Top 10 Construction Contract Provisions – Changes and Claims
November 03, 2016 —
James R. Lynch – Ahlers & Cressman PLLCThis is the seventh post in our “Top 10 Construction Contract Provisions” series. Prior posts discussed
Price and Payment,
Liquidated Damages,
Consequential Damages – Part I and
Part II,
Indemnity,
Scope of Work, and
Flow-Down Provisions.
Today’s topic, Changes and Claims, is a contender for the top spot on our list, for both day-to-day impact on the job and importance in disputes. In fact, these provisions[i] are so variable and are involved in so many reported construction law decisions, that this post will not attempt to survey all their various forms, uses, or potential legal ramifications, but instead focuses on bottom line “best practices”—questions to consider as a general contractor, subcontractor, or owner when drafting, negotiating, or managing the Changes and Claims provisions of a contract. There is no “ideal” here, and the changes and claims procedures should be suited to the project, owner, contractor(s), likely issues, and other project-specific considerations. Key considerations include the following:
1. How prescriptive is the Change Order process? At one end of the spectrum, a Change Order provision may include requirements for written direction and request by the owner and formal response by the contractor, with pricing and specific supporting data or documentation, in addition to strict timelines for response, execution, and performance, precise methods to determine the resulting contract adjustment, limits on the type or extent of adjustment, or terms defining the effect of a signed Change Order, e.g. to what extent related claims or impacts might be extinguished. At the other end of the spectrum, the Change Order provision might simply recognize that the owner may direct changes, and the parties intend to document the directions and resulting compensation in a Change Order, with no further elaboration. There is no universal ideal on this spectrum. A highly defined and prescriptive process may be appropriate for a complex, high value, multi-stakeholder project on which significant changes are likely. The same process would be an inefficient waste of resources on a small and simple project where significant changes are unlikely and the parties would be unlikely to comply with more formal procedures.
Read the court decisionRead the full story...Reprinted courtesy of
James R. Lynch, Ahlers & Cressman PLLCMr. Lynch may be contacted at
jlynch@ac-lawyers.com
Formal Request for Time Extension Not Always Required to Support Constructive Acceleration
April 25, 2022 —
David Adelstein - Florida Construction Legal UpdatesDoes a constructive acceleration claim require the contractor to always request an extension of time which is then denied by the owner? While this is certainly the preference and the contractor should be requesting an extension of time as a matter of course for an excusable delay, the answer is NO! in certain circumstances. This is conveyed in the factually detailed case discussed below where a formal request for an extension of time was not required for the contractor to support its constructive acceleration claim.
But first, what is constructive acceleration:
Constructive acceleration “occurs when the government demands compliance with an original contract deadline, despite excusable delay by the contractor.” The Federal Circuit in Fraser defined the elements of constructive acceleration as follows:
(1) that the contractor encountered a delay that is excusable under the contract; (2) that the contractor made a timely and sufficient request for an extension of the contract schedule; (3) that the government denied the contractor’s request for an extension or failed to act on it within a reasonable time; (4) that the government insisted on completion of the contract within a period shorter than the period to which the contractor would be entitled by taking into account the period of excusable delay, after which the contractor notified the government that it regarded the alleged order to accelerate as a constructive change in the contract; and (5) that the contractor was required to expend extra resources to compensate for the lost time and remain on schedule.
Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, *42 (Fed.Cl. 2022) quoting Fraser Constr. Co. v. U.S., 384 F.3d 1354, 1361 (Fed. Cir. 2004) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
ASCE Statement on Hurricane Milton and Environmental Threats
October 15, 2024 —
Feniosky Peña-Mora, P.E., President - American Society of Civil EngineersWASHINGTON, DC. – On the heels of the tragic damage caused by Hurricane Helene throughout the Southeast, Floridians were struck by another major hurricane, Milton, less than two weeks later. Our hearts go out to those impacted again by this storm through property damage, lack of water access, power outages, or worse, loss of life, all before getting a chance to recover from Helene. Civil engineers are dedicated to protecting the public with projects that can lessen the impacts of these storms, and we are eager to help communities rebuild as quickly as possible following events like Milton and Helene.
Although we do not yet know the full scope of destruction caused by Hurricane Milton, severe weather, including compound flooding events, are increasing regularly and pose a great risk to our safety and economic vitality. While so many eyes are fixated on hurricanes impacting the Southeast, wildfires are burning across several western states, including the Elk Fire in Wyoming, the largest wildfire the Bighorn National Forest has experienced in more than a century, now spanning over 75,000 acres as the region is experiencing unusually hot and dry weather and strong winds that are helping this fire to spread rapidly. The climate impacts we are accustomed to – wildfires in the West and hurricanes in the Southeast – are getting stronger, and now environmental challenges are occurring in areas we wouldn't suspect, such as Hurricane Helene striking mountain communities in Western North Carolina that have been labeled as "climate safe-havens," and Texas dealing with annual winter storms.
ASCE is a leader in codes and standards development and has created an
easy-to-understand toolkit for legislators and the public to learn the benefits of these up-to-date standards and determine when and how to adopt them, making our built environment more resilient to natural catastrophes. ASCE's flagship standard,
ASCE/SEI 7-22, recently underwent the most significant update to its
flooding chapter to ensure structures following this standard are prepared for 500-year flood events.
Read the court decisionRead the full story...Reprinted courtesy of
JAMS Announces Updated Construction Rules
June 21, 2021 —
JAMSIrvine, Calif. – JAMS, the largest private provider of
alternative dispute resolution (ADR) services worldwide, is pleased to announce it has revised and updated its
Construction Arbitration Rules & Procedures and
Expedited Construction Arbitration Rules & Procedures, effective June 1. These Rules were updated to reflect the latest developments and trends in
construction arbitration.
In response to the transition to virtual and hybrid proceedings, Rule 22 makes explicit the arbitrator’s full authority to conduct the hearing in person, virtually or in a combined form, as well as with participants in more than one geographic location. To support access to case documents throughout the proceedings, Rule 8 aligns electronic filing and service with the functionality of JAMS Access, a centralized, secure online case management platform.
Additional rules were created or revised to clarify and strengthen the authority of the arbitrator. Key changes include allowing an arbitrator to withhold approval of any intended change in party representation that could compromise the proceedings or the final award, to set a hearing without consulting a party that he or she reasonably believes will not participate and to permit a party to file a motion for summary disposition of a claim if the arbitrator believes that party has demonstrated the motion is likely to succeed.
About JAMS – Local Solutions. Global Reach.
Founded in 1979, JAMS is the largest private provider of alternative dispute resolution services worldwide. JAMS successfully resolves and manages business and legal disputes by providing efficient, cost-effective and impartial ways to overcome barriers at any stage of conflict. JAMS offers customized in-person, virtual and hybrid resolution services locally and globally through a combination of industry-specific experience, first-class client service, the latest technology and highly trained mediators and arbitrators.
Read the court decisionRead the full story...Reprinted courtesy of
JAMS
CSLB Releases New Forms and Announces New Fees!
April 05, 2017 —
Garret Murai – California Construction Law BlogThe California Contractors State License Board (CSLB”) has issued new application forms. Effective May 1, 2017, the CSLB will only accept forms with a revision date of October 2017 (Pro tip: see bottom of form to verify it indicates a revision date of “10/16” or later).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Construction Defect Bill Introduced in California
June 10, 2011 —
CDJ STAFFLinda Halderman (R-Fresno) has introduced a bill which would require lawyers soliciting clients for construction defect cases to provide their prospective clients with a statement including that sellers may be required to disclose that they were engaged in a construction lawsuit. Further, the bill would require lawyers to disclose that they cannot guarantee financial recovery.
Halderman was quoted by The Business Journal as saying, “Lawsuit abuse has been very damaging, especially to homeowners in the Valley.” Halderman hopes that her bill will discourage class action lawsuits against builders and that this will protect jobs in the construction industry.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Appeals Court Upholds Decision by Referee in Trial Court for Antagan v Shea Homes
May 10, 2012 —
CDJ STAFFIn the case Antangan v. Shea Homes Ltd. Partnership (Cal. App., 2012), Plaintiffs appealed “an order vacating a judgment and entering a modified judgment in their construction defect action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership,” while the Defendant, Shea Homes Limited Partnership (Shea Homes) appealed “an order of the judicial referee denying its motion to strike and tax costs.”
On the Antagon issue, the appeals court concluded that “the trial court did not err by vacating and modifying its judgment so that the cost of referee’s fees would be equally divided by the parties and consistent with a prior stipulation they filed in court.”
On the Shea Homes issue, the appeals court concluded: “1) the judicial referee did not err by ruling that plaintiffs’ offers to compromise (§ 998) were validly served on Shea Homes’ counsel, 2) the offers substantially complied with statutory requirements, 3) the offers were not required to be apportioned, and 4) the referee’s award of $5,000 as costs for a person assisting plaintiffs’ counsel was not an abuse of discretion.” The appeals court affirmed the judgment.
Here is a brief history of the trial case: “Plaintiffs Chito Antangan, Jimmy Alcova and other homeowners brought an action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership for damages alleging that the properties they purchased from these ‘developer defendants’ were defective. Plaintiffs claimed numerous construction defects required them ‘to incur expenses’ for ‘restoration and repairs’ and the value of their homes had been diminished.”
In response, Shea Homes filed a motion for an order to appoint a judicial referee. The motion was granted and it was ruled that “a referee would ‘try all issues’ and ‘report a statement of decision to this court.’”
On May 10, 2010 the judicial referee (Thompson) “awarded plaintiffs damages and various costs, and ruled that ‘Shea Homes shall bear all of the Referee’s fees.’” The latter ruling would become a matter for contention later on.
In July of 2010, the plaintiffs “sought, among other things, $54,409.90 for expert fees, and $14,812.50 for the services of Melissa Fox for ‘exhibit preparation & trial presentation.’ Shea Homes filed a motion to strike and/or tax costs claiming: 1) Fox was a paralegal, 2) plaintiffs were not entitled to attorney’s fees, and 3) the fees for Fox’s services were an indirect and improper method to obtain attorney’s fees. The referee disagreed and awarded $5,000 for Fox’s services. The referee also ruled that plaintiffs had properly served valid offers to compromise (§ 998) on Shea Homes’ counsel in 2009. He said those offers to defendants in the case at that time did not have to be apportioned.”
“Antangan contends the trial court erred when it vacated and modified its original judgment, which ordered Shea Homes to pay all the referee’s fees. We disagree.”
Antagon contended that the trial court erred when it vacated and modified its original judgment regarding Shea Homes paying the referee’s fees. The appeals court disagreed: “A trial court has inherent authority to vacate or correct a judgment that is void on its face, incorrect, or entered by mistake. (§ 473; Rochin v. Pat Johnson Manufacturing Co. (1998),67 Cal.App.4th 1228; Olivera
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
AB5 Construction Exemption – A Checklist to Avoid Application of AB5’s Three-Part Test
February 18, 2020 —
Blake Dillion - Payne & Fears LLPConstruction companies have a unique opportunity to avoid the application of the restrictive new independent contractors law that took effect this year. This article provides a checklist that will help construction companies determine whether their relationships with subcontractors qualify for this exemption.
California’s Assembly Bill 5 (“AB5”), which went into effect Jan. 1, 2020, enacts into a statute last year’s California Supreme Court decision in
Dynamex Operations West, Inc. v. Superior Court, 4 Cal. 5th 903 (2018), and the Court’s three-part standard (the “ABC test”) for determining whether a worker may be classified as an employee or an independent contractor.
Certain professions and industries are potentially exempt from this standard, including the construction industry. The ABC test does not apply to the relationship between a contractor and an individual performing work pursuant to a subcontractor in the construction industry, if certain criteria are met. In order for the “construction exemption” to apply, the contractor must demonstrate that all of the following criteria are satisfied.
- The subcontract is in writing;
- The subcontractor is licensed by the Contractors State License Board and the work is within the scope of that license;
- If the subcontractor is domiciled in a jurisdiction that requires the subcontractor to have a business license or business tax registration, the subcontractor has the required business license or business tax registration;
- The subcontractor maintains a business location that is separate from the business or work location of the contractor;
- The subcontractor has the authority to hire and to fire other persons to provide or assist in providing the services;
- The subcontractor assumes financial responsibility for errors or omissions in labor or services as evidenced by insurance, legally authorized indemnity obligations, performance bonds, or warranties relating to the labor or services being provided; and
- The subcontractor is customarily engaged in an independently established business of the same nature as that involved in the work performed.
The contractor must be able to establish each of the above criteria for the construction exemption to apply. If the contractor is successful, the long standing multi-factor test for determining independent contractor vs. employee status as described in
S.G. Borello & Sons, Inc. v. Dep’t of Industrial Relations, 48 Cal. 3d 341 (1989) will apply.
You should review your processes and procedures for engaging subcontractors to ensure that you can satisfy the above criteria. If you have questions about the application of AB5, the construction exemption, or the
Borello factors, you should speak with an attorney.
Read the court decisionRead the full story...Reprinted courtesy of
Blake A. Dillion, Payne & FearsMr. Dillion may be contacted at
bad@paynefears.com