Hirer Not Liable Under Privette Doctrine Where Hirer Had Knowledge of Condition, but not that Condition Posed a Concealed Hazard
December 11, 2023 —
Garret Murai - California Construction Law BlogThe Privette doctrine, so-called because of a case of the same name,
Privette v. Superior Court, 5 Cal.4th 698 (1993), provides a rebuttable presumption that a hirer is not liable for workplace injuries sustained by employees of hired parties. In other words, if a property owner hires a contractor, and one of the contractor’s employees gets injured while working on the property, there is a rebuttable presumption that the property owner is not liable for the employee’s injuries, the rationale being that because the contractor is required to carry workers’ compensation insurance the contractor is in the better position to absorb losses incurred a workplace injury.
There are, however, two widely recognized exceptions to the Privette doctrine. The first, is the Hooker exception, again named after a case of the same name,
Hooker v. Department of Transportation, 27 Cal.th 198 (2002), which provides that a hirer is liable for injuries to a hired parties’ employees, if the hirer retained control over the work being performed, negligently exercised that control, and the negative exercise of that control contributed to the employee’s injury.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Windstorm Exclusion Found Ambiguous
September 10, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe Second Circuit reversed the District Court's issuance of summary judgment to the insurer because a windstorm exclusion was deemed ambiguous. 7001 East 71st Street, LLC v. Continental Cas. Co., 2018 U.S. App. LEXIS 17334 (2nd Cir. June 26, 2018).
A windstorm during Hurricane Sandy caused the roof of 7001 East 71st Street LLC (7001) to tear, allowing rainwater to seep in and damage 7001's "Covered Equipment" as defined by the policy. Continental denied coverage based upon the windstorm exclusion and the district court granted summary judgment to Continental.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Newmeyer & Dillion Named for Top-Tier Practice Areas in 2018 U.S. News – Best Law Firms List
November 02, 2017 —
Newmeyer & Dillion LLPNEWPORT BEACH, Calif. – NOVEMBER 2, 2017 – Prominent business and real estate law firm Newmeyer & Dillion LLP is pleased to announce that U.S. News-Best Lawyers® recognized the firm's Orange County office in its "Best Law Firms" 2018 list, ranking five of its practice areas with its highest ranking possible - Tier 1. These areas include Commercial Litigation, Construction law, Insurance law, Litigation - Construction and Litigation - Real Estate.
"We continue to be honored that our clients and peers recognize the foundational principles this firm was built on - personalized service and achieving the best results possible." said Jeff Dennis, Newmeyer & Dillion's Managing Partner.
Firms included in the 2018 "Best Law Firms" list are recognized for professional excellence with persistently impressive ratings from clients and peers. Achieving a tiered ranking signals a unique combination of quality law practice and breadth of legal expertise.
The 2018 rankings are based on a rigorous evaluation process that includes the collection of client and lawyer evaluations, peer review from leading attorneys in their field, and review of additional information provided by law firms as part of the formal submission process. To be eligible for a ranking, a firm must have a lawyer listed in The Best Lawyers in America, which recognizes the top 4 percent of practicing attorneys in the U.S. More than 21,000 attorneys provided almost 700,000 law firm assessments, and more than 8,0000 clients provided more than 47,000 evaluations.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier, and have been given Martindale-Hubbell Peer Review's AV Preeminent highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Design and Construction Defects Not a Breach of Contract
February 14, 2013 —
CDJ STAFFThe California Court of Appeals tossed out a breach of contract award in Altman v. John Mourier Construction. The decision, which was issued on January 10, 2013, sent the construction defect case back to a lower court to calculate damages based on the conclusions of the appeals court.
The case involved both design issues and construction issues. According to the plaintiffs’ expert, the design plans did not make the buildings sufficiently stiff to resist the wind, and that the framing was improperly constructed, further weakening the structures, and leading to the stucco cracking. Additionally, it was alleged that the roofs were improperly installed, leading to water intrusion. The contractor’s expert “agreed the roofs needed repair, but disputed what needed to be done to repair the roofs and the cost.”
The jury rejected the plaintiffs’ claims of product liability and breach of warranty, but found in their favor on the claims of breach of contract and negligence. The plaintiffs were awarded differing amounts based on the jury’s conclusions about their particular properties.
Both sides sought new trials. JMC, the contractor, claimed that the jury’s verdicts were “inconsistent in that the relieved JMC of liability for strict products liability and breach of warranty, but found JMC liable for breach of contract and negligence.” The plaintiffs “opposed the setoff motion on the ground that the jury heard evidence only of damages not covered by the settlements.” Both motions were denied. After this, the plaintiffs sought and received investigative costs as damages. JMC appealed this amended judgment.
The appeals court rejected JMC’s claims that evidence was improperly excluded. JMC sought to introduce evidence concerning errors made by the stucco subcontractor. Earlier in the trial, JMC had insisted that the plaintiffs not be allowed to present evidence concerning the stucco, as that had been separately settled. When they wished to introduce it themselves, they noted that the settlement only precluded the plaintiffs from introducing stucco evidence, but the trial court did not find this persuasive, and the appeals court upheld the actions of the trial court. Nor did the appeals court find grounds for reversal based on claims that the jury saw excluded evidence, as JMC did not establish that the evidence went into the jury room. Further, this did not reach, according to the court, a “miscarriage of justice.”
The court rejected two more of JMC’s arguments, concluding that the negligence award did not violate the economic loss rule. The court also noted that JMC failed to prove its contention that the plaintiffs were awarded damages for items that were covered in settlements with the subcontractors.
The appeals court did accept JMC’s argument that the award for breach of contract was not supported by evidence. As the ruling notes, “plaintiffs did not submit the contracts into evidence or justify their absence; nor did plaintiffs provide any evidence regarding contract terms allegedly breached.”
The court also did not allow the plaintiffs to claim the full amount of the investigative costs. Noting that the trial court had rational grounds for its decision, the appeals court noted that “the jury rejected most of the damages claimed by plaintiffs, and the trial court found that more than $86,000 of the costs itemized in plaintiffs’ invoices ‘appear questionable’ as ‘investigation’ costs/damages and appeared to the trial court to be litigation costs nonrecoverable under section 1033.5.”
Read the court decisionRead the full story...Reprinted courtesy of
Defense for Additional Insured Not Barred By Sole Negligence Provision
August 11, 2011 —
Tred R. Eyerly - Insurance Law HawaiiA general contractor was entitled to a defense as an additional insured when the underlying complaint did not allege it was solely negligent. A-1 Roofing Co. v. Navigators Ins. Co., 2011 Ill. App. LEXIS 656 (Ill. Ct. App. June 24, 2011).
A-1 was the general contractor for a roof resurfacing job at a high school. Jack Frost Iron Works Inc. (“Frost”) was one of A-1’s subcontractors. Frost had a CGL policy with Navigators Insurance Company under which A-1 was an additional insured.
An employee of Frost’s subcontractor Midwest Sheet Metal Inc. was killed at the job site when a boom-lift he was operating flipped over. The boom-lift had been leased by another Frost subcontractor, Bakes Steel Erectors, Inc. (BSE). The deceased's estate filed suit against A-1, BSE and two other defendants.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
The Regulations on the Trump Administration's Chopping Block
August 02, 2017 —
Pam Radtke Russell - Engineering News-RecordThe Trump administration's next big step toward repealing the controversial Waters of the U.S. (WOTUS) rule is official, with a proposal to rescind the Obama-era regulation appearing in the Federal Register on July 27, setting off a relatively short comment period that will end Aug. 28.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMr. Russell may be contacted at
Russellp@bnpmedia.com
Feds OK $9B Houston Highway Project After Two-Year Pause
March 20, 2023 —
James Leggate - Engineering News-RecordThe Federal Highway Administration has agreed to let a $9-billion Texas highway reconstruction project proceed after a two-year pause over concerns linked to the project’s potential impact on communities along the route, including a lawsuit filed by Harris County to halt contracting, pending a new environmental impact review.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
New Orleans Drainage System Recognized as Historic Civil Engineering Landmark
May 29, 2023 —
The American Society of Civil EngineersNEW ORLEANS, La. – The
American Society of Civil Engineers (ASCE) today recognized the New Orleans Drainage System in New Orleans, Louisiana as a
Historic Civil Engineering Landmark. The project was innovative and largely unprecedented for its time, and the first portions came online in the year 1900. The system now consists of 22 drainage pumping stations and 1,200 miles of network drains, as well as green infrastructure elements to manage stormwater runoff. The infrastructure is largely credited for making the existence of New Orleans possible, and the improved drainage and reduction in standing water contributed to better public health and reduced the number of malaria and typhoid deaths in the early 20th century.
New Orleans' position near the mouth of the Mississippi River made it a vital city for trade and commerce in the U.S. economy since the early 1800s, despite its problematic natural environment. The city was perched along the banks of the Mississippi River and next to Lake Pontchartrain, surrounded by swamps. Improvements to levee systems prevented the city from being inundated with flooding from the river, but rainfall became a pervasive issue as the city's population grew in the 1870s.
The drainage system was first proposed in 1876 to replace primitive "drainage machines," steam-powered paddle wheels that moved water runoff into canals that led to Lake Pontchartrain. The existing system was inefficient and could not handle the frequent, heavy tropical rain New Orleans experiences and could not lift water sufficiently to drain the city. After several proposals, construction on the current drainage system started in 1897, and the first portions of the system came online in 1900. The system drains stormwater through pipes and canals to reach drainage pump stations which expel the water into several bodies of water surrounding the city. Engineers have repeatedly expanded and enlarged the drainage system, including a massive investment in the drainage system authorized by the Southeast Louisiana Urban Flood Control Project and approved by Congress in 1996. The Sewerage and Water Board's green infrastructure plan is a critical partner and complement to the drainage system today.
The New Orleans Drainage System's design has inspired water management system design in communities around America and worldwide. In Southeastern Florida, water management systems using pumps and canals divert excess water away from heavily populated areas during heavy rain, including tropical storms and hurricanes. Engineers in Kolkata, India and Shanghai, China have also used drainage and pumping systems like the ones in New Orleans to assist with water management.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of