Government Claims Act Does Not Apply to Actions Solely Seeking Declaratory Relief and Not Monetary Relief
March 25, 2024 —
Garret Murai - California Construction Law BlogPerhaps it should come as no surprise, but public entities get special treatment under the law, and when filing a claim against a public entity, in most cases, a claimant is required to file a claim with the public entity before filing suit under the Government Claims Act (Gov. Code §810 et seq.).
But, as the next case demonstrates, that’s not always the case. In Stronghold Engineering Incorporated v. City of Monterey, 96 Cal.App.5th 1203 (2023), the 6th District Court of Appeals examined whether a public works contractor that alleged an extended overhead claim was required to file a Government Claims Act claim before filing suit when its initial complaint was limited to a claim for declaratory relief.
The Stronghold Case
In December 2015, general contractor Stronghold Engineering Incorporated entered into a construction contract with the City of Monterey for the renovation of the City’s conference center and an adjacent city-owned plaza. The construction contract provided that any modification to the construction contract had to be approved by the City through a written change order. No surprise there.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Deferred Maintenance?
December 17, 2024 —
Daniel Lund III - LexologyA Tennessee-based “outsourced maintenance vendor” to an engine company filed suit in Louisiana state court seeking to recover nearly $150,000 on “open account,” for work previously performed. The engine company removed the case to the Federal District Court in New Orleans and asserted as a defense that the vendor lacked a proper Louisiana construction contractor’s license. The engine company filed a motion for summary judgment based on the defense.
Under Louisiana law, a contract between parties is “absolutely null”--considered to have never existed--where one of the parties performed services without a required Louisiana contractor’s license, and the combined work reaches a $50,000 threshold. The engine company asserted that the vendor performed typical construction contractor work, including plywood flooring, applied epoxy to concrete flooring, erected part of a commercial carport, undertook certain heavy demolition, and installed fences, guardrails, and wire racks.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Recent Supreme Court Decision Could Have Substantial Impact on Builders
January 23, 2023 —
Cassidy Ingram - Ahlers Cressman & SleightOn October 27, 2022, the Washington State Supreme Court issued a decision which could have a substantial impact on the enforceability of contract clauses that require litigation to be commenced within a stated period of time from project completion. In Tadych v. Noble Ridge Construction, Inc.,the Supreme Court held that the contractual one-year statute of limitations for bringing claims against the contractor was substantively unconscionable and reversed the Court of Appeals.
In Tadych, plaintiff owners (the Tadychs) contracted with defendant contractor (Noble Ridge Construction, Inc., or NRC) for the construction of a custom home in 2012. The contract included a one-year claim limitations clause that required claims to be raised within a one year period from project completion and that any claims not raised during the one-year period would be waived. In December 2013, as the project neared completion, the Tadychs met with NRC to identify any outstanding project issues. The Tadychs noted several, including rainwater pools at the landing at the bottom of the stairs and several nicks and cracks on the stucco exterior walls.
The Tadychs moved into the home on April 8, 2014, and the City of Seattle Department of Planning and Development conducted its final site inspection on April 15 and approved the residence for occupancy on April 23. In January or February of 2015, the Tadychs began to notice a shift in their home. In February of 2015, the Tadychs engaged the Construction Dispute Resolution (CDR) to review NRC’s work. CDR raised concerns about the adequacy of the home’s construction and prepared a written report in March 2015 indicating several deviations from the architectural plans and building codes. The Tadychs sent this report to NRC, who assured the Tadychs that NRC’s work followed all requirements and rejected any claims that there were deviations from the plans. The Tadychs continued to notice issues with the home through October 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Cassidy Ingram, Ahlers Cressman & SleightMs. Ingram may be contacted at
cassidy.ingram@acslawyers.com
NY Gov. Sets Industry Advisory Council to Fix Public Contracts Process
February 01, 2022 —
James Leggate - Engineering News-RecordA New York construction industry advisory group, created under a law Gov. Kathy Hochul signed in December, will study and recommend adjustments to state public contracting to address damages incurred by contractors, subcontractors and others because of payment delays on public projects.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
New Mexico Architect Is Tuned Into His State
February 08, 2021 —
David M. Brown - Engineering News-RecordFor 40-plus years, Van Gilbert has combined his love for the topography, history and culture of New Mexico with an equally passionate dedication to designing not just structures, but buildings that help create communities.
Reprinted courtesy of
David M. Brown, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Preparing Your Business For Internal Transition
October 14, 2019 —
Stephen P. Katz, Esq. - ConsensusDocsWhen is it right to start thinking about succession planning and preparing a construction company for transition? Many would agree – in concept, at least – that serious thought regarding succession and transition planning should begin at a company’s inception and be revisited throughout its lifecycle, but as a practical matter, it is frequently not part of the mindset when growing a business. This article explores issues that construction company owners should consider in order to achieve smooth transition of ownership and control. We will address three critical questions:
- What happens to the business when an owner retires;
- In the event an owner(s) become disabled; and,
- Unplanned exit/owner pre-deceases her/his exit from the company
Owners who do not plan carefully for transition are often faced with the less than appealing option of liquidating their business for much less than its value, or by closing the business with no return upon that event. However, those who plan carefully can realize the value of their life’s work, pass the business to the next generation and see their legacy continue.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen P. Katz, Esq., Peckar & Abramson, P.C.Mr. Katz may be contacted at
skatz@pecklaw.com
“But I didn’t know what I was signing….”
May 30, 2018 —
Bobby Kethcart - Snell & Wilmer Real Estate Litigation BlogIn real estate cases—which frequently involve long purchase agreements, loan documents, personal guarantees, deeds of trust, etc.—we’ve likely all had a client or opposing party who trots out the line that they didn’t know what they were signing, or they didn’t read or understand what they were signing, so the document shouldn’t be enforced according to its terms.
Most of us instinctively believe the claim is a loser: You signed the document, you’re bound by it.
But is this actually right?
Well, we did some digging. Here is the Arizona law on the subject:
Nationwide Resources Corp. v. Massabni, 134 Ariz. 557, 658 P.2d 210 (App. 1982):
“A mistake of only one of the parties to a contract in the expression of his agreement or as to the subject matter does not affect its binding force and ordinarily affords no ground for its avoidance, or for relief, even in equity.”
“A manifestation of acceptance to the offeror or his agent forms a contract regardless of the intent of the acceptor.”
Read the court decisionRead the full story...Reprinted courtesy of
Bobby Kethcart, Snell & WilmerMr. Kethcart may be contacted at
rkethcart@swlaw.com
Bad Faith and a Partial Summary Judgment in Seattle Construction Defect Case
February 10, 2012 —
CDJ STAFFThe US District Court of Washington has issued a ruling in the case of Ledcor Industries v. Virginia Surety Company, Inc. Ledcor was the builder of a mixed-use real estate project in Seattle called the Adelaide Project. Ledcor purchased an insurance policy from Virginia Surety covering the project. After the completion of the project, Ledcor received complaints of construction defects from the homeowners, which they forwarded to Virginia Surety.
Virginia Surety denied coverage on several grounds. Absent any lawsuit, Virginia claimed that there was “not yet any duty to defend or indemnify.” Further, as the policy commenced ten days after work on the project was substantially completed, Virginia cited a provision in the policy that excluded coverage for damage that occurred before the policy began. As problems included water intrusion, Virginia noted an exclusion for fungal damage. Finally, Virginia noted that it was not clear whether damage was due to Ledcor’s own actions.
The homeowners sued over the construction defects. Ledcor settled these suits before trial. In this, they were defended by, and settlements were paid by American Home, another of Ledcor’s insurers. Ledcor claims that Virginia Surety acted in bad faith by denying coverage and by its failure to investigate the ongoing nature of the work at the project.
The judge determined that Virginia Surety acted in bad faith when it invoked the fungus exclusion. Virginia noted that fungal damage “‘would have been’ referenced in the list of construction defects,” however, the HOAs claimed only “water stains” and “water damage,” and made no mention of mold or fungus. The court found that Virginia Surety “was not entitled to deny coverage simply because it may have suspected that mold or fungus damage existed.” The court noted that further proceedings would be needed to determine what portion of the settlement Virginia is obligated to pay.
The court found that there were matters of fact to be determined on the further issues in the case. The judge wrote that although Virginia acted in bad faith in invoking the fungus exclusion, it still had to be determined if they were in breach of contract by failing to defend Ledcor. Ledcor still needs to show that the damages claimed by the HOA were due to work actually covered by Virginia Surety.
Ledcor made an additional claim that Virginia Surety violated Washington’s laws concerning the insurance industry. Here, the court noted that the improper exclusion for fungus issues “constitutes a per se unfair trade practice.” Six other claims were made under this law. The court found that Virginia Surety did not misrepresent “pertinent facts or insurance policy provisions.” It also issued its denial letter promptly, satisfying the fifth provision. However, Virginia Surety did violate the second provision, in that it failed “to acknowledge and act reasonably promptly upon communications with respect to claims.” Two other issues could not be determined.
Judge Martinez’s decision granted a summary judgment to Ledcor on the issue of bad faith. An additional summary judgment was granted that Virginia Surety violated Washington’s Insurance Fair Conduct Act. Judge Martinez did not grant summary judgment on any of the other issues Ledcor raised.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of