Some Work Cannot be Included in a Miller Act Claim
June 28, 2021 —
Christopher G. Hill - Construction Law MusingsThe Miller Act is close to my heart here at Construction Law Musings. Payment bond claims under the Miller Act help protect subcontractors on construction projects where the national government or its agencies are the owners of the property and therefore mechanic’s liens are unavailable. Even where you follow the proper claims process under this statute, the question remains as to what sorts of costs can be included in the claim.
A recent case out of the Eastern District of Virginia federal court in Alexandria, VA gives some insight into the limits of claims under the federal Miller Act. In Dickson v Forney Enterprises, Inc. et. al., the Court looked at the question of whether costs of a project manager’s purely clerical duties can be included and correspondingly whether performing those duties can extend the relevant one-year limitations period for filing suit.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
California Contractors – You Should Know That Section 7141.5 May Be Your Golden Ticket
February 18, 2020 —
Amy L. Pierce, Mark A. Oertel & John Lubitz - Lewis Brisbois Bisgaard & Smith LLPUnder California’s Contractors’ State License Law, Cal. Bus. & Prof. Code §§ 7000 et seq., all contractors’ and subcontractors’ licenses expire two years from the last day of the month in which the license issued, or two years from the date on which the renewed license last expired. The Contractors State License Board (CSLB) sends licensees a renewal application 60 to 90 days prior to the date the license is set to expire.
Most contractors have various controls in place to make sure that the renewal application is timely filed and the required fee paid. Even so, we are only human and mistakes are made, and a renewal application filing deadline can be missed for a variety of reasons, e.g., the licensee’s mailing address has not been updated on the CSLB’s records, the individual responsible for filing the license renewal is out on leave, there has been a death in the family or a serious health issue, etc. Quoting Robert Burns, even “[t]he best-laid schemes of mice and men go oft awry” (To a Mouse, 1786).
General contractors should be cognizant of both their and their subcontractors’ license renewal obligations and deadlines.
If a licensee missed timely filing its renewal application, Business & Professions Code Section 7141.5may provide some relief. Section 7141.5 provides that the Registrar of Contractors,
“may grant the retroactive renewal of a license if the licensee requests the retroactive renewal in a petition to the registrar, files an application for renewal on a form prescribed by the registrar, and pays the appropriate renewal fee and delinquency fee prescribed by this chapter. This section shall only apply for a period not to exceed 90 days from the due date and only upon a showing by the contractor that the failure to renew was due to circumstances beyond the control of the licensee.”
Reprinted courtesy of Lewis Brisbois Bisgaard & Smith LLP attorneys
Amy Pierce,
Mark Oertel and
John Lubitz
Ms. Pierce may be contacted at Amy.Pierce@lewisbrisbois.com
Mr. Oertel may be contacted at Mark.Oertel@lewisbrisbois.com
Mr. Lubitz may be contacted at John.Lubitz@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Litigation Roundup: “Post No Bills!”
April 02, 2024 —
Daniel Lund III - LexologyA company which is in the business of posting “advertising signs on temporary construction sites on behalf of clients” was “sued for trespass, conversion, and other torts” when it entered a site to remove posters. The company sought to have its insurance carrier cover the cost of its defense but was refused. A federal court lawsuit in California against the insurer ensued. The insurer prevailed on a Rule 12 motion to dismiss, and the insured appealed.
At issue: had an “occurrence” under the CGL policy taken place – that is, an “accident,” an “unexpected, unforeseen, or undesigned happening or consequence from either a known or unknown cause?” The appellate court noted that the company’s contractor “intended” to enter the work site and remove posters, which gave rise to the trespass claim. For its part, the company urged that the contractor’s actions “were based on erroneous information… [a] mistaken belief that it had the right or duty to enter the site and remove the posters….”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Contractor to Repair Defective Stucco, Plans on Suing Subcontractor
February 21, 2013 —
CDJ STAFFThe contractor for the Manatee County Judicial Center will be replacing the defective stucco on the building, but they have stated that they intend to go after the subcontractor who initially installed the defective stucco. The contractor, Balfour Beatty LLC, has said they will pay for the repairs, but Steve Holt, an executive of the firm said that “we have initiated a lawsuit against the subcontractor, who we believe was substantially or completely responsible to recover those funds.” Mr. Holt named Commercial Plastering as the subcontractor responsible.
Read the court decisionRead the full story...Reprinted courtesy of
Flooded Courtroom May be Due to Construction Defect
September 01, 2011 —
CDJ STAFFThe General Services Administration wouldn’t pin it on a construction defect, but a spokesperson said that a pipe that was misaligned during installation was the likely cause of a flood in the Thomas F. Eagleton US Courthouse on August 23. According to the St. Louis Dispatch, the burst pipe caused a 17-story waterfall in the courthouse, soaking ceilings and floors, and drenching the building’s contents.
The building was dedicated eleven years ago. During the nearly ten years before the building was complete, there were construction disputes and soil contamination issues.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Not in My Kitchen – California Supreme Court Decertifies Golden State Boring Case
November 26, 2014 —
Roger Hughes – California Construction Law BlogOn November 11, 2014, the California Supreme Court rejected the recent California Court of Appeals decision Golden State Boring & Pipe Jacking, Inc. v Eastern Municipal Water District, 228 Cal.App.4th 273 (2014) which we wrote about earlier by “decertifying” it (meaning that lawyers cannot cite to the case as legal precedent) The decertification removed a decision that added substantially to the confusion as to when an action on a payment bond is timely filed. Even though the decision was determined in accordance with pre-2014 statutes, the case was relevant precedent for construction attorneys when determining time deadlines for filing a claim on a bond.
Background
In July of this year, the California Court of Appeals for the Fourth Appellate District upheld a trial court’s granting of summary judgment against a project subcontractor Golden State Boring & Pipe Jacking, Inc. (GSB) who sued Safeco Insurance Company (Safeco) for unpaid contract amounts on a project payment bond issued by Safeco. Both at the trial level and on appeal Safeco successfully argued that GSB’s action on its payment bond claim was time barred by former California Civil Code Sections 3249 (now Section 9558), because it was filed more than six month after the period in which stop notices may be filed as provided by California’s Civil Code Section 3184 (now Section 9558).
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Construction May Begin with Documents, but It Shouldn’t End That Way
March 02, 2020 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Rob Mathewson. In his role as CEO, Rob handles strategy and partnerships for Geedra in addition to overseeing technology architecture and implementation. He has spent twenty years in sales and marketing management roles with experience in industrial, consumer and construction markets. Rob believes the construction industry is ripe for innovation, based on its massive size, yet low productivity. Even with such inefficiencies, a building still rises from the ground. Rob’s goal with Geedra is to leverage technology to increase transparency and communication so that projects can be completed with less risk, effort and cost. Prior to founding Geedra, Rob was the Chief Marketing Officer for Construction Documentation Services, where he was responsible for sales, marketing and business development. He spent 15 years in the chemical distribution business, including eleven years as the Northwest Branch Manager of a $50 million distributor. Rob was the founder and CEO for On The Spot Games, a board game startup. He is currently in the midst of a streak of over 2,900 consecutive days without a bad hair day.
An avid mentor himself, his own business inspirations come from problem solvers like Dean Kamon, innovative communicators like Seth Godin, fierce competitors like Lance Armstrong and global gurus like Thomas Friedman. When he’s not creating innovations in the construction industry, his passions include bike riding, throwing the ball around with his kids, and cooking. He is an accomplished public speaker and is a past president of Emerald City Toastmasters. Rob holds a B.S. in Manufacturing Engineering from Boston University and a MBA from Seattle University.
Construction folks are a focused bunch. Once a contractor signs a deal for a project, its team will immediately get to work generating and then executing a construction document set. For the entire duration of the schedule to follow, the construction team eats, sleeps and dreams about those documents. Their monomaniacal efforts continue until a building rises up from a patch of dirt in a matter of months.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Another Worker Dies in Boston's Latest Construction Accident
June 20, 2022 —
Scott Van Voorhis - Engineering News-RecordBoston Police and the US Occupational Safety and Health Administration are investigating a June 9 early morning construction accident that killed a worker in Boston’s Seaport district— the latest in a spate of fatalities at worksites across the city's metro area during the past 18 months.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of