnity does not always require an expressly written obligation; and (2) when facts are undisputed that a contractor is solely at fault for a construction defect, a property owner can be indemnified after paying a neighboring property owner for damages caused by the contractor’s defective work.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr. Erickson may be contacted at
rerickson@swlaw.com
Excess-Escape Other Insurance Provision Unenforceable to Avoid Defense Cost Contribution Despite Placement in Policy’s Coverage Grant
April 20, 2016 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel, LLPIn Certain Underwriters at Lloyds, London v. Arch Specialty Ins. Co. (No. C072500; filed 4/11/16), a California appeals court found an “other insurance” provision unenforceable to excuse defense contribution between successive primary insurers, regardless of the fact that the limiting language was contained in the policy’s coverage grant.
Certain Underwriters and Arch each insured Framecon over successive policy periods. Framecon was sued by a developer in a series of construction defect actions, and tendered to both insurers. Underwriters agreed to defend under a reservation of rights but Arch declined, citing the wording of its insuring agreement, which stated:
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Condominium Association Responsibility to Resolve Construction Defect Claims
July 23, 2014 —
Nicholas D. Cowie – Maryland Condo Construction Defect Law BlogThe Maryland Court of Special Appeals recently issued an opinion in Greenstein v. Council of Unit Owners of Avalon Court Six Condominium Inc. finding that an association can be sued by its unit owner members if it fails to take timely legal action against a developer. In that case, the association was aware of construction defects, but failed to take action to preserve its claim and then filed a lawsuit against the developer too late, after the statute of limitations expired. As a result, the suit against the developer was dismissed and the association was forced to assess its unit owner members for the $1 million in repair costs. Some of the unit owners then sued their association, seeking to recover the cost of their assessments on the ground that the association was negligent in failing to pursue a timely legal action against the developer.
On appeal, the court was asked to decide whether state law permits owners to sue their condominium association for negligently failing to sue a developer for common element construction defects. The court, in an unpublished opinion, found that an association could be held liable to its members. The court said: “The duty to maintain, repair and replace the common elements together with the exclusive right to initiate litigation regarding the common elements [which was stated in a provision of the association’s bylaws] creates a concomitant obligation on the part of the [association] to pursue recovery from [the developer] on behalf of [the unit owners] for damage to the common elements caused by [the developer’s] negligence, breach of contract or violation of any applicable law.”
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Maryland Condo Construction Defect Law BlogMr. Cowie may be contacted at
ndc@cowiemott.com
Condos Down in Denver Due to Construction Defect Litigation
November 06, 2013 —
CDJ STAFFA new report suggests that fears of construction defect litigation may be the cause of the slump in condo building in the Denver area. The Denver Business Journal reports that the Denver Regional Council of Governments commissioned the study by Economic & Planning Systems. The conclusion of the report was that the only type of condominium likely to be built is high-cost units with high profit margins. This is not good news for the DRCOG, which is seeking to create more affordable housing.
The report found that builders assess the likeliness of being sued “is nearly 100 percent,” that costs of addressing construction defects are 12% higher than at apartment complexes, and that preparing for litigation adds about $15,000 to the cost of a condo unit.
One possible remedy is to reform Colorado’s construction defect laws. Bob Muphy, the mayor of Lakewook and an advocate of construction defect litigation reform, said that he sees “this as a verification of what I’ve been talking about.”
Read the court decisionRead the full story...Reprinted courtesy of
Toolbox Talk Series Recap – Arbitration Motion Practice
August 07, 2023 —
Michael Zehner - The Dispute ResolverIn the June 22, 2023 edition of the Toolbox Talk Series,
Adrian Bastianelli, Peckar & Abramson, P.C., and
Brian Cashmere, Williams Mullen, moderated by Jennifer Millender of the American Arbitration Association (“AAA”), discussed motion practice in arbitration. Specifically, they offered advice on how to choose the right issue for a motion, how to get approval for a motion, how to write the motion, and how to get the arbitrator to grant it. They also discussed the pros and cons of motion writing in arbitration settings.
1. How to choose the “right issue” for a motion in arbitration
The panel discussed what type of issues can, or should, be brought up in a motion in arbitration. Cashmere stated that a clear and concise issue is best for this type of review. For example, statute of limitations, notice, or contract interpretation issues may make great summary judgment or partial summary judgment motions. Essentially, an issue that the arbitrator may resolve via primarily a question of law is more likely to succeed. Bastianelli warned against submitting just any “available” motion, as the practice may turn the arbitrator against you. Both panelists mentioned the need to consider strategy before filing a motion—ask, “how will filing this motion help or hurt reachingArbi final resolution.” Cashmere noted that sometimes the threat of bringing the issue to a hearing can put pressure on the adverse party in a way that is favorable to your client’s goals; possibly even more so than actually submitting the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Zehner, BBG Construction LawMr. Zehner may be contacted at
mzehner@bbglaw.com
ASCE Report Calls for Sweeping Changes to Texas Grid Infrastructure
March 28, 2022 —
C.J. Schexnayder - Engineering News-RecordA just-released detailed analysis of the catastrophic 2021 Texas winter storm finds systemic flaws in the state's electric sector contributed to a “cascade of failures” that overwhelmed its power grid and left millions freezing in the dark.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of