No Coverage for Faulty Workmanship Causing Property Damage to Insured's Product Only
October 07, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Nebraska court found there was no coverage for rebar that did not meet specifications and did not cause property damage to other portions of the construction project. Drake-Williams Steel, Inc. v. Cont'l Cas. Co., 2016 Neb. LEXIS 116 (Neb. Aug. 5, 2016).
The general contractor was hired by the city to build an arena. Drake-Williams Steel, Inc. (DWS) was hired to supply rebar for the arena. The rebar was improperly bent when it was fabricated by DWS and did not conform to the terms of the contract. The rebar was incorporated into three components of the arena: the columns, the grade beams, and the pile caps. The pile caps were made of concrete with reinforcing rebar and were installed below ground level on top of the concrete piles that extended to the bedrock. The grade beams were also made of concrete and rebar. The beams formed an oval around the arena and connected different pile caps together and were also installed below ground level. No corrections were made to the grade beams.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Risk Management and Contracting after Hurricane Irma: Suggestions to Avoid a Second Disaster
September 14, 2017 —
Stephen H. Reisman, Gary M. Stein & Adam P. Handfinger – Peckar & Abramson, P.C.Peckar & Abramson attorneys have assisted contractors in the immediate aftermath of several Hurricanes, including Andrew in 1992, Wilma in 2005, Ike in 2008, and Sandy in 2012. Based on this experience, we offer some post-storm strategies for contracting and risk management in three situations:
- Ongoing projects in the area directly impacted by the storm;
- Projects remote from the storm-impacted areas, but which may be affected by material or labor shortages; and
- Requests for assistance in recovery/clean-up/rebuild eff orts, which would be new projects.
Projects Directly Impacted By Hurricane Irma:
1. Immediately review each Owner contract to determine what notices are required for delays and/or extra costs arising from the storm. Contract notice requirements and time limits vary, whether for force majeure or other similar time and compensation rights. There is no effective one-size-fits-all solution. While the initial notice letters will likely look very similar, you should make sure that each is sent as required by the contract. Check each contract’s requirements for particulars regarding content, the form of delivery, and parties and individuals designated to receive the letters as well as carbon copy recipients like the architect. Follow-up notices and time periods differ from contract to contract and should be tracked so that if, for example, a follow-up notice is required in a week per the contract terms, it is tracked to ensure compliance.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Stephen H. Reisman,
Gary M. Stein and
Adam P. Handfinger
Mr. Reisman may be contacted at sreisman@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Court Addresses Coverage Owed For Subcontractor’s Defective Work
May 06, 2019 —
Brian Bassett - TLSS Insurance Law BlogIn Acuity Ins. Co. v. 950 W. Huron Condo. Assoc’n, 2019 IL App (1st) 180743, the Illinois Court of Appeals held that a claim against a subcontractor for damage caused to property outside the scope of its work satisfied the insuring agreement of a CGL policy.
The condominium association for the building located at 950 West Huron Street in Chicago, Illinois (“the Association”), sued its general contractor and construction manager Belgravia Group, Ltd., and Belgravia Construction Corporation (collectively “Belgravia”). The Association sought to recover for alleged defects from Belgravia’s unworkmanlike construction of the building that permitted water to permeate and cause damage.
In the Association’s complaint, it alleged that in June 2002, after the Association took possession of the building but prior to the completion of construction, Belgravia became aware of numerous conditions and defects, including extensive water infiltration of the building. After discussing the issues with Belgravia, the Association claimed that Belgravia retained contractors to provide cosmetic fixes. However, this did not address the problems and defects. The Association alleged that it spent a substantial amount of money to identify and correct the damage and that it would incur additional costs for future repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Bassett, Traub LiebermanMr. Bassett may be contacted at
bbassett@tlsslaw.com
Homeowners Sued for Failing to Disclose Defects
December 30, 2013 —
CDJ STAFFThe Madison-St. Clair Record reports that a Wisconsin homeowner has sued the former owners of her home, alleging that they failed to disclose a defect. According to the lawsuit, David and Doris Stephens informed Jennifer Davies that a basement window well had previously leaked, but that the problem had been fixed and not recurred in three years. Ms. Davies had problems with the leaks after she moved in.
And while the window was the only defect the Stepehenses reported, Ms. Davies found problems with the home’s heating and air conditioning as well. Though she paid only $112,000 for the home, Ms. Davies is suing for $400,000 for the repairs, loss of property value, and the court fees.
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Faulty Workmanship Based Upon Exclusion for Contractual Assumption of Liability
August 06, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Supreme Court for West Virginia determined the policy's contractual assumption exclusion barred coverage for the general contractor based upon claims of faulty workmanship. J.A. St & Assocs. v. Bitco Gen. Ins. Corp., 2019 W. Va. LEXIS 205 (May 1, 2019).
J.A. Street & Associates, Inc. entered a contract with the developer, Thundering Herd Development, L.L.C., to build a commercial shopping center on seventy-eight acres of land. Street agreed to oversee the site preparation for the development and the construction of many of the buildings. Thundering Herd retained an engineering firm, S&ME, Inc. to do geotechnical exploration and to provide advice regarding land preparation for the shopping center. Thundering Heard also entered an agreement with the Target Corporation to construct a store on a pad to be prepared at the shopping center.
Street hired subcontractors to prepare the site by grading the land and installing fill material. A slope was constructed at the rear of the proposed Target site, but it failed, causing a landslide, damage to the pad, and damage to adjacent property owned by a third party. Thundering Heard incurred $721,875 in additional costs to repair this slope, reconstruct the Target site, and compensate the neighbor for the damage to the adjacent property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
California MCLE Seminar at BHA Sacramento July 11th
June 11, 2014 —
Kimberly Albarq-CDJ STAFFThere are just three weeks remaining to sign up for Bert L. Howe & Associate’s next California MCLE seminar, UNDERSTANDING CONSTRUCTION DEFECT LITIGATION.
This activity will be presented on Friday, July 11th at noon, at BHA’s Sacramento office:
2520 Venture Oaks Way
Suite 435
Sacramento, CA 95833
There is no cost for attendance at this seminar and lunch will be provided.
This course has been approved for Minimum Continuing Legal Education credit by the State Bar of California Committee on MCLE in the amount of 1.0 credit hours, of which 0.0 credit hours will apply to legal ethics/professional responsibility credit. The seminar will be presented by Don MacGregor, general contractor and project manager.
Water intrusion through doors, windows and roofing systems, as well as soil and foundation-related movement, and the resultant damage associated therewith, are the triggering effects for the vast majority of homeowner complaints today and serve as the basis for most residential construction defect litigation. The graphic and animation-supported workshop/lecture activity will focus on the residential construction process from site preparation through occupancy, an examination of associated damages most often encountered when investigating construction defect claims, and the inter-relationships between the developer, general contractor, sub trades and design professionals. Typical plaintiff homeowner/HOA expert allegations will be examined in connection with those building components most frequently associated with construction defect and claims litigation.
The workshop will examine:
* Typical construction materials, and terminology associated with residential construction
* The installation process and sequencing of major construction elements, including interrelationship with other building assemblies
* The parties (subcontractors) typically associated with major construction assemblies and components
* An analysis of exposure/allocation to responsible parties.
Attendance at THE UNDERSTANDING CONSTRUCTION DEFECT LITIGATION seminar will provide the attendee with:
* A greater understanding of the terms and conditions encountered when dealing with common construction defect issues
* A greater understanding of contractual scopes of work encountered when reviewing construction contract documents
* The ability to identify, both quickly and accurately, potentially responsible parties
* An understanding of damages most often associated with construction defects, as well as a greater ability to identify conditions triggering coverage
To register for the event, please email Don MacGregor at dmac@berthowe.com. If you have any questions, please feel free to contact Don at (800) 482-1822 (office) or (714) 713-4956 (cell).
Read the court decisionRead the full story...Reprinted courtesy of
Properly Trigger the Performance Bond
January 05, 2017 —
David Adelstein – Florida Construction Legal UpdatesA performance bond is a valuable tool designed to guarantee the performance of the principal of the contract made part of the bond. But, it is only a valuable tool if the obligee (entity the bond is designed to benefit) understands that it needs to properly trigger the performance bond if it is looking to the bond (surety) to remedy and pay for a contractual default. If the performance bond is not properly triggered and a suit is brought upon the bond then the obligee could be the one materially breaching the terms of the bond. This means the obligee has no recourse under the performance bond. This is a huge downside when the obligee wanted the security of the performance bond, and reimbursed the bond principal for the premium of the bond, in order to address and remediate a default under the underlying contract.
A recent example of this downside can be found in the Southern District of Florida’s decision in Arch Ins. Co. v. John Moriarty & Associates of Florida, Inc., 2016 WL 7324144 (S.D.Fla. 2016). Here, a general contractor sued a subcontractor’s performance bond surety for an approximate $1M cost overrun associated with the performance of the subcontractor’s subcontract (the contract made part of the subcontractor’s performance bond). The surety moved for summary judgment arguing that the general contractor failed to property trigger the performance bond and, therefore, materially breached the bond. The trial court granted the summary judgment in favor of the performance bond surety. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dma@katzbarron.com
Real Estate & Construction News Roundup (9/4/24) – DOJ Sues RealPage, Housing Sales Increase and U.S. Can’t Build Homes Fast Enough
October 07, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, environmental regulations tighten for commercial properties, Wells Fargo sells most of its commercial mortgage services business, first-time home buyers struggle with housing affordability, and more!
- The U.S. Department of Justice announced that it is suing the real estate company RealPage, saying it engaged in a price-fixing scheme to drive up rents. (Jennifer Ludden, NPR)
- As environmental regulations for commercial buildings and properties tighten across the U.S., green leases and technologies offer owners and operators opportunities to reduce their portfolios’ carbon footprints, generate cost savings and further align with ESG goals. (Nish Amarnath, Construction Dive)
- Wells Fargo & Co. agreed to sell most of its commercial mortgage servicing business to Trimont LLC, ceding the title of biggest US commercial and multifamily mortgage servicer to the Atlanta-based firm. (Hannah Levitt and Scott Carpenter, Yahoo)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team