Colorado Statutes of Limitations and Repose, A First Step in Construction Defect Litigation
December 20, 2012 —
CDJ STAFFGrund Dagner, a law firm operating in Denver and Boulder, Colorado notes on their blog that when defending a construction defect claim, one of their first steps is to determine if the claims are affected by the statutes of limitations or repose, and that they “have had much success raising these defenses with the court before trial.”
Colorado has a two-year statute of limitations, starting from when the homeowner discovers the defect. Further, Colorado’s statute of repose precludes lawsuits beginning “more than six years after the substantial completion of the improvement to the real property.”
Grund Dagner notes that they “recently obtained dismissal of claims related to eight of 22 buildings in a condominium project, where the homeowners in those building observed the defects more than two years before the HOA initiated its claims against our client.”
Read the court decisionRead the full story...Reprinted courtesy of
Architecture, Robotics, and the Importance of Human Interaction – An Interview with Prof. Kathrin Dörfler
September 21, 2020 —
Aarni Heiskanen - AEC BusinessWe sat down with Professor Kathrin Dörfler of the Technical University of Munich (TUM) in advance of WDBE 2020. We discussed the importance of innovation and how her research focuses on the need for practical and productive solutions when it comes to on-site support.
Digital and technical innovation plays an essential role in optimizing the modern built environment. Now leading the Augmented Fabrication Lab (AFAB) in TUM, Professor Kathrin Dörfler quickly saw the need for practical solutions early in her career.
The Importance of ‘Need’
“I’m originally an architect,” she says. “I studied digital art and architecture and my tendency to go toward digital fabrication came from this proximity to computational design and the need to use robots for fabrication. There was no other way to build the things you created in your virtual space without using machinery.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Business Risk Exclusions Bar Coverage for Construction Defect Claims
June 28, 2013 —
Tred EyerlyThe federal district court assumed there was "property damage" caused by an "occurrence," but found the business risk exclusions barred coverage for construction defect claims. Hubbell v. Carney Bros. Constr., 2013 U.S. Dist. LEXIS 68331 (D. Colo. May 13, 2013).
The plaintiffs entered a construction contract with the insured general contractor to build a home. After the project was one-third completed, plaintiffs terminated the contract. Experts hired by plaintiffs found a failure to properly site the residence, as the house was constructed 48 feet from the intended location; violations of county height restrictions; failure to follow building plans, which were themselves deficient; and an improperly poured foundation. The experts estimated that the costs of repairing the property to be between $1.3 and $1.5 million, and that the cost of demolishing the structure and rebuilding it would be between $1.1 and $1.3 million.
After plaintiff filed suit, a stipulated judgment of $1.952 million was entered.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
White and Williams Celebrates 125th Anniversary
March 04, 2024 —
White and Williams LLPWhite and Williams LLP, a global-reaching law firm headquartered in Philadelphia, PA, is celebrating its 125th Anniversary. Since its founding in 1899, the Firm has grown to two hundred lawyers with offices in Connecticut, Delaware, Maryland, Massachusetts, New Jersey, New York, Rhode Island, and Pennsylvania.
“We are proud to celebrate our 125th anniversary. We are grateful to all of our clients for the trust that they place in our firm to handle their important litigation and transactional matters. The partnership we enjoy with our clients is special and a source of great pride to all of us at White and Williams. We are deeply committed to the success of our clients' goals and objectives,” stated Tim Davis, Managing Partner. “We look forward to celebrating this historic milestone with our clients, attorneys, staff and alumni throughout 2024,” added Davis.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Claim Against Broker for Failure to Procure Adequate Coverage Survives Summary Judgment
April 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe broker's motion for summary judgment, seeking to dismiss negligence claims for failure to obtain adequate coverage, was denied by the court in Voss v. The Netherlands Ins. Co., 2014 N.Y. LEXIS 384 (N.Y. Ct. App. Feb. 25, 2014).
The insured met with a representative of CH Insurance Brokerage Services Co., Inc. (CHI) to discuss coverage for the premises and her two companies. At CHI's request, the insured shared information on sales figures for calculating business interruption coverage. The broker represented that CHI would reassess and revisit the coverage needs as her business grew.
CHI recommended $75,000 per incident in coverage for business interruption losses. The insured questioned whether the $75,000 limit was adequate, but the broker assured her that it was sufficient. The insured then accepted the recommendation. Subsequently, the insured's business grew, but CHI renewed the policy with the same $75,000 business interruption limit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Jersey Shore gets Beach Prisms Designed to Reduce Erosion
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFThirty-five beach prisms manufactured by Smith-Midland Corporation have been installed along the Jersey shore in Ocean Gate, New Jersey. According to the Wall Street Journal, “The prisms protect homes, prevent erosion, and reduce impacts from natural disasters like Hurricane Sandy.” They “are made with a built-in parabolic curve that scatters waves away as spray instead of allowing them to crash up onto the vulnerable shoreline.”
Ocean Gate’s Mayor Paul J. Kennedy stated, "We've been losing beach year after year with the Nor'easters we get. So we came up with an idea that hopefully will work,” The Wall Street Journal reported.
Read the court decisionRead the full story...Reprinted courtesy of
No Bond, No Recovery: WA Contractors Must Comply With WA Statutory Requirements Or Risk Being Barred From Recovery If Their Client Refuses To Pay
September 18, 2018 —
Joshua Lane - Ahlers Cressman & Sleight PLLCThe risk that a contractor’s client may refuse to pay the full contract balance is a day-to-day reality for every contractor. That risk – and the stress it causes in the mind of any contractor – is tempered by the knowledge that Washington statutes provide contractors with ready access to the courts to file a lawsuit and be fully compensated for the work performed. But a recent case provides a grim reminder that the same statutes that giveth court access can also taketh away.
Washington’s Contractor Registration Act (“WCRA”)[1] requires every contractor engaging or offering to engage in services in Washington to register with the Department of Labor and Industries (”L&I”). In order to sue to collect compensation for work or to enforce a contract, a contractor must prove that he/she “was a duly registered contractor and held a current and valid certificate of registration at the time he or she contracted for the performance of such work or entered into such contract.”[2] In order to conclude that a contractor has substantially comply with these requirements, a court must find that:
(1) The department has on file the information required by RCW 18.27.030; (2) the contractor has at all times had in force a current bond or other security as required by RCW 18.27.040; and (3) the contractor has at all times had in force current insurance as required by RCW 18.27.050.[3]
Read the court decisionRead the full story...Reprinted courtesy of
Joshua Lane, Ahlers Cressman & Sleight PLLCMr. Lane may be contacted at
joshua.lane@acslawyers.com
Touchdown! – The Construction Industry’s Winning Audible to the COVID Blitz
February 08, 2021 —
Bill Shaughnessy, Jones Walker, LLP - ConsensusDocsCOVID-19 has changed the way we live, work, play football, and build. As with all of society (and our football leagues and teams), the construction industry was impacted over the last year through the implementation of new safety protocols in response to COVID-19. While some construction projects were delayed or put on hold, much of the construction industry was fortunate to continue to build throughout the pandemic. Building under COVID-19 safety protocols led contractors to “call an audible” in order to make up for lost time and to save costs. In doing so, many contractors started incorporating or expanding the use of under-utilized tools, resources, capabilities, and technology such as pre-fabrication, and modular construction, while at the same time reexamining planning methods, monitoring critical schedule activities, and ways to better execute construction.
In many ways, the effects of COVID-19 safety protocols and measures implemented by contractors in the past year have led to more efficient and cheaper construction projects now and for the future. So, it is not surprising as we turn our calendars to 2021 that contractors can expect these tools, resources, and technologies to be utilized more in the years ahead, even once the pandemic subsides. This article highlights some of the “positive” effects of COVID-19 on projects and highlights several ways contractors attempted to increase efficiency and reduce costs in response to the pandemic.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker, LLPMr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com