Construction Problems May Delay Bay Bridge
May 10, 2013 —
CDJ STAFFFaulty bolts could lead to a delay in the opening of the Bay Bridge. Caltrans noticed problems with bolts and found that the bolts had cracked. Of the 98 bolts already tightened, 30 have failed. According to the San Francisco Chronicle, workers will be tightening all 288 bolts and then testing them. According to Tony Anziano, Caltrans’s toll bridge program manager, repairs could take one or two months. Mr. Anziano noted that the manufacturer might be responsible for part of the expense, but that the budget for the bridge also has funds set aside for unanticipated repairs.
The bolts were supplied by Dyson, an Ohio company, but it was clear whether Dyson manufactured the bolts or simply marketed them.
Read the court decisionRead the full story...Reprinted courtesy of
IRMI Expert Commentary: Managing Insurance Coverage from Multiple Insurers
May 11, 2020 —
Gregory D. Podolak, Philip B. Wilusz & Ashley McWilliams - Saxe Doernberger & VitaWhat do you do when less is more? In many loss scenarios, triggering coverage under multiple policies can be a critical and effective strategy. However, doing so has the potential to complicate the insurance recovery proceedings immensely, and possibly even undermine those overall goals. The relation of "other insurance" clauses, allocation schemes, and the practical impacts of interacting with multiple insurers can all leave the insured with some difficult questions.
We present here several scenarios that illustrate how these concerns can arise and how they should be addressed to avoid running into what The Notorious B.I.G.—had he been a coverage lawyer—would have called "The More Coverage We Come Across, the More Problems We See."
The "Other Insurance" Issue
This first scenario is where a single-year loss implicates multiple lines of coverage. Consider the following: a general contractor (GC) faces a property damage liability claim from an owner. As a prudent insured, the GC notifies its customary first line of defense, its commercial general liability (CGL) insurer, to provide a defense. As knowledge of the claim evolves, it appears an element of pollution may be involved. The GC also places its pollution insurer on notice. Later, it's determined that the GC may have a professional liability exposure, so it tenders a claim to its professional liability insurer. Now assume that each insurer accepts coverage.
Reprinted courtesy of Saxe Doernberger & Vita attorneys
Gregory D. Podolak,
Philip B. Wilusz and
Ashley McWilliams
Mr. Podolak may be contacted at gdp@sdvlaw.com
Mr. Wilusz may be contacted at pbw@sdvlaw.com
Ms. McWilliams may be contacted at amw@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Trivial Case
November 07, 2022 —
Garret Murai - California Construction Law BlogConstruction defect cases leading to physical injury are rarely trivial, at least in the eyes of the injured party, but alas sometimes they are as the next case,
Nunez v. City of Redondo Beach, 81 Cal.App.5th 749 (2022), demonstrates.
The Nunez Case
Monica Nunez, Vice President of Finance and Accounting at a restaurant chain and a part-time fitness instructor at a gym, tripped and fell on a public sidewalk in Redondo Beach. Ms. Nunez, who was in her forties, tripped following a group run when her back foot hit a sidewalk slab that was elevated at its highest point approximately 11/16 inches. Ms. Nunez landed on her left knee and right arm and in the process fractured her kneecap and elbow.
Ms. Nunez sued the City of Redondo Beach for her injuries alleging causes of action for dangerous conditions on public property under Government Code section 835, nuisance under Government Code section 815.2, and failure to perform a mandatory duty under Government Code section 815.6.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Settlement Payment May Preclude Finding of Policy Exhaustion: Scottsdale v. National Union
December 11, 2013 —
Heather Anderson — Higgins, Hopkins, McLain & Roswell, LLC.In the last year, the U.S. District Court for the District of Colorado found that a settlement payment from an excess insurance carrier to another primary insurance carrier precluded a finding of vertical exhaustion sufficient to trigger the primary carrier’s duty to indemnify. See Scottsdale Ins. Co. v. National Union Fire Ins. Co. of Pittsburgh, 2012 WL 6004087 (D. Colo. 2012). The Scottsdale case arose out of the construction of a 507-unit apartment complex in Arapahoe County, Colorado in which a number of defects became apparent during construction. As a result, the owner of the project sued the general contractor and/or the construction manager, seeking to recover more than $22 million for various construction deficiencies. Id. at *1.
The general contractor was insured under policies issued by several carriers. Scottsdale Insurance Co. (“Scottsdale”) and National Union Fire Ins. Co. (“National Union) provided umbrella coverage, and CNA and American Zurich Ins. Co. (“Zurich”) provided primary insurance under commercial general liability policies. About five years later, the construction defect case settled for $8.5 million dollars.
Read the court decisionRead the full story...Reprinted courtesy of
Heather AndersonHeather Anderson can be contacted at
anderson@hhmrlaw.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Michael Baker Intl. Settles Federal Pay Bias Allegations
February 26, 2024 —
James Leggate - Engineering News-RecordMichael Baker International Inc. agreed to pay $122,299 in back wages as part of an agreement with the U.S. Dept. of Labor to resolve allegations that the engineer-consultant paid women in four job titles less than their male counterparts.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Top 10 Insurance Cases of 2023
January 29, 2024 —
Jeffrey J. Vita & Michael A. Amato - Saxe Doernberger & Vita, P.C.Federal and state courts tackled many interesting insurance-related issues this past year. Perhaps no state had a more impactful year than Illinois, which held that construction defects could constitute an occurrence, that a LEG 3 “extension” attempting to preclude coverage for faulty or defective workmanship was ambiguous as a matter of law (applying Illinois law), and that ostensibly prohibitive “catch-all exclusions” can render policy language ambiguous in favor of coverage. Other courts wrestled with procedural inquiries, such as the legal duty of a broker in providing notice to an insurer or the ability of an insured to recoup its attorneys’ fees in pursuing a coverage action against its insurer. These are merely a sampling of the impactful insurance decisions rendered in 2023.
Each year, we endeavor to identify cases of general interest to our clients and the broader insurance community. Specifically, we attempt to identify trends, cases of first impression, cases illustrating conflicts among the courts, or cases dealing with emerging issues. We now proudly unveil the top 10 most influential coverage decisions of 2023 and look ahead to a few cases to watch as 2024 unfolds.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Michael A. Amato, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at JVita@sdvlaw.com
Mr. Amato may be contacted at MAmato@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Crisis Averted! Pennsylvania Supreme Court Joins Other Courts in Finding that Covid-19 Presents No Physical Loss or Damage for Businesses
October 21, 2024 —
Edward M. Koch & Marc L. Penchansky - White and Williams LLPSeeking to find some relief from business losses experienced during the COVID-19 pandemic, many businesses turned to their property insurers for coverage for their lost income. A clear national trend emerged among courts deciding the issue, as most businesses could not establish coverage because they had not experienced a “direct physical loss of or damage to their covered property” as required by most policies.
While this legal question may have become an afterthought for many attorneys, the question remained an open one in Pennsylvania while the Pennsylvania Supreme Court considered two contradictory holdings issued in the Superior Court on this topic. Compare Macmiles, LLC v. Erie Ins. Exch., 286 A.3d 331 (Pa. Super. 2022) (holding there was no coverage for loss of use of a commercial property unaccompanied by any physical alteration or other physical condition that rendered the property unusable or uninhabitable) with Ungarean v. CNA, 286 A.3d 353 (Pa. Super. 2022) (holding that the policy at issue was ambiguous and therefore the policy covered the insured for COVID-related business losses). Last week, the Supreme Court considered the Superior Court’s holdings in Macmiles and Ungarean and held, at long last, that COVID-19 did not cause a direct physical loss of or damage to covered property.
Reprinted courtesy of
Edward M. Koch, White and Williams LLP and
Marc L. Penchansky, White and Williams LLP
Mr. Koch may be contacted at koche@whiteandwilliams.com
Mr. Penchansky may be contacted at penchanskym@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of