Select the Best Contract Model to Mitigate Risk and Achieve Energy Project Success
October 17, 2022 —
Gregory S. Seador - Construction ExecutivePower and energy projects are inherently complex and risky. Therefore, management and proper allocation of risk among project participants are essential to success.
Careful drafting of the engineering, procurement and construction (EPC) contract is a critical first step in managing risk. The standard contract format used for power and energy construction projects is the EPC contract. In its traditional form, the EPC contract makes the EPC contractor responsible for the entire project, including engineering (design of the power plant), procurement (purchase, installation and performance of all equipment) and construction (construction of the plant).
EPC contracts can, however, employ different contract models and pricing structures, each of which carries differing levels of risk for project participants. Selecting the appropriate contract model and pricing structure to meet the unique needs of the project is important.
Reprinted courtesy of
Gregory S. Seador, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Seader may be contacted at
seador@slslaw.com
Suppliers of Inherently Dangerous Raw Materials Remain Excluded from the Protections of the Component Parts Doctrine
December 02, 2015 —
Leah B. Mason & Michael J. Worth – Haight Brown & Bonesteel, LLPIn Brady v. Calsol, Inc. 2015 No. B262028, the California Court of Appeal, Second District, reversed summary judgment for a raw materials supplier where there was a triable issue of fact as to whether the benzene levels contained in the supplier’s mineral spirits could have caused plaintiffs’ leukemia.
Plaintiffs were mechanics Ernest Brady and David Gibbs, who used Safety-Kleen solvent to degrease automotive parts. Brady and Gibbs were diagnosed with leukemia allegedly caused by exposure to Safety-Kleen solvent during the course of their employment. In 2008, Plaintiffs sued Calsol, Inc., a distributor of mineral spirits for the ultimate manufacturer, Safety-Kleen Systems, Inc. Plaintiffs asserted negligence and strict products liability claims. Specifically, plaintiffs alleged that benzene, a carcinogen found in mineral spirits, caused their leukemia. Benzene is only carcinogenic to humans at certain levels. The parties dispute the levels of benzene found in the mineral spirits supplied to Safety-Kleen. Calsol contended the benzene levels were present only in low concentrations. Plaintiffs alleged the benzene levels were capable of causing injury.
Reprinted courtesy of
Leah B. Mason, Haight Brown & Bonesteel LLP and
Michael J. Worth, Haight Brown & Bonesteel LLP
Ms. Mason may be contacted at lmason@hbblaw.com
Mr. Worth may be contacted at mworth@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Suit Limitation Provision Upheld
March 04, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's one year suit limitation provision was upheld, depriving insureds of benefits under the policy. Oswald v. South Central Mut. Ins. Co., 2018 Minn. App. Unpub. LEXIS 1077 (Dec. 24, 2018).
The Oswalds' hog barn burned down on June 21, 2016. Arson was a possible cause.
The Oswalds were insured under a combination policy issued by North Star Mutual Insurance Company and South Central Mutual Insurance Company. Central provided coverage for basic perils, broad perils, and limited perils, which included fire losses. The Central policy required property claims to be brought within one year after the loss. By endorsement, the North Star policy required suits be brought within two years after the loss. Presumably, the claims was denied, although the decision does not state this.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurance Policy Provides No Coverage For Slab Collapse in Vision One
August 17, 2011 —
Douglas Reiser, Builders Council BlogThis post will examine whether Division Two of the Washington Court of Appeals properly reversed and remanded several lower court decisions in the case of Vision One LLC v. Philadelphia Indemnity Insurance. In short, and from the perspective of an appellate attorney, the court of appeals got the decision right. Given the rules of contract interpretation and causation in tort claims, there was really no other way the court could have ruled. I understand that from a contractor’s perspective and insurance perspective, the decision seems odd. But from a purely legal standpoint, the decision is well-reasoned and well-supported. Let me explain.
Background
First, here are the facts in a nutshell. Vision One is a construction company that undertook to construct a condo complex in Tacoma. Vision then contracted with D&D Concrete to pour a concrete slab for a section of the foundation. To shore the concrete slab, D&D further contracted Berg Equipment to provide necessary equipment to stabilize the structure. Well, something down the line went wrong. The shoring failed and the slab collapsed, causing a great deal of damage.
Read the full story…
Read the court’s decision…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (8/21/24) – REITs Show Their Strength, Energy Prices Increase Construction Costs and CRE Struggles to Keep Pace
October 01, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, UBS to liquidate $2 billion real estate fund, hotel workers in San Francisco vote to strike, housing market to change after blockbuster settlement, and more!
- When it comes to buying and selling homes, new rules are about to be put in play, five months after the National Association of Realtors agreed to a settlement over how its 1.5 million agents across the U.S. are paid commissions. (Kate Gibson, CBS)
- Project abandonments tumbled in July in one of the largest monthly declines ever due to the anticipated interest rate cut. (Sebastian Obando, Construction Dive)
- Increases in energy prices drove most of the total rise in construction input costs over the past month. (Sebastian Obando, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
David M. McLain, Esq. to Speak at the 2014 CLM Claims College
August 13, 2014 —
David M. McLain, Esq. – Colorado Construction LitigationDavid McLain will be a speaker at the School of Construction. The Claims College will be held from September 7-10 in Philadelphia, Pennsylvania. Mr. McLain is a founding member of Higgins, Hopkins,McLain & Roswell, LLC, a firm which specializes in construction law and construction litigation throughout Colorado. Mr. McLain received his undergraduate degree from Colorado State University, graduating cum laude, and his law degree from the University of Denver, College of Law. Mr. McLain completed the Claims and Litigation Management Alliance Litigation Management Institute, earning the designation from that organization as a Certified Litigation Management Professional. He has a general civil litigation practice with an emphasis on the defense of complex construction lawsuits on behalf of developers and general contractors. As a result of the experience gained by defending some of Colorado’s largest residential construction defect lawsuits, developers, general contractors, and subcontractors seek out Mr. McLain to consult on risk avoidance and risk management strategies. Currently among his clients are several of the state’s largest home builders, regional and custom builders, and numerous insurance carriers. Mr. McLain is an AV® Preeminent™ Peer Review Rated attorney by Martindale-Hubbell and is a regular speaker at local, regional, and national seminars regarding construction defect litigation in Colorado.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Zero-Energy Commercial Buildings Increase as Contractors Focus on Sustainability
February 10, 2020 —
Jeffrey S. Wertman - Construction ExecutiveImagine a functional, low energy commercial building that annually consumes only as much power as the building creates with on-site, clean, renewable resources. From coast to coast, there is considerable momentum for zero-energy (ZE) buildings, also known as ZEB’s or net-zero energy buildings (NZEBs). Although still an emerging market, the growth trend for ZEBs is steep.
The world’s net-zero energy market for commercial and residential projects is expected to exceed $1.4 trillion by 2035. The number of ZEBs across North America has dramatically increased since 2010 which encompasses about 80 million square feet of commercial building space. ZE has captured the attention of building owners, developers, architects, engineers, contractors, designers, policymakers and others who see its potential to efficiently use clean energy resources to reduce the substantial carbon footprint of buildings.
Real Applications of Net Zero
From 2012 to 2019, the number of ZE projects has increased ten-fold. According to the “2019 Getting to Zero Project List” released in May 2019 by the New Buildings Institute, a nonprofit organization striving to achieve better energy performance in commercial buildings, the total number of certified, verified and emerging ZE projects grew to 607 in 2019. New projects continue to appear regularly. Today, hundreds of ZE buildings, including commercial buildings of all types (including retail, office, warehouse, hotel, educational and government) are being developed.
Reprinted courtesy of
Jeffrey S. Wertman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Motion for Summary Judgment to Reject Collapse Coverage Denied
November 24, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer unsuccessfully moved for summary judgment seeking to reject the insured's collapse claim. Gnannn v. United Servs. Auto, Ass'n, 2019 Conn. Super. LEXIS 1955 (Conn. Super Ct. July 11, 2019).
The insureds' home was built in 1985 and they purchased their home in 1993. A home inspection reported that some settlement and curing related cracks existed in the slab floor, but no signs of abnormal settlement were noticed. The concrete walls were in overall good condition.
In 2015, the insureds became aware of abnormal cracking in the basement. USAA was informed of the claim but denied coverage in October 2015. The insureds sued USAA. After suit was filed, the insureds hired an engineer, David Grandpre, to inspect their home. He observed severe cracking in the basement walls caused by an expansive chemical reaction within the concrete. The structure was not in imminent peril of falling down, and it continued as insureds' residence. But Mr. Grandpre noticed bulging and bowing, evidence that the concrete basement walls had failed and had begun to move inward due to the lateral pressure of the soil outside the home.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com