Be Careful When Walking Off of a Construction Project
November 24, 2019 —
Christopher G. Hill - Construction Law MusingsI am truly grateful that my buddy Craig Martin (@craigmartin_jd) continues his great posts over at The Construction Contractor Advisor blog. He is always a good cure for writer’s block and once again this week he gave me some inspiration. In his most recent post, Craig discusses a recent Indiana case relating to the ever present issue of termination by a subcontractor for non-payment. In the Indiana case, the court looked at the payment terms and determined that the subcontractor was justified in walking from the project when it was not paid after 60 days per the contract.
This result was the correct, if surprising. Why do I say surprising? Because I am always reluctant to recommend that a subcontractor walk from a job for non payment if it is possible to continue. This is not so much for legal reasons (not paying a sub is a clear breach of contract by a general contractor) but practical ones. The practical effect of walking from the job is that the subcontractor is put on the defensive. Instead of arguing later that it performed but was not paid, that subcontractor is put in the position of arguing that the general contractor cannot collect its completion related and other damages because it breached first. This is a more intuitively difficult argument and one that is not as strong as the first.
Of course, all of this is contingent on the language in your contract (is there a “pay if paid” or language like that in the Indiana case?).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Building Permits Hit Five-Year High
October 01, 2013 —
CDJ STAFFThe New York Times reports that building permits in August were at their highest since May 2008, even despite a recent rise in mortgage rates. Construction starts on single-family homes were at their highest in six months as well. On the other hand, construction starts for condominiums and apartments fell slightly more than 11 percent.
Read the court decisionRead the full story...Reprinted courtesy of
Coping with Labor & Install Issues in Green Building
October 08, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder reported on the problem that builders have with using green techniques—finding skilled laborers and subs. “If a green product is not installed correctly it most likely won’t do its job,” building scientist Carl Seville said to Builder.
Austin Trautman of Vali Homes told Builder that the biggest problem he had with his first net-zero prototype house was the HVAC work. “It’s actually a simpler system with straightforward installation, but they just couldn’t figure it out.”
Cliff Majersik, executive director of the Institute for Market Transformation, said that teaching subs the new techniques is worthwhile: “Once you know how to do it, an energy-efficient house can even be less expensive to build.”
Read the court decisionRead the full story...Reprinted courtesy of
New Executive Order: Revitalizing Our Nation’s Commitment to Environmental Justice for All
May 08, 2023 —
Anthony B. Cavender - Gravel2GavelThe White House has released the text of the President’s new Executive Order strengthening the Federal Government’s commitment to taking new actions to enhance and promote environmental justice. The Order was published in the Federal Register on April 26, 2023 at 88 FR 25251. President Clinton’s pioneering 1994 Executive Order remains effective, but the Federal Government must, as part of a whole-of-government approach to environmental justice, “build upon and strengthen its commitment to deliver environmental justice to all communities across America.”
Unlike that Order, this Order defines “environmental justice.” For purposes of this new Order, “environmental justice” takes into account all adverse human health and environmental effects and hazards, including those related to climate change, the cumulative impacts of environmental and other burdens, and the legacy of racism or other structural or systematic barriers, and ensures equitable access to a healthy, sustainable and resilient environment in which to live, play, work, learn, worship and engage in cultural and subsistence practices.
“Federal activity” is now broadly defined as “any agency rulemaking, guidance, policy, program, practice or action that affects or has the potential to affect human health and the environment, including any agency action related to climate change.” This Order references the seven previous Executive Orders devoted to climate change, clean energy and the Inflation Reduction Act.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Case Remanded for Application of Efficient Proximate Cause Doctrine
November 06, 2013 —
Tred Eyerly — Insurance Law HawaiiThe Florida Court of Appeals remanded the case after the insured was awarded an $8 million dollar judgment against its property insurer for hurricane and other damage to a home. Am. Home Assur. Co. v. Sebo, 2013 Fla. App. LEXIS 14799 (Fla. Ct. App. Sept. 18, 2013).
Sebo purchased his home in April 2005, when it was four years old. It was insured under a manuscript policy issued by AHAC for $8 million. The all-risk policy covered rain, but excluded damage caused by faulty, inadequate or defective planning.
After Sebo bought the home, water leaks were noticed. Sebo believed that the house suffered from major design and construction defects. In October 2005, Hurricane Wilma struck and further damaged the home.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Under the Hood of U.S. Construction Spending Is Revised Data
January 06, 2016 —
Vince Golle – BloombergHere’s one key takeaway from the Commerce Department’s report Monday on U.S. construction spending. The
0.4 percent decrease in November, which itself was weaker than the most pessimistic Bloomberg survey forecast, was accompanied by downward revisions to prior months. The combination suggests some economists may revise down their fourth-quarter GDP tracking forecasts.
* October construction spending rose 0.3 percent, compared with a prior estimate of 1 percent, while September outlays advanced 0.2 percent versus a previous estimate of a 0.6 percent gain
Read the court decisionRead the full story...Reprinted courtesy of
Vince Golle, Bloomberg
NLRB Hits Unions with One-Two Punch the Week Before Labor Day
November 18, 2019 —
John Baker & Robert Pettigrew - White and Williams LLPThe National Labor Relations Board (the Board) continues to modify the way employers, unions and employees view and relate to each other in the workplace. In two decisions right before Labor Day, the Board strengthened employer rights in their workplaces, while at the same time making life for their union counterparts more difficult.
On August 23, 2019, the Board revisited the issue of whether an employer must grant access to the off-duty employees of an onsite contractor so they can engage in Section 7 activities on the employer’s property. In general, Section 7 activities consist of employees acting together to improve their pay and working conditions, which constitute fundamental rights under the National Labor Relations Act (the Act). In Bexar County Performing Arts Center Foundation d/b/a Tobin Center, the San Antonio-based performing arts center, the Tobin Center, owned the Center as well as grounds that abutted the famed San Antonio River Walk. The Tobin Center housed three resident companies, one of which was the Ballet San Antonio with whom it had a licensor-licensee agreement.
In addition to plays, movies and other productions, the Tobin Center hosted the San Antonio Symphony (the Symphony) to perform for 22 weeks of the year. The Ballet San Antonio also occasionally utilized the Symphony for live musical performances at its ballets. When, however, the Ballet San Antonio decided to use recorded music for a particular production, off-duty employees of the Symphony protested by leafletting the public on the Tobin Center property. The leaflets advised the public of this decision and urged that they “DEMAND LIVE MUSIC!” Their protests were not directed at the property owner, who denied them access to its property.
Reprinted courtesy of
John Baker, White and Williams LLP and
Robert Pettigrew, White and Williams LLP
Mr. Baker may be contacted at bakerj@whiteandwilliams.com
Mr. Pettigrew may be contacted at pettigrewr@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Suing a Local Government in Land Use Cases – Part 2 – Procedural Due Process
February 16, 2017 —
Wally Zimolong – Supplemental Conditionsn my last post I discussed suing a local government for a substantive due process violation. In this post, I discuss a the right to procedural due process.
The Fourteenth Amendment of the United States Constitution protects prohibits the government from depriving an individual or business of life (in the case of an individual), liberty, or property without due process of law. Unlike the somewhat abstract and subjective concept of substantive due process, procedural due process is direct and objective. Generally, if an individual or business maintains a property or liberty interest, a local government must afford that individual or business notice that the government intends to deprive them of a liberty or property interest and a reasonable opportunity to be heard to contest the proposed deprivation. Unless there is an emergency, the notice and opportunity to be heard must be given before the government deprives an individual or business of a liberty of property interest. This is known as a pre-deprivation hearing. Because of the clear contours of the right, procedural due process violations are typically easier to prove than substantive due process violations.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com