David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPPerhaps more than any other specialty contractor, electrical contractors bear the brunt of the “problem project.” Long after most other trades have completed their work and scattered in the wind, electrical contractors remain on site until the owner’s last inspection. And when the project is a “problem project,” the owner or prime contractor tend to liberally share their losses and liquidated damages among those specialty contractors remaining on site at the end. So what is an electrical contractor to do when the project starts coming off the rails?
What is a Problem Project?
First, it helps to identify the attributes of a problem project. While there are many negative qualities of a bad job, a problem project is one that busts budgets – whether labor, material, or time. Most commonly, the problem project will significantly exceed the labor budget. Because an electrical contractor’s most important (and understandably expensive) resource is its people, the labor budget is critical to the success of a job. When a project suffers delays or is ineptly managed, the labor costs soar, turning a potentially profitable job into a disaster.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
My Employees Could Have COVID-19. What Now?
March 23, 2020 —
Amy R. Patton, Leila S. Narvid, Matthew C. Lewis, Robert Tadashi Matsuishi & Sarah J. Odia - Payne & FearsUpdated Guidance as of March 19, 2020.
You are concerned about potentially sick employees in the workplace. One employee is off work sick for a couple of days, and then wants to return to work. Another plans to return to work after a week of travel. Another appears to be sick at work. They are coughing, sneezing, and appear to be short of breath. You are concerned they may have COVID-19. What can you do? You're not the only one concerned -- your other employees are, too.
Your public-facing employees want to wear masks to protect themselves. One employee tells you he doesn’t want to touch anything that others in the office have touched. What are your obligations to these employees?
Below, we address questions relating to keeping employees safe from COVID-19 in the workplace without violating the Americans with Disabilities Act (ADA) or employee privacy laws.
Can I require an employee returning from days away from work due to illness to report the symptoms the employee was experiencing that kept him/her out of work?
Short answer: yes, so long as the questions are limited to whether the employee has had flu-like symptoms. Though the ADA prohibits asking employees questions related to an employee disability, COVID-19 (like the seasonal flu) likely does not rise to the level of a disability, so asking an employee about flu-like (or COVID-19-like) symptoms is unlikely to elicit information related to a disability. The Equal Employment Opportunity Commission (EEOC) has taken the position that an employer may ask if an employee is experiencing flu-like symptoms if the employee reports being ill during a pandemic.
Reprinted courtesy of Payne & Fears attorneys
Amy R. Patton,
Leila S. Narvid,
Matthew C. Lewis,
Robert Tadashi Matsuishi and
Sarah J. Odia
Ms. Patton may be contacted at arp@paynefears.com
Ms. Narvid may be contacted at ln@paynefears.com
Mr. Matthew may be contacted at mcl@paynefears.com
Mr. Robert may be contacted at rtm@paynefears.com
Ms. Odia may be contacted at sjo@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
The 2021 Top 50 Construction Law Firms™
June 14, 2021 —
Cybele Tamulonis - Construction ExecutiveVaccination rates continue to rise, mandates are loosening for returning to work and school, and a $2 trillion infrastructure bill is looming on the horizon, but contractors remain cautious and counseled by the legal experts who thrive in the complex field of construction law.
According to the latest report by the Bureau of Labor Statistics, construction employment numbers did not move much in April despite an increased demand for housing and a recovering economy. Due to continued fallout from the pandemic—and what seems like no end in sight for the rising costs of materials—contractors have been turning to construction law firms to navigate delayed projects, interpret contract language, assist in risk mitigation and ensure the road ahead is paved with understandable and protective clauses.
For the 2021 survey for the annual U.S. ranking of The Top 50 Construction Law Firms™, Construction Executive’s editorial team reached out to dozens of attorneys at the nation’s best construction law firms to learn how the legal landscape is changing, as well as how legal teams are aiding clients with sharpening contract language and pivoting in response to challenges in the wake of the COVID-19 pandemic.
Reprinted courtesy of
Cybele Tamulonis, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Home Prices Climbed 0.1% in July as Gains Slowed
September 24, 2014 —
Prashant Gopal – BloombergU.S. home prices rose less than economists estimated in July as investors pull back from the property market.
Prices climbed 0.1 percent on a seasonally adjusted basis from June, the Federal Housing Finance Agency said today in a report from Washington. The average economist estimate was for a 0.5 percent increase, according to data compiled by Bloomberg.
Investors who helped drive up prices are retreating as fewer foreclosures and other discounted homes become available. All-cash purchases in August fell to about 23 percent of the market from the usual 33 percent, the National Association of Realtors reported yesterday. Investors accounted for 12 percent, the least since late 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
World’s Biggest Crane Lifts Huge Steel Ring at U.K. Nuclear Site
January 25, 2021 —
Rachel Morison - BloombergThe world’s largest crane hoisted the first of three massive steel rings that will encase one of the reactors at Electricite de France SA’s nuclear construction site in the U.K., a key milestone in getting the project completed on time.
Operators of the 250-meter (820-foot) tall crane, affectionately known as “Big Carl,” lifted the ring that weighs as much as a jumbo jet overnight to take advantage of windless conditions.
Hinkley Point C is the U.K.’s first new nuclear power plant in more than two decades. Once up and running the reactor will generate electricity for six million homes by 2025.
It’s the largest and most advanced infrastructure project in the country and, when finished, will contain 3 million tons of concrete and 50,000 tons of structural steel, enough to build a railway line between London and Rome.
Read the court decisionRead the full story...Reprinted courtesy of
Rachel Morison, Bloomberg
Angela Cooner Appointed Vice-Chair of Arizona’s Inaugural Board of Legal Specialization Construction Defect Law Advisory Commission
June 20, 2022 —
Angela Cooner - Lewis BrisboisPhoenix, Ariz. (May 17, 2022) - Phoenix Partner Angela Cooner has been appointed as the vice-chair of the State Bar of Arizona’s inaugural Board of Legal Specialization Construction Defect Law Advisory Commission. The commission was created pursuant to the Arizona Supreme Court’s recent administrative order recognizing construction defect law as a new area of specialization.
The commission will, among other things, create the application, examination, and interview process that Arizona attorneys will be required to complete to earn the construction defect law specialized certification. Ms. Cooner will serve a two-year term that will end on January 31, 2024.
Read the court decisionRead the full story...Reprinted courtesy of
Angela Cooner, Lewis BrisboisMs. Cooner may be contacted at
Angela.Cooner@lewisbrisbois.com
Three's a Trend: Second, Fourth and Ninth Circuits Uphold Broad "Related Claims" Language
February 23, 2016 —
Greg Steinberg – White and Williams LLPThe hallmark of a claims-made insurance policy is that the policy only provides coverage for claims that are “first made” during the policy period. As noted by the Texas Supreme Court, “for the insurer, the inherent benefit of a claims-made policy is the insurer's ability to close its books on a policy at its expiration and thus to attain a level of predictability unattainable under standard occurrence policies.”[1]
To ensure this “level of predictability,” claims-made insurance policies contain provisions stating that all “Related Claims” will be treated as a single claim deemed first made at the time the earliest of such claims was made. The “Related Claims” provision is an issue that comes up time and again – claims can span years, especially in the context of regulatory investigations, which often culminate in enforcement proceedings and litigation. This inevitably leads to disputes regarding whether later claims can be related back to the earlier claim, an issue that becomes even thornier when different insurers participate on different policy years.
Over time, case law on “Related Claims” has been mixed and somewhat inconsistent, with each case tending to hinge on its own unique set of facts, making it difficult to identify a clear standard for determining whether claims are related. However, three recent decisions out of the Second, Fourth and Ninth Circuits show that courts are increasingly deferring to the plain language of the policy and applying these provisions broadly.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Steinberg, White and Williams LLPMr. Steinberg may be contacted at
steinbergg@whiteandwilliams.com
Residential Contractors, Be Sure to Have these Clauses in Your Contracts
May 16, 2018 —
Christopher G. Hill - Construction Law MusingsI have often “mused” on the need to have a good solid construction contract at the beginning of a project. While this is always true, it is particularly true in residential contracting where a homeowner may or may not know the construction process or have experience with large scale construction. Often you, as a construction general contractor, are providing the first large scale construction that the homeowner has experienced. For this reason, through meetings and the construction contract, setting expectations early and often is key.
As a side note to this need to set expectations, the Virginia Department of Professional and Occupational Regulation (DPOR) and the Virginia General Assembly require certain clauses to be in every residential construction contract. DPOR strictly enforces these contractual items and failure to put them in your contracts can lead to fines, penalties and possibly even revocation of a contractor’s license.