Construction Litigation Roundup: “A Less Than Valiant Effort”
June 21, 2024 —
Daniel Lund III - LexologyA Miller Act claimant in federal court in New Jersey in relation to a VA medical center project found itself on the wrong end of the law and was sent packing by the court.
The claimant had supplied products for the project to general contractor Valiant Group, LLC, pursuant to a purchase order from the GC. The general contractor allegedly refused to pay the supplier, leading to the claim against the GC and its payment bond surety in the amount of $126,900. The supplier also sought recovery under the federal Prompt Payment Act, 31 U.S.C. §§ 3901-07. State law claims were asserted as well.
Chipping away at the federal law claims – the claims forming the asserted basis for federal court jurisdiction for the case – the court first dispensed with the Prompt Payment Act claim. According to the court, allegations that the general contractor had “wrongfully and improperly withheld remuneration… despite [having] ‘received payment from the U.S. Department of Veterans Affairs’" – whether or not accurate – did not trigger the Act. The court wrote:
“The Prompt Payment Act was enacted ‘to provide the federal government with an incentive to pay government contractors on time by requiring agencies to pay penalties . . . on certain overdue bills . . . [and] was later amended to include provisions applicable to subcontractors.’… Absent from the Act, however, are ‘any explicit provisions for subcontractor enforcement if the prime contractor fails to make timely payment.’… This is because the Act ‘merely requires that the prime contractor's contract with the subcontractor include the specified payment clause. [It] does not require the prime contractor to actually make payments to the subcontractor[.]’… The Act, therefore, does not ‘give subcontractors an additional cause of action for an alleged breach by a general contractor of a subcontract.’”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
CDJ’s #7 Topic of the Year: The Las Vegas Harmon Hotel Year-Long Demolition & Trial Begins
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFThe 26-story tower in MGM’s $9 billion Las Vegas, Nevada CityCenter project, is being demolished piece by piece after a structural engineer reported that an earthquake of 7.7 could bring it down. While litigation began as early as 2010, the trial didn’t begin until October of 2014, and expectation is it will last through almost all of 2015 as well, according to Carri Geer Thevenot of the Las Vegas Review-Journal.
Read the court decisionRead the full story...Reprinted courtesy of
Federal Courts Reject Insurers’ Attempts to Recoup Defense Costs Expended Under Reservation of Rights
April 11, 2022 —
Anthony L. Miscioscia & Margo Meta - White and WilliamsIn situations where there is a dispute over a duty to defend, an insurer may provide a defense to its insured, subject to a reservation of rights, to not only deny coverage for a defense, but also to file a declaratory judgment action and recoup defense costs in the event it is determined there is no duty to defend. But are defense costs recoupable? Last week, federal trial courts in Georgia and Pennsylvania answered this question with a resounding “no”.
In Chemical Equipment Labs, Inc. v. Travelers Property Casualty Company of America, Case No. 19-3441, 2022 U.S. Dist. LEXIS 61298 (E.D.Pa. Mar. 31, 2022), the United States District Court for the Eastern District of Pennsylvania was called to determine whether Travelers Property Casualty Company of America (Travelers) was entitled to reimbursement of defense costs after it was determined that it had no duty to defend its insured in an arbitration for breach of a charter agreement. The Travelers’ policies did not contain an express reimbursement provision. The court found that Travelers was not entitled to reimbursement because under Pennsylvania law, “[r]eimbursement of defense costs requires an express provision in the written insurance contract.”
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Margo Meta, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Meta may be contacted at metam@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Shifting Fees and Costs in Nevada Construction Defect Cases
November 26, 2014 —
Casey J. Quinn - Newmeyer & Dillion LLPIn Nevada, homeowners who sue a builder for residential constructional defects may recover attorneys’ fees and costs caused by the defect. Many times, the request for attorneys’ fees can outpace the size of the actual claim for defects. However, Nevada provides builders with two ways to potentially shift the right to recover attorneys’ fees and costs away from the homeowner and to the builder.
The first arises during the Nevada Revised Statutes (NRS) Chapter 40 process (Nevada’s Right to Repair law). After a builder receives notice of construction defects, it is required to provide the claimant with a written response to each defect, which may include a proposal for monetary compensation (including contribution from a subcontractor, supplier, or design professional). See NRS 40.6472. If a claimant unreasonably rejects a reasonable written offer of settlement included in the response and decides to commence litigation, the court may deny the claimant’s attorneys’ fees and costs and award attorneys’ fees and costs to the builder. See NRS 40.650. Thus, by including a reasonable offer of monetary compensation in a Chapter 40 response, a builder could possibly avoid paying any fees and costs and even recover its own fees in defending against the claim.
A second method for shifting fees and costs is through a written offer of judgment (OOJ). See NRS 17.115 and NRCP 68. Not limited solely to construction defect matters, an OOJ is a useful tool in all kinds of litigation. OOJs are designed to facilitate and encourage pre-trial settlement by incentivizing parties to make reasonable settlement offers that—when unreasonably rejected—have the consequence of shifting the right to recover attorneys’ fees. Basically, when a party rejects an OOJ and fails to obtain a more favorable judgment, the court cannot award any attorneys’ fees and costs to the rejecting party and may award attorneys’ fees incurred from the date of the offer to the entry of judgment, as well as all reasonable costs, to the party who made the offer. In a recent decision, the Nevada Supreme Court affirmed that when a homeowner rejects an OOJ and fails to obtain a more favorable judgment, it can wipe out that homeowner’s right to Chapter 40 fees and costs. See Gunderson, et al. v. D.R. Horton, 130 Nev. Adv. Op. 9 (Feb. 27, 2014). In other words, “While NRS Chapter 40 permits an award of reasonable attorney fees proximately caused by a construction defect, it does not guarantee it.” Id.
Because of the potentially harsh consequences of rejecting an OOJ, there are specific requirements that must be met to trigger them. An offer of judgment must be made in writing, can be made at any time at least 10 days before trial, and is irrevocable for 10 days with no provision for withdrawal before the 10 days expire. See Nava v. Second Judicial Dist. Court, 118 Nev. 396, 46 P.3d 60 (2002). A party may make successive offers of judgment, but the most recent offer extinguishes previous offers and is controlling for determining the date from which attorneys’ fees may be awarded. See Albios v. Horizon Communities, Inc. 132 P.3d 1022 (2006).
In Beattie v. Thomas, 99 Nev. 579, 668 P.2d 268, 274 (1983), the Nevada Supreme Court explained that the purpose of OOJs are not to cause plaintiffs to unfairly forego legitimate claims. However, when a valid offer of judgment is made, the offer is rejected, and the party rejecting the offer fails to obtain a more favorable judgment, a court must evaluate whether the plaintiff's claim was brought in good faith; whether the offer of judgment was reasonable and in good faith in both its timing and amount; whether the plaintiff's decision to reject the offer and proceed to trial was grossly unreasonable or in bad faith; and whether the fees sought by the offer are reasonable and justified. “After weighing the foregoing factors, the district judge may, where warranted, award up to the full amount of fees requested.” Id.
It is worth noting that in Albios v. Horizon Communities, Inc. 132 P.3d 1022 (2006), the Nevada Supreme Court held that when a party rejects a reasonable OOJ and is foreclosed from recovering fees and costs, the party is likewise foreclosed from an award of fees and costs under Chapter 40. This means that even if a builder fails to include a monetary settlement offer as part of a Chapter 40 response, it may still avoid paying the claimant’s fees and costs with a reasonable and timely OOJ.
Finally, it is important to remember that OOJs are a powerful tool that can cut both ways. If an OOJ is not reasonable and timely, or if it fails to contemplate all the potential recovery of an offeree, the OOJ may have no effect on the outcome of a case. Moreover, if a party rejects an OOJ and fails to obtain a more favorable judgment, that party could end up paying the offeror’s costs and attorney’s fees incurred from the date of the offer. Given this powerful impact, OOJs should be an integral part of pre-litigation planning and overall litigation strategy.
About the Author
Casey J. Quinn is an associate in the Las Vegas office of
Newmeyer & Dillion LLP. His practice focuses on complex commercial, construction, and insurance litigation and appellate work. Casey can be reached by email at Casey.Quinn@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Will Millennial’s Desire for Efficient Spaces Kill the McMansion?
September 10, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder Magazine reported that millennials are currently “inhabiting high-tech, yet cozy student housing and apartments” without having “outsized space expectations,” however, that may change over the next ten years as “their preference for the walkable convenience that often accompanies smaller living spaces will collide head on with their parents’ (and grandparents’) insatiable addiction for square footage.” Regardless, builders may decide to change based upon a younger generation that accepts “efficient spaces.”
According to Builder Magazine, Nick Lenhert, executive director at architectural firm KTGY, argued that the young “don’t really want what mom and dad have until they get married. Then all of a sudden things start to revert. They start getting realistic about what they need for the children and what they need for themselves. [Right now,] Gen Y is used to living in small spaces or with roommates because that’s all they can afford.”
However, John Thatch, principal and director of design at the architectural and planning firm Dahlin Group, believes that even as millennials get older and conceivably need greater square footage, there is still a possibility that their tendency toward efficient spaces will continue: “I’m hoping this is the generation [that pulls in house size] because our generation went gigantic. It’s a chance for architects to get back to design smaller, more thoughtful spaces that are flexible.”
Read the court decisionRead the full story...Reprinted courtesy of
Modular Homes Test Energy Efficiency Standards
August 06, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Systems Building Research Alliance (SBRA) will be putting three different energy standards to the test, according to Big Builder. Clayton Homes has been selected to build three modular homes, which will be used in a 15-month energy performance test conducted by Southern Energy Homes (SEHomes).
Each home will comply with a different standard: “one complies with the U.S. Department of Housing and Urban Development’s (HUD) thermal standards, one is an Energy Star-qualified home and one meets the DOE requirements for the Challenge Home Program, also known as a DOE Zero Energy Ready Home.”
Testing is expected to be completed July 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Bright Spot in Indianapolis
March 01, 2012 —
CDJ STAFFThe downtown Indianapolis area is the site of about 85 major building projects that are from groundbreaking to just complete. The Indianapolis Star reports that the cumulative worth of the projects is about $3 billion, a level of construction that Indianapolis has seen only once before.
About thirty of the projects are residential. The main commercial project is a $754 million hospital building. The boom in downtown Indianapolis is not matched elsewhere, with the Indianapolis Star reporting that in the rest of Central Indiana, construction has slowed.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Home Prices in 20 U.S. Cities Kept Climbing in January
April 06, 2016 —
Victoria Stilwell – BloombergHome values in 20 U.S. cities kept climbing in January, a sign the limited supply of available properties may push prices out of reach for some buyers.
The S&P/Case-Shiller index of property values increased 5.7 percent from January 2015, following a 5.6 percent gain in the year ended in December, the group said Tuesday in New York. That matched the median projection of 26 economists surveyed by Bloomberg. Nationally, prices rose 5.4 percent year-over-year.
Home values that are rising more quickly than incomes could pose a problem for the housing recovery, as they put purchases out of reach for first-time and low-income buyers. A wider selection of available homes will be needed to help keep price increases in an accessible range.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, Bloomberg