Stella Pulman - Gravel2Gavel Construction & Real Estate Law BlogThe looming decommissioning liabilities of offshore energy producers have been a focus of the federal government in recent years. One recent case out of the U.S. Court of Federal Claims, Taylor Energy v. United States, highlights the tension between the federal government’s desire to maintain financial security for decommissioning activities, and that of an operator whose security is tied up indefinitely while the government awaits technological advances to allow for safe decommissioning.
The case relates to a trust agreement between Taylor Energy and the United States, established to secure Taylor’s decommissioning liabilities for 28 wells in the Gulf of Mexico. Taylor completed certain decommissioning work for which it was reimbursed by the trust. However, with over $400 million remaining in the trust, Taylor and the Bureau of Safety and Environmental Enforcement (BSEE) concluded that the ecological benefits of further decommissioning would be outweighed by the ecological risks. But despite recognizing that the limitations of current technology made the environmental impacts of further decommissioning work unjustifiable, the BSEE declined to release Taylor from its decommissioning obligations and instead decided to await “changes in technology and a better understanding of the undersea environment.” Because Taylor’s decommissioning obligations remained in place, the U.S. refused to release the remaining funds in the trust.
Taylor claimed that the United States should release the remaining funds in the trust because “decommissioning the remaining wells is not ‘currently technologically feasible.’” Taylor asserted that Louisiana law applied to the trust agreement, and that under Louisiana law every contract must be completed within an ascertainable term. By holding the trust funds until decommissioning was complete, Taylor argued that the government was essentially holding the funds in perpetuity given the technological infeasibility of completing decommissioning. Taylor also asserted that the agreement was premised on an impossibility (the full decommissioning of the wells), and/or a mutual mistake of the parties (that the wells could be decommissioned).
Read the court decisionRead the full story...Reprinted courtesy of
Stella Pulman, PillsburyMs. Pulman may be contacted at
stella.pulman@pillsburylaw.com
New York Labor Laws and Action Over Exclusions
February 01, 2021 —
Theresa A. Guertin & Ashley McWilliams - Saxe Doernberger & Vita, P.C.One of the most important methods for shifting risk in the construction context is insurance coverage. Upstream parties such as owner/developers and general contractors typically require that their downstream subcontractors who perform work on their properties or projects bring specific insurance to the table. These insurance requirements have a twofold purpose: protect the upstream parties, through additional insured coverage, from liabilities caused by the subcontractor; and protect the downstream parties by ensuring that they have adequate insurance for their own potential liabilities.
In New York, subcontractor insurance coverage can have some surprising terms which frustrate risk transfer. Numerous policies contain “Action Over” exclusions, which bar coverage for one of the most significant exposures faced by owner-developers and general contractors: bodily injury lawsuits brought by subcontractor employees. It is critical that upstream parties understand the unique impact of New York’s labor laws on the insurance market and be prepared to identify and request removal of Action Over exclusions on subcontractor insurance policies.
Reprinted courtesy of
Theresa A. Guertin, Saxe Doernberger & Vita, P.C. and
Ashley McWilliams, Saxe Doernberger & Vita, P.C.
Ms. Guertin may be contacted at TGuertin@sdvlaw.com
Ms. McWilliams may be contacted at AMcWilliams@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to BWB&O’s Las Vegas Team on Obtaining Summary Judgment for the Firm’s Landowner Client!
August 03, 2022 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce Partner Anthony Garasi, Senior Associate Madeline Arcellana, and Associate Laura Rios successfully won a Motion for Summary Judgment (“MSJ”), while also defeating two competing MSJs filed by Plaintiff, and ultimately obtaining a full dismissal of their landowner client against claims of premises liability.
Plaintiff, who sued both BWB&O’s client (the landowner) and its tenant, alleged injury when he slipped and fell, while utilizing a temporary wooden board as a ramp that was placed on the subject property by the tenant, who was occupying the property subject to a lease-to-own arrangement with BWB&O’s client.
In this Motion practice, the BWB&O team successfully obtained a ruling from the Court to find that BWB&O’s client had effectively contracted to delegate its maintenance responsibilities to its tenant, and also that the tenant owed BWB&O’s client full indemnity for Plaintiff’s alleged losses.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Keeping Up With Fast-moving FAA Drone Regulations
February 28, 2018 —
Dick Zhang – Construction Executive Magazine One of the biggest changes in recent years relating to commercial drone regulations has been FAA rule Part 107. Prior to 107, drone pilots were required to hold a current, manned aircraft pilot certificate, and had to pass a written, practical and oral exam to earn that credential. After 107 came into effect, a drone pilot was only required to pass a written exam to earn this commercial drone license.
The majority of people working at construction companies who take the Part 107 exam don’t have any type of aviation background, so it’s recommended that they give themselves at least two hours of study a day over two weeks to prepare for the exam. This commitment allows enough time for the student to both master any prepared test materials as well as do any additional research when necessary. The Part 107 certification is good for 24 months. While the FAA hasn’t posted anything about a recertification process yet, it will need to do so soon because everyone who took the exam when it was available in September 2016 will need to be recertified by August 2018.
Read the court decisionRead the full story...Reprinted courtesy of
Dick Zhang, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.Mr. Zhang may be contacted at
contact@identifiedtech.com
Uniform Rules Governing New York’s Supreme and County Courts Get An Overhaul
February 08, 2021 —
Andrew I. Hamelsky, Jenifer A. Scarcella & Monica Doss - White and Williams LLPBy Administrative Order effective February 1, 2021, New York’s Uniform Civil Rules for the Supreme Court will incorporate a number of changes to the general part that reflect many of New York’s Commercial Division Rules, in an effort to streamline court processes. The general part rule changes are a step forward for improving the efficiency, modernization and cost-effectiveness of the New York Courts, and will require practitioners to be more conscientious of court appearances and deadlines. Judges will likely be strict on adherence to the new Uniform Rules. Some notable changes to the rules are highlighted below.
Court Appearances and Scheduling Orders
Uniform Rule 202.1 has been revised to require that counsel who appear before the court must be familiar with the case they are appearing for, and be fully prepared and authorized to discuss and resolve the issues that are the subject of the appearance.
Reprinted courtesy of
Andrew I. Hamelsky, White and Williams LLP,
Jenifer A. Scarcella, White and Williams LLP and
Monica Doss, White and Williams LLP
Mr. Hamelsky may be contacted at hamelskya@whiteandwilliams.com
Ms. Scarcella may be contacted at scarcellaj@whiteandwilliams.com
Ms. Doss may be contacted at dossm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Nonparty Discovery in California Arbitration: How to Get What You Want
January 08, 2019 —
Leilani L. Jones - Payne & FearsOpting for arbitration requires attorneys to balance efficiency and procedural protections. The implications of arbitration are something clients certainly have to carefully consider both when drafting arbitration provisions, and after initiating a demand. While arbitration can in many respects streamline the civil discovery process, one of the largest roadblocks for cases in California arbitrations is “streamlining” discovery from nonparties. This article explores the challenges presented by third party discovery in arbitration, and proposes strategies for obtaining such discovery efficiently and expeditiously.
Read the court decisionRead the full story...Reprinted courtesy of
Leilani L. Jones, Payne & FearsMs. Jones may be contacted at
llj@paynefears.com
Despite Increased Presence in Construction, Women Lack Size-Appropriate PPE
September 26, 2022 —
Robin Marth - Construction ExecutiveFit. Functionality. Comfort. These are absolute musts for any employee wearing personal protective equipment (PPE) for work. Yet for many women in the workplace, finding PPE that fits well remains a challenge.
In 2021, women comprised 11% of construction workers, 7.9% of truck drivers and 29% of manufacturing employees (Bureau of Labor Statistics), and their numbers in these fields continue to increase. Unfortunately, their options for proper-fitting PPE are not growing.
"It's difficult to find PPE that fits women, because there is limited availability of these products, or suppliers do not offer them at all," says Brandy Bossle, owner and principal consultant at Triangle Safety Consulting LLC. "We really need suppliers to go out of their way to offer PPE that's cut for both men and women."
Private fleet driver and Women in Trucking Image Team member Carol Nixon agrees, saying, "You can find men's hats, gloves, jackets and safety vests everywhere, but not with a female fit."
Women can be shaped differently from head to toe—their faces, shoulders, waists, fingers and toes are often narrower, and they often have shorter torsos, among other differences.
In order for PPE to fit many women comfortably and properly, these proportions need to be taken into account. In fact, OSHA states on its website that PPE used by women should be based on female body measurement data and that employers should offer PPE in sizes suitable for women.
Reprinted courtesy of
Robin Marth, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Marth may be contacted at
media@jjkeller.com
The 2021 Top 50 Construction Law Firms™
June 14, 2021 —
Cybele Tamulonis - Construction ExecutiveVaccination rates continue to rise, mandates are loosening for returning to work and school, and a $2 trillion infrastructure bill is looming on the horizon, but contractors remain cautious and counseled by the legal experts who thrive in the complex field of construction law.
According to the latest report by the Bureau of Labor Statistics, construction employment numbers did not move much in April despite an increased demand for housing and a recovering economy. Due to continued fallout from the pandemic—and what seems like no end in sight for the rising costs of materials—contractors have been turning to construction law firms to navigate delayed projects, interpret contract language, assist in risk mitigation and ensure the road ahead is paved with understandable and protective clauses.
For the 2021 survey for the annual U.S. ranking of The Top 50 Construction Law Firms™, Construction Executive’s editorial team reached out to dozens of attorneys at the nation’s best construction law firms to learn how the legal landscape is changing, as well as how legal teams are aiding clients with sharpening contract language and pivoting in response to challenges in the wake of the COVID-19 pandemic.
Reprinted courtesy of
Cybele Tamulonis, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of