The Value of Photographic Evidence in Construction Litigation
April 26, 2021 —
Marie Mueller - Construction ExecutiveIf a picture is worth a thousand words, can it be worth a thousand dollars? Ten thousand? Maybe, if it provides key evidence in a construction dispute. Litigating a construction case involves each side telling their story. Details and visual context make a story compelling. Evidence and corroboration make a story persuasive. Photographs can help on both of these fronts.
The Value of Photographic Evidence in Construction Litigation
Consider the following examples:
- A dispute relates to the timeliness of particular work. An employee has a memory of a load of materials arriving to the site later than it should have, but the records are incomplete or ambiguous about when it actually occurred. If the employee also took a photo of the materials, on the day they arrived, they could match up the date of the photo to their memory and build a clear timeline.
- A dispute relates to the presence or absence of obstructions in drilled shafts. There are no available photographs or videos of the work due to site restrictions. Presentation of this type of case may be severely limited by not being able to show photos depicting the size, shape and type of material removed from the shafts, and by the lack of video depicting the work.
Reprinted courtesy of
Marie Mueller, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Mueller may be contacted at
mmueller@verrill-law.com
UPDATE: ACS Obtains Additional $13.6 Million for General Contractor Client After $19.2 Million Jury Trial Victory
June 27, 2022 —
Kristina Southwell - Ahlers Cressman & Sleight PLLCIn March 2022, ACS obtained a $19.2 million jury verdict in favor of its general contractor client after a lengthy trial against the project owner. Since that time, ACS has successfully obtained awards through post-trial motion practice for an additional $13.6 million in favor of the general contractor. These awards increased to total judgment to more than $32 million.
When moving to enter judgment on the jury verdict, ACS successfully argued for and obtained more than $5 million in prejudgment interest on the jury verdict to compensate the general contractor for having to go years without payment for work performed. ACS also successfully obtained a decree of foreclosure on its construction lien and incorporated language in the judgment requiring the owner to pay an additional $1.9 million in Washington State sales tax on the jury award. Finally, under the authority of the Washington construction lien statute (RCW 60.04.181), ACS sought to recover the attorneys’ fees, costs, and expenses incurred by the general contractor client during the course of litigation. ACS succeeded in obtaining an award for more than $6.6 million for various expenses and costs including ACS’s attorney fees, all the costs of hiring expert witnesses, costs and expenses related to subcontractors’ presentation of pass-through claims against the owner, and other litigation costs and expenses.
Read the court decisionRead the full story...Reprinted courtesy of
Kristina Southwell, Ahlers Cressman & Sleight PLLCMs. Southwell may be contacted at
wendy.wheatmccoy@acslawyers.com
Ahead of the Storm: Preparing for Irma
September 07, 2017 —
Stephen H. Reisman – Peckar & Abramson, P.C.While Hurricane Irma boils in the Atlantic and seems to be aiming towards Florida, storm preparations are well underway. As contractors are busy organizing efforts to secure their job sites, we at Peckar & Abramson offer some quick reminders that may prove helpful when the dust finally settles:
- Review your contracts, particularly the force majeure provisions, and be sure to comply with applicable notice requirements.
- Even if not expressly required at this point in time, consider providing written notice to project owners that their projects are being prepared for a potential hurricane or tropical storm and that productivity and the progress of the work will be affected, with the actual time and cost impact to be determined after the event.
- Consult your hurricane plan (which is often a contract exhibit) and confirm compliance with all specified safety, security and protection measures.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen H. Reisman, Peckar & Abramson, P.C.Mr. Reisman may be contacted at
sreisman@pecklaw.com
Builder Pipeline in U.S. at Eight-Year High: Under the Hood
August 26, 2015 —
Sho Chandra – BloombergHere’s the takeaway from the Commerce Department’s report Tuesday in in Washington that showed sales of new homes in the U.S rebounded in July to a 507,000 annualized rate. The median forecast of 75 economists surveyed by Bloomberg projected 510,000.
* Number of homes sold but not yet started climbed to a 192,000 annualized rate, the most since June 2007.
* That means builders have a large pipeline of demand to fill, which will keep housing starts rising.
* The number of homes under construction was the lowest since August 2014 and the number completed were the fewest since November.
Read the court decisionRead the full story...Reprinted courtesy of
Sho Chandra, Bloomberg
Los Angeles Warehousing Mecca Halts Expansion Just as Needs Soar
September 05, 2022 —
Ngai Yeung & Augusta Saraiva - BloombergCommunities in the Inland Empire, the US’s logistics mecca east of Los Angeles, are suspending new warehousing projects to examine the impact from decades of pollution -- putting the industry under pressure when it’s needed most.
This week, the city council for Pomona is set to vote on extending a temporary halt on industrial developments to study the environmental impact, while the nearby city of Norco will decide whether to establish a 45-day moratorium. The actions follow similar freezes by a handful of Southern California cities like Riverside, Colton, Chino and Redlands over the past several years.
Meanwhile, a state-level bill -- which is a long-shot to pass in the legislature but gives a reading of the mood -- proposes banning large industrial construction within 1,000 feet of non-industrial areas such as schools, homes and playgrounds in Riverside and San Bernardino counties, an area that spans 27,000 square miles.
Reprinted courtesy of
Ngai Yeung, Bloomberg and
Augusta Saraiva, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
With No Evidence of COVID-19 Being Present, DC Trial Court Finds No Claim for Business Interruption
September 28, 2020 —
Tred R. Eyerly - Insurance Law HawaiiA D.C. Superior Court rejected a business interruption claim due to closures related to the COVID-19 pandemic. Rose's 1, LLC v. Erie Ins. Exchange, Civil Case No 2020 CA 002424 B (Order dated Aug. 8, 2020). The decision is here.
Plaintiffs owned a number of restaurants in the District of Coiumbia. Plaintiffs had commercial property coverage in a policy issued by Erie. The policy provided coverage for loss of income sustained due to interruption of business resulting directly from "loss or damage" to the insured property.
DC Mayor Bowser issued a series of orders in March 2020 which closed all non-essential businesses, including plaintiffs' restaurants. Plaintiffs filed claims with Erie. When coverage was denied, plaintiffs filed suit. Both sides moved for summary judgment.
The dispute centered on whether the closure of the restaurants due to the mayor's orders constituted a "direct physical loss" under the policy. Plaintiffs argued that the loss of use of the restaurants was "direct" because the closures were the direct result of the mayor's orders without intervening action. The court reasoned, however, that the orders were governmental edicts that commanded individuals and businesses to take certain actions. Standing alone and absent intervening actions by individuals and businesses, the orders did not effect any direct changes to the properties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
How California’s Construction Industry has dealt with the New Indemnity Law
October 22, 2014 —
Mark S. Himmelstein, Esq. - Newmeyer & DillionIt has been almost two years since the California legislature enacted changes to the state’s indemnity law affecting commercial construction contracts. Although we do not yet have any court opinions analyzing the new statutes, the attorneys at
Newmeyer & Dillion now have real world experience in negotiating such indemnity provisions. It is time to evaluate how the construction community has reacted to the changes. In this article, we examine the practical applications of the new law to various construction agreements.
Enacted on January 1, 2013, the new legislation was the latest in a series of efforts by subcontractors and their insurers to eliminate “Type I” indemnity clauses. Under a Type I provision, a subcontractor has a duty to indemnify the developer or general contractor for the negligence of the developer or general contractor or other subcontractors, in addition to the negligence of the subcontractor itself. In 2006, the law was changed to preclude Type I provisions regarding “For Sale” residential construction defect claims. At that time, there was no such restriction enacted for commercial construction contracts. However, since then, commercial subcontractors have been seeking similar legislation. Their efforts culminated in the 2013 revisions regarding commercial contracts.
Commercial Subcontracts
Pursuant to the new indemnity statute — Civil Code section 2782.05 — we have revised our clients’ commercial subcontracts to:
(a) Eliminate the requirement that the subcontractor indemnify the general contractor for the general contractor’s “active negligence;” and
(b) Include the subcontractor’s options for defending claims for which they have an indemnity obligation.
Many subcontractors have responded: “Hey, wait a minute, the new legislation eliminated Type I indemnity so you (general contractor) cannot still require any indemnification for the general contractor’s negligence”. Well, that might be the rumor in subcontractor circles, but the new statute does not eliminate indemnity for the general contractor’s passive fault. In addition, the Civil Code lists 13 instances where the new indemnity restrictions do not apply.
Residential Subcontracts
The legislature did not make anyone’s job easier by drafting a different indemnity provision for commercial subcontracts than for residential subcontracts. In fact, the residential and commercial statutes are different in several critical respects. First, the restrictions on indemnity in the residential statute apply only to construction defect claims in newly constructed “For Sale” houses. The statute does not preclude Type I indemnity provisions for any other claims arising out of residential subcontracts. In contrast, the indemnity restrictions in the commercial statute apply to all claims arising out of commercial subcontracts. In addition, the commercial statute allows indemnity for the general contractor’s passive fault. Since some subcontractors on “residential” projects perform off-site “commercial” work as well, we have amended even residential subcontracts to address the subcontractors’ various indemnity obligations for different parts of their work (e.g., residential work versus commercial work).
Owner-Contractor Agreements
The January 1, 2013 new indemnity provisions apply not only to subcontracts, but also to owner-contractor agreements. Civil Code section 2782(c)(1) precludes indemnity for an owner’s active negligence. Interestingly, the exclusions contained in Civil Code section 2782.05 for subcontracts do not apply, and the statute does not provide contractors with the option of defending claims set forth in the sections concerning subcontracts. Therefore, we have revised the indemnity provisions in owner-contractor agreements to exclude indemnity for the owner’s active negligence.
Design Professional Agreements
The 2007 revisions with respect to “For Sale” residential contracts (discussed above), and the 2013 revisions for commercial contracts do not apply to design professionals. The new indemnity statute concerning commercial subcontracts specifically excludes design professionals from the “anti-indemnity” benefits provided to subcontractors. Therefore, Type I indemnity provisions are fair game and can still be included in design professional contracts.
Conclusion
In sum, Civil Code sections 2782 et seq. now contain an increasingly complex framework for indemnity rules in construction contracts. For example, there is one set of rules for “For Sale” residential construction defect claims (no indemnity for the developer’s active or passive negligence), another for any other claims arising out of residential construction (Type I indemnity is permitted), another for commercial subcontracts (no indemnity for the general contractor’s active negligence, but indemnity for the general contractor’s passive negligence unless any of the exceptions apply, in which case Type I indemnity is permitted), and yet another for commercial owner contractor agreements (no indemnity for the owner’s active negligence, but indemnity for the owner’s passive negligence with no exceptions).
California’s indemnity laws are complex, and rumors as to the impact of the new legislation have made it even more difficult to negotiate these provisions. It is imperative that indemnity clauses in construction contracts clearly delineate the obligations for the specific type or types of work contemplated by the contract. The legislature’s attempt to simplify indemnity obligations has actually made such provisions lengthier and more cumbersome. As experienced construction attorneys, our task is to draft indemnity provisions that comply with the laws, address potential claims, and are understandable.
Mr. Himmelstein is a partner in the Newport Beach office of Newmeyer & Dillion and practices in the areas of construction, real estate, business and insurance litigation. He also specializes in drafting and negotiating construction and real estate contracts. Mark can be reached at mark.himmelstein@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Texas Supreme Court Holds that Invoking Appraisal Provision and Paying Appraisal Amount Does Not Insulate an Insurer from Damages Under the Texas Prompt Payment of Claims Act
September 16, 2019 —
John C. Eichman & Grayson L. Linyard - Hunton Insurance Recovery BlogIn two cases decided June 28, 2019, the Texas Supreme Court held that an insurer’s invocation of a contractual appraisal provision after denying a claim does not as a matter of law insulate it from liability under the Texas Prompt Payment of Claims Act (“TPPCA”). But, on the other hand, the court also held that the insurer’s payment of the appraisal award does not as a matter of law establish its liability under the policy for purposes of TPPCA damages.
In Barbara Techs. Corp. v. State Farm Lloyds, No. 17-0640, 2019 WL 2666484, at *1 (Tex. June 28, 2019), State Farm Lloyds issued property insurance to Barbara Technologies Corporation for a commercial property. A wind and hail storm damaged the property, and Barbara Tech filed a claim under the policy. State Farm denied the claim, asserting that damages were less than the $5,000 deductible.
Barbara Tech filed suit against State Farm, including for violation of the TPPCA. Six months later, State Farm invoked the appraisal provision of the policy. More than a year after the suit was filed, appraisers agreed to a value of $195,345.63. State Farm then paid that amount, minus depreciation and the deductible. Barbara Tech amended its petition to include only TPPCA claims.
Reprinted courtesy of
John C. Eichman, Hunton Andrews Kurth and
Grayson L. Linyard, Hunton Andrews Kurth
Mr. Eichman may be contacted at jeichman@HuntonAK.com
Mr. Linyard may be contacted at glinyard@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of