As California Faces Mandatory Water Use Reductions How Will the Construction Industry be Impacted?
May 07, 2015 —
Garret Murai – California Construction Law BlogEarlier this month, Governor Jerry Brown issued Executive Order B-29-15, which imposes mandatory water use reductions for the first time in the history of California.
The Executive Order, issued as the state enters its fourth year of severe to exceptional drought, directs the State Water Resources Control Board (“State Water Board”) to impose a 25% reduction on the state’s 400 local water supply agencies which serve 90% of California residents, over the coming year.
The State Water Board has already issued proposed regulations based on informal comments received from the public, and in a “Fact Sheet” issued this weekend, has indicated that it is seeking additional informal comments no later than April 22, 2015, with final proposed emergency regulations to be released on April 28, 2015, which will then be considered by the State Water Board at its meetings on May 5 and 6, 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
The Colorado Court of Appeals Rules that a Statutory Notice of Claim Triggers an Insurer’s Duty to Defend.
October 23, 2012 —
David M. McLain, Higgins, Hopkins, McLain & RoswellGene and Diane Melssen d/b/a Melssen Construction (“Melssen”) built a custom home for the Holleys, during which period of time Melssen retained a CGL insurance coverage from Auto Owners Insurance Company. Soon after completion of the house, the Holleys noticed cracks in the drywall and, eventually, large cracks developed in the exterior stucco and basement slab. Thereafter, the Holleys contacted Melssen, the structural engineer, an attorney, and Auto-Owners, which assigned a claims adjuster to investigate the claim.
In April 2008, the Holleys sent Melssen a statutory notice of claim pursuant to C.R.S. § 13-20-803.5 (“NOC”). In this NOC, the Holleys claimed approximately $300,000 in damages related to design and construction defects. The Holleys also provided a list of claimed damages and estimated repairs, accompanied by two reports from the Holleys’ consultant regarding the claimed design and construction defects. In June 2008, Melssen tendered the defense and indemnity of the claim to Auto-Owners. While Auto-Owners did not deny the claim at that time, it did not inspect the property or otherwise adjust the claim. Thereafter, in October 2008, Auto-Owners sent Melssen a letter denying coverage on the basis that the damage occurred outside of the applicable policy period.
Ultimately, Melssen settled the claims against it for $140,000.
Read the full story…
Reprinted courtesy of David McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes You Just Need to Call it a Day: Court Finds That Contractor Not Entitled to Recover Costs After Public Works Contract is Invalidated
June 29, 2020 —
Garret Murai - California Construction Law BlogJanuary was a tough month in the courts for Hensel Phelps Construction Company. Hot off the heels of Hensel Phelps Construction Co. v. Superior Court, a case concerning the 10-year statute of limitations under Civil Code section 941, comes Hensel Phelps Construction Co. v. California Department of Corrections and Rehabilitation, Case No. B293427 (January 28, 2020), a bid dispute case . . .
The Tale of a Bid, a Bid Protest, and Two Cases
A. The Bid and Bid Protest
On March 15, 2015, the California Department of Corrections and Rehabilitation (CDCR) issues an Invitation for Bid for the HVAC project at the Ironwood State Prison. The deadline to submit bids was April 30, 2015. Hensel Phelps Construction Co. submitted a timely bid and was determined to be the “apparent low bidder” with a bid of $88,160,000.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Court of Appeals Discusses Implied Duty of Good Faith and Fair Dealing in Public Works Contracting
August 17, 2017 —
Lindsay K. Taft - Ahlers & Cressman PLLCThe implied duty of good faith and fair dealing is implied in every contract, including construction contracts. Generally speaking, this implied duty requires parties cooperate with one another so that they each obtain the full benefit of their contracted bargain. Recently, the Court of Appeals (Division II) in Nova Contracting, Inc. v. City of Olympia discussed this duty’s application to a public works contract.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Commercial Development Nearly Quadruples in Jacksonville Area
December 04, 2013 —
CDJ STAFFConstruction is up in the Jacksonville area, and no sector is doing better than commercial construction. During the first ten months of 2012, there was $21.2 million of commercial construction, but during the first ten months of 2013, there was been $73.2 million of commercial construction, helped along by a $13.7 million medical complex.
In addition to the massive growth in commercial construction, residential construction is up, but by a comparatively modest 52%.
Read the court decisionRead the full story...Reprinted courtesy of
Athletic Trainers Help Workers Get Back to the Jobsite and Stay Healthy After Injury
August 12, 2024 —
Bryan Lockhart - Construction ExecutiveThere are a number of factors on an active jobsite that can lead to workplace injuries. Heavy machinery, fast-moving equipment, material handling, loud noises and more can create safety hazards and make it easy to lose focus or become distracted. Additionally, the movements workers have to do in their roles—such as lifting or pushing objects or crouching low to the ground for extended periods—can add strain to the body if not done correctly.
The goal is always to minimize the risk of injury, and yet, incidents still occur. According to 2020 Bureau of Labor Statistics data, slips, trips and falls are the most common injuries, accounting for 18% of non-fatal work injuries resulting in days away from work. When workers are injured, it can lead to downtime, lost productivity on the site and workers’ compensation claims.
Employers and site leaders can take various approaches to help workers return to the jobsite safely and effectively and keep them healthy once they return. Introducing an onsite clinic and athletic trainers can help prevent injuries, improve worker health, get people back to work effectively and keep them healthy in the long run. Here are three ways athletic trainers help workers get back to the job and improve their overall health.
Reprinted courtesy of
Bryan Lockhart, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Baker Intl. Settles Federal Pay Bias Allegations
February 26, 2024 —
James Leggate - Engineering News-RecordMichael Baker International Inc. agreed to pay $122,299 in back wages as part of an agreement with the U.S. Dept. of Labor to resolve allegations that the engineer-consultant paid women in four job titles less than their male counterparts.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of