Performance Bond Surety Takeover – Using Terminated Contractor To Complete The Work
January 06, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen a contractor is defaulted under a performance bond, can its surety hire the same defaulted contractor to complete the work? Stated differently, can the performance bond surety engage its defaulted bond-principal in taking over and completing the same work the contractor was defaulted under? The answer is “yes” if you are dealing with a standard form AIA A312 performance bond (and other bond forms that contain analogous language), as demonstrated by the recent decision in Seawatch at Marathon Condominium Association, Inc. v. The Guarantee Company of North America, 2019 WL 4850194 (Fla. 3d DCA 2019).
In this case, a condominium association hired a contractor in a multi-million dollar contract to renovate condominium buildings. The contractor provided the association, as the obligee, a performance bond written on an AIA A312 performance bond form. During construction, the association declared the contractor in default and terminated the contractor. In doing so, the association demanded that the performance bond surety make an election under paragraph 4 of the AIA A312 bond form that gave the surety the following options:
4.1 Arrange for the CONTRACTOR, with consent of the OWNER, to perform and complete the Contract; or
4.2 Undertake to perform and complete the Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the OWNER for a contract for performance and completion of the Contract, arrange for a contract to be prepared for execution by the OWNER and the contractor selected with the OWNER’S concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the Bonds Issued on the Contract, and pay to the OWNER the amount of damages as described in paragraph 6 in excess of the Balance of the Contract Price incurred by the OWNER resulting from the CONTRACTOR Default; or
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Subcontractor Not Estopped from Enforcing Lien Not Listed In Bankruptcy Petition
March 01, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPIn Stock Building Supply, Inc. v. Platte River Insurance Co.,[1] the Court of Appeals dealt with issues of judicial estoppel, bankruptcy, retroactive application of statutory lien amendments, and the full payment defense.
The owner, Madison Retail-Suwanee, LLC (“Madison”) hired Cannon/Estapa General Contractors, Inc. (“Cannon”) to be the general contractor for the construction of a shopping center (“the Project”). Cannon subcontracted with Stock Building Supply (“Stock”) to supply labor, materials, and services for the Project. Cannon failed to complete the project and Madison had yet to pay Cannon the full contract price. In 2007, Stock timely filed a lien on the Project and obtained a judgment against Cannon for the amount due under the subcontract. Platte River Insurance Company (“Platte”), the surety, issued a bond to discharge Stock’s lien. Consequently, Stock pursued an action against Platte to collect the judgment in the amount of $93,865.27.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
A Few Green Building Notes
April 03, 2019 —
Christopher G. Hill - Construction Law MusingsThis past week, the blogosphere (if that’s even the word these days) has been abuzz about green building and the value that green can add to a project. Three items in particular (among many) got my attention.
The first of these was the fact that a new private sustainability rating system is ready for launch. The Institute for Sustainable Infrastructure (or ISI) is seeking public comment on its proposed envISIon. This new system (aptly dubbed Version 1.0) will go “live” in July for comment. Why mention this new system? First of all, ISI’s founding members are the American Society of Civil Engineers (ASCE), the American Public Works Association (APWA) and the American Council of Engineering Companies (ACEC). This trio gives the new program some fairly heavy weight backing. Second, while there are rating systems aside from the ever present LEED, none have taken hold in any real way to compete with LEED. I am curious to see if the envISIon system has any better luck. Finally, this shows that sustainable building is of interest to more than the USGBC and those of us that discuss LEED on a daily basis. I find this to be a great thing that could lead to more societal acceptance of sustainable practices as a standard practice rather than a goal.
Hopefully such efforts will offset the other two notes that caught my eye recently.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
BWB&O Partner Jack Briscoe and Associate Anoushe Marandjian Win Summary Judgment Motion on Behalf of Homeowner Client!
March 13, 2023 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to share that Partner, Jack Briscoe and Associate, Anoushe Marandjian obtained an order for summary judgment in a multi-theory liability action in Los Angeles Superior Court.
Plaintiff suffered severe injuries when he fell off a ladder while performing finish carpentry work at the home of BWB&O’s client. Plaintiff alleged various theories of liability against our client, the homeowner, including that: our client supplied a dangerous and defective ladder that, among other things, was unstable and not tall enough for the job; that the floor was covered with a slippery plastic sheeting hidden underneath construction paper which constituted a dangerous condition; that our client was his “employer” under the Labor Code; and that our client was civilly liable on the basis that he had directly hired Plaintiff, who was an unlicensed contractor. Alternatively, Plaintiff alleged that our client was vicariously liable for the conduct of his general contractor, who failed to maintain worker’s compensation insurance covering Plaintiff.
After several rounds of written discovery, which required extensive attempts to “meet and confer” over Plaintiff’s deficient responses, as well as the parties’ depositions, Mr. Briscoe and Ms. Marandjian filed a Motion for Summary Judgment on behalf of our client on various grounds, including that the Privette Doctrine precluded Plaintiff from recovery against our client and that our client was not negligent (there was no dangerous condition and if there was, our client did not create it or that it existed for a long enough time for our client to have discovered it and remedied it). Plaintiff’s Opposition to our Motion for Summary Judgment included a Declaration from an expert witness alleging various grounds upon which our client was liable.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Change #7- Contractor’s Means & Methods (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaFirst, a little history: as you know, means, methods, techniques, sequences, and procedures are all part of the Contractor’s responsibility on a construction site. However, when the AIA A201 was last revised, in 2007, there was a provision put in for that rare time when the Contract Documents gave specific instructions concerning a particular construction method. If the Contractor viewed such instructions as unsafe, he was to give notice to the Owner and Architect, and was not to proceed with that portion of the Work without further written instructions from the Architect. If the Architect directed him to proceed, the Contractor was absolved from any risks with following that instruction. Instead, the Owner assumed the responsibility for any loss or damage.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
DC Circuit Upholds EPA’s Latest RCRA Recycling Rule
September 23, 2019 —
Anthony B. Cavender - Gravel2GavelOn July 2, 2019, the U.S. Court of Appeals for the District of Columbia Circuit decided the case of California Communities Against Toxics, et al. v. EPA. In this decision, the court rejected the latest petition to strike or vacate EPA’s 2018 revisions to the Resource Conservation and Recovery Act (RCRA) hazardous waste recycling rules. In 1985, EPA promulgated a new regulatory definition of “solid waste,” which is the linchpin of the agency’s very stringent hazardous waste management rules. (See the rules located at 40 CFR Sections 260-268.) Unless a material is a “solid waste” as defined by the rules, it cannot also be a hazardous waste.
The 1985 rules grappled with the challenges posed by recycling practices, and attempted to distinguish between legitimate recycling which is not subject to hazardous waste regulation, and other more suspect forms of recycling. The rules are complex and replete with nuance. In doing so, EPA was adhering to RCRA’s statutory mandate that it develop appropriate rules to govern the treatment, storage and disposal of hazardous waste, while also promoting “properly conducted recycling and reuse.” The DC Circuit reviewed the 1985 rules in the seminal case of American Mining Congress v EPA, 824 F.2d 1177 (1987), (AMC) and stressed that only those materials that were truly discarded could be regulated as solid waste; for instance, those materials that were destined for immediate recycling or recovery in an ongoing production process were not discarded and hence were not solid waste. Over the years, the court has struggled to clarify the basic holding of AMC in numerous cases while EPA has frequently revised and amended the RCRA rules, and in particular the definition of solid waste, in an attempt to balance the policies mandated by the statute.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
White and Williams Obtains Reversal on Appeal of $2.5 Million Verdict Against Electric Utility Company
September 03, 2014 —
Edward Koch, Mark Paladino, Luke Repici, & Andrew Susko – White and Williams LLPPPL Electric Utilities successfully argued on appeal that the $2.5 million plaintiff’s molded verdict awarded to an injured painting subcontractor should be vacated because the alleged evidence was legally insufficient and therefore the utility was not liable.
In Nertavich v. PPL Electric Utilities, the plaintiff argued that although the utility was a landowner out of possession of the worksite, the utility was liable because it controlled the work of the subcontractor both by contract and by conduct. PPL argued on appeal before the Superior Court of Pennsylvania that the alleged evidence of the utility company’s control was insufficient as a matter of law to constitute control over the means and methods of the subcontractor’s work, and thus, PPL was not liable as a landowner out of possession.
Reprinted courtesy of White and Williams LLP attorneys
Edward Koch,
Mark Paladino,
Luke Repici and
Andrew Susko
Mr. Koch may be contacted at koche@whiteandwilliams.com;
Mr. Paladino may be contacted at paladinom@whiteandwilliams.com;
Mr. Repici may be contacted at repicil@whiteandwilliams.com;
and Mr. Susko may be contacted at suskoa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Appellate Court Endorses Discretionary Test for Vicarious Disqualification of Law Firms Due To New Attorney’s Conflict
February 07, 2018 —
David W. Evans and Stephen M. Tye – Publications & Insights In
California Self-Insurer’s Security Fund et al. v. The Superior Court of Orange County (1/26/2018 – No. G054981), the Fourth Appellate District considered whether vicarious disqualification of a law firm is mandatory or discretionary where an attorney with a conflict joins a firm and the firm enacts an ethical screen to prevent transmission of confidential information between the new attorney and the rest of the firm.
This case arose from an effort by the California Self-Insurer’s Security Fund (the “Fund”) to be reimbursed for workers’ compensation benefits advanced on behalf of the Healthcare Industry Self-Insurance Program (the “Program”). The Fund hired Nixon Peabody LLP (“Nixon Peabody”) to represent it in connection with this matter. In November 2013, represented by members of Nixon Peabody’s San Francisco office, the Fund filed a lawsuit naming 304 members of the Program as defendants. Approximately 170 defendants have since settled.
Two of the non-settling defendants (“Moving Parties”), were represented by Michelman & Robinson, LLP (“M&R”). From approximately 2009 until February 1, 2017, attorney Andrew Selesnick served as Chair of M&R’s Health Care Department at the firm’s Los Angeles office, managing a team of attorneys who represented clients in the healthcare industry. Commencing in 2014, a team of four attorneys at M&R, including Selesnick, represented the Moving Parties and four other defendants, the latter of whom have since settled. Selesnick was actively involved, including participating in a confidential discussion pertaining to Moving Parties’ liability and damages and receiving many e-mails containing communications about the common defense of the remaining 170 defendants.
Reprinted courtesy of
David W. Evans, Haight Brown Bonesteel and
Stephen M. Tye, Haight Brown Bonesteel
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of