New Case Alert: California Federal Court Allows Policy Stacking to Cover Continuous Injury
November 23, 2016 —
William S. Bennett - Saxe Doernberger & Vita, P.C.“Stacking” is a practice that is very favorable for policyholders, especially in environmental coverage cases involving extended pollution events. It allows a policyholder to combine the limits of multiple consecutive policies to cover continuous injury claims occurring over multiple policy periods. Without stacking, insurers can limit a policyholder’s recovery to a single policy limit.
The Eastern District of California recently decided that a policyholder could stack the limits of six consecutive policies, where the occurrence was a continuous injury spanning all six policy years. Among other rulings, the court determined that the plain language of the policy under dispute did not prevent stacking.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Kadeejah Kelly Named to The National Black Lawyers’ “Top 40 Under 40” List
October 17, 2022 —
Lewis BrisboisNew York, N.Y. (October 6, 2022) – New York Associate
Kadeejah J. Kelly was recently named to The National Black Lawyers (NBL) “Top 40 Under 40” list.
The NBL “Top 40 Under 40” recognizes the most talented black attorneys under the age of 40 who have an outstanding reputation among peers, the judiciary and the public. The honorees on this list are nominated from leading lawyers, current members, and Executive Committee members.
Ms. Kelly is a member of the General Liability and Professional Liability Practices. She has extensive experience defending owners, contractors, developers and corporations in high exposure construction cases including New York Labor Law matters, premises liability and construction defect claims. She also has experience defending malpractice claims against attorneys, accountants, architects, engineers, funeral home directors and other miscellaneous professionals.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
How Does Your Construction Contract Treat Float
November 08, 2017 —
David Adelstein - Florida Construction Legal UpdatesAlthough there are different types of construction schedule float and more technical definitions, the definition that makes sense to me is that float is the amount of time a particular activity can be delayed without that activity delaying the project’s completion date (substantial completion date). In looking at a construction schedule, this determination is made from looking at the difference between the early start date for an activity and the late start date for that activity or the difference between the early finish date for that activity and the late finish date for that activity in your CPM schedule (which should be the same amount of time). This is often referred to as “total float” and is the float that I usually focus on since it may pertain to a delay to the substantial completion date of the project and can trigger either the assessment of liquidated damages and/or the contractor’s extended general conditions, whatever the case may be.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Construction Defects could become Issue in Governor’s Race
October 22, 2014 —
Jesse Howard Witt – Acerbic WittAccording to today’s Denver Business Journal, construction defects have emerged as a potential issue in Colorado’s gubernatorial race. During last night’s debate, Republican challenger Bob Beauprez criticized incumbent Democrat John Hickenlooper for failing to help senators with a last-minute push to enact a bill stripping away homeowner protections in construction disputes. Republicans had argued that the bill was needed to appease apartment developers who claim that quality control and insurance costs are too high on condominium projects.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.wittlawfirm.net
Federal Court Denies Summary Judgment in Leaky Condo Conversion
August 04, 2011 —
CDJ STAFFIn the US District Court for Illinois, Judge William Hibber has rejected the request for summary judgment sought by the developers of a condominium building in the case of Nautilus Ins. Co. v. 1735 W. Diversey, LLC (the insureds). The insureds renovated a building at 1735 W. Diversey, Chicago, converting it into condominiums. After the project was completed and all units sold, and a condominium association form, one of the owners found that unit suffered leaks during rainstorms. The condo board hired a firm, CRI, to investigate the cause of the leakage. CRI found “water infiltration through the exterior brick masonry walls, build-up of efflorescence on the interior surfaces of the masonry, and periodic spalling of portions of the brick masonry.”
The redevelopment firm had purchased coverage from Nautilus. “Shortly after the Board filed its first complaint, the Insureds tendered the mater to Nautilus and requested that it indemnify and defend them from the Board's underlying claims. Nautilus, however, rejected the Insureds’ tender and denied coverage under both insurance policies.” Nautilus stated that the water leakage did not constitute an occurrence under the policies. The court cited these policies in which an occurrence is defined as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions.” The Illinois courts have determined that construction defects are not accidents.
The court concluded that the insured did not bring forth claims within the coverage of the policies and denied the motion for summary judgment.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: Builder’s Alternative Pre-litigation Procedures Upheld Over Strong Opposition
April 01, 2014 —
Steven M. Cvitanovic and Whitney L. Stefko - Haight Brown & Bonesteel, LLPLast week, the Court of Appeal, Fifth Appellate District, was tasked with evaluating the enforceability of provisions in home purchase contracts containing alternative pre-litigation procedures which differ from the standard Right to Repair Act procedures. The Court of Appeal, in McCaffrey v. Superior Court of Fresno, et al. ultimately upheld the contractual provisions, and in overturning the trial court's decision, preserved the rights of builders to contract around certain requirements set forth in the Right to Repair Act.
The McCaffrey Group, Inc. constructed single-family homes in a Fresno development. Plaintiffs consisted of 24 homeowners within the development who brought suit against McCaffrey for construction defects in their homes. The homeowners were comprised of three categories: (1) the original purchasers who bought their homes from McCaffrey before January 1, 2003 and had a 2001 version of McCaffrey's contract; (2) the original purchasers who bought their homes from McCaffrey on or after January 1, 2003 and signed a 2003 version of McCaffrey's contract; and (3) the subsequent purchasers who did not buy their homes directly from McCaffrey, but purchased their homes subject to either the 2001 or 2003 version of McCaffrey's home purchase agreement.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Statutes Authorizing Public-Private Partnership Contracting
February 01, 2022 —
Robert A. James & Shade Oladetimi - Gravel2Gavel Construction & Real Estate Law BlogPublic-private partnerships are often cited as a key pathway to restoring and enhancing the nation’s infrastructure. They can be challenging arrangements to structure. (As a result of the pandemic, they have even suffered the indignity of having their “PPP” acronym coopted by the
Paycheck Protection Program. With apologies to Small Business Administration practitioners, we use “PPP” in this article to refer to the infrastructure tool.)
One gating condition to setting up a PPP is identifying the authority for a public entity to use a contracting method that does not run afoul of the general requirements that (i) works of improvement be let to the lowest responsive bid by a responsible bidder and (ii) design services be awarded through a qualifications-based selection process. Integrated forms of project delivery that vest in a single concessionaire multiple design, construction, financing, operation, maintenance and entrepreneurial roles must find an exception to any applicable background rules.
Reprinted courtesy of
Robert A. James, Pillsbury and
Shade Oladetimi, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Ms. Oladetimi may be contacted at shade.oladetimi@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
District Court Allows DBE False Claims Act Case to Proceed
February 23, 2017 —
Wally Zimolong – Supplemental ConditionsLast week, I posted about how whistleblowers continue to receive large settlements related to DBE fraud. A somewhat recent case from the federal court in Maryland shows how whistleblowers are ferreting out DBE fraud on construction projects receiving any form of federal funding.
The Case
The case involves a bridge painting project in Maryland that was let by the Maryland State Highway Administration. The contract required the prime contractor to meet a 15% DBE participation goal. The prime contractor submitted a bid stating it would have 15.12% DBE participation. After it was awarded the contract, the prime contractor – as is typical – submitted additional forms certifying to the MSHA that 15.12% of its contract price would be performed by a DBE firm. The prime contractor indicated that one DBE subcontractor, Northeast Work and Safety Boats, LLC (“NWSB”), would perform the 15.12% of the work.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com