California Enacts New Claims Resolution Process for Public Works Projects
January 19, 2017 —
Garret Murai – California Construction Law BlogIf you’re a public entity or contractor involved in public works construction you should be aware of a new law,
AB 626, which took effect on the first of this year and establishes a new mandatory claims resolution process for disputes on public works projects. Here’s what you need to know:
What is the new law and where is it codified at?
AB 626 added new Public Contract Code Section 9204 that according to the bill’s author, Assemblymember David Chiu of San Francisco, establishes “a claim resolution process applicable to any claim by a contractor in connection with a public works project.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Miller Act and “Public Work of the Federal Government”
March 01, 2017 —
David Adelstein – Florida Construction Legal UpdatesThe Miller Act applies to the “construction, alteration, or repair of any public building or public work of the Federal Government.” 40 U.S.C. s. 3131.
A recent opinion out of the Northern District of Oklahoma sheds light on what the Miller Act means regarding its application to any public work of the Federal Government. See U.S. v. Bronze Oak, LLC, 2017 WL 190099 (N.D.Ok. 2017). If the project is not a public works project of the Federal Government, the Miller Act does not apply.
In this case, the Department of Transportation entered into an agreement with the Cherokee Nation where the Department would provide lump sum funding and the Nation would use the money to fund transportation projects. Based on the federal funding, the Nation issued a bid for a transportation project in Mayes County, Oklahoma and the project was awarded to a prime contractor. The prime contractor provided a payment bond that identified the United States as the obligee (as a Miller Act payment is required to do) and stated that it was issued per the Miller Act. Thereafter, the Nation and Mayes County, Oklahoma entered into a Memorandum of Understanding where the County would assume responsibility for the construction and maintenance of the project and the Nation would pay the County an agreed amount upon the completion of the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Even Where Fraud and Contract Mix, Be Careful With Timing
April 12, 2021 —
Christopher G. Hill - Construction Law MusingsI have often discussed the limited circumstances under which a construction contract claim and a fraud claim can coexist. A recent case from the Western District of Virginia federal court demonstrates that care is necessary even in those limited circumstances.
In Fluor Fed. Sols., LLC v. Bae Sys. Ordinance Sys., the Court examined the question of a fraud statute of limitations under Virginia law. The basic facts found in the Complaint are these:
In 2011, the United States Army awarded BAE Systems Ordinance Systems Inc. a basic ordering agreement under which BAE was responsible for modernization projects at the Radford Army Ammunition Plant. This action stems from a subcontract between Fluor Federal Solutions LLC and BAE, under which Fluor agreed to design and construct a new natural gas boiler at the plant. Fluor has completed work on the project, and BAE has accepted that work. Nonetheless, Fluor claims that BAE has refused or failed to pay for the balance of the project costs. Fluor alleges that BAE received several changes to its prime contract from the Army but did not pass those changes along to Fluor until after BAE solicited a bid from Fluor and entered a contract with Fluor to build a temporary facility. Instead, BAE continued to misrepresent the scope of the project. Fluor alleges that the change in plans increased costs substantially, but that BAE withheld information about those changes so that it could solicit lower bids. Fluor alleges that it requested a copy of BAE’s prime contract on numerous occasions, but BAE failed to provide a copy of it. Instead, Fluor submitted a request under the Freedom of Information Act. It received a copy of BAE’s prime contract on Oct. 3, 2018.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
How to Mitigate Lien Release Bond Premiums with Disappearing Lien Claimants
May 20, 2019 —
Scott MacDonald - Ahlers Cressman & Sleight PLLCIt is one of those dreaded business situations that plagues the construction industry, especially in times of economic downturn—what to do when a lower-tier entity files a lien against a property then disappears. It has happened to countless owners, general contractors, subcontractors, and even some particularly unlucky sub-tier subcontractors and suppliers. Here is how it arises: a project is moving along, then performance or payment issues arise, and a company that is over extended or unwilling to continue work stops performance, walks off the job, and files a lien against the property for whatever amounts were allegedly unpaid. Often, the allegedly unpaid sums were legitimately withheld due to a good faith dispute over payment/performance, and it is not unusual for the defaulting entity to not be entitled to any of the sums claimed in the lien. Regardless, the lien stays on the property, and pressure is applied from the “upstream” entities to the party who contracted with the defaulting entity to “deal” with the lien.
Oftentimes, a contract will require the parties to “deal” with a lien by obtaining a lien release bond (“release bond”). For those lucky enough to not have encountered this issue, a release bond is a nifty statutory device whereby a surety agrees to record a release bond for the full claimed amount of the lien, with the release bond substituting in for the liened property, effectively discharging the property from liability under the lien. In other words, the lien is released from the property and attaches to the release bond. If the lien claimant recovers on its lien, it is technically satisfied by the surety providing the release bond (or the party who agrees to indemnify and defend the release bond). In exchange for delivering the release bond, the surety demands yearly premiums be paid on the release bond amount
Read the court decisionRead the full story...Reprinted courtesy of
Scott MacDonald, Ahlers Cressman & Sleight PLLCMr. MacDonald may be contacted at
scott.macdonald@acslawyers.com
Quick Note: Staying, Not Dismissing, Arbitrable Disputes Under Federal Arbitration Act
July 31, 2024 —
David Adelstein - Florida Construction Legal UpdatesAs you hopefully know from posted articles, arbitration is a creature of contract. Stated differently, there must be a contractual basis to have a dispute resolved through binding arbitration. The Federal Arbitration Act (FAA) applies to transactions involving interstate commerce. Oftentimes, lawsuits are filed despite an arbitration provision in a contract because parties can, if they desire, waive their rights to have their dispute resolved through binding arbitration.
In what should not be a shocker, the United States Supreme Court in Smith v. Spizzirri, 144 S.Ct. 1173, 1178 (2024), held that when a federal “district court finds that a lawsuit involves an arbitrable dispute, and a party requests a stay pending arbitration, section 3 of the FAA compels the court to stay the proceeding.” Dismissing the lawsuit should not be the option. Staying the lawsuit should.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Chicago Developer and Trade Group Sue City Over Affordable Housing Requirements
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Chicago Tribune reported that Hoyne Development and Home Builders Association of Greater Chicago are suing the city of Chicago, claiming that the “Affordable Requirements Ordinance is unconstitutional because it involves the taking of private party without ‘just compensation,’ violating the Fifth Amendment.”
Shannon Breymaier, spokeswoman for Chicago Mayor Rahm Emanuel, however, disputes the claims, and told the Chicago Tribune in an email that the city planned to “defend the ordinance vigorously.”
Read the court decisionRead the full story...Reprinted courtesy of
Daiwa House to Invest 150 Billion Yen in U.S. Rental Housing
March 07, 2014 —
Kathleen Chu – BloombergDaiwa House Industry Co. (1925), Japan’s biggest homebuilder by market value, plans to invest 150 billion yen ($1.48 billion) in U.S. rental housing, three times more than it had aimed to allocate to overseas investments, to boost revenue.
Daiwa House will acquire and develop leasing properties in Texas and allocate the funds over the next three years, the Osaka-based company said in an e-mailed statement today. The homebuilder targets 50 billion yen of revenue in the U.S. by the year ending March 2019, it said.
Japan’s shrinking population has prompted the country’s homebuilders such as Daiwa House to seek new revenue sources. Texas is the most that Daiwa House is investing overseas for rental housing and compares with the 50 billion yen the company had announced for investments abroad in its mid-term plan in November.
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen Chu, BloombergMs. Chu may be contacted at
kchu2@bloomberg.net
Slip and Fall Claim from Standing Water in Parking Garage
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFIn Metairie, Louisiana, Paul Unkauf filed a lawsuit after he allegedly “slipped and fell on standing water in the parking garage,” located at Heritage Plaza, according to the Louisiana Record. The defendants, Stewart Development LLC, Stirling Properties LLC, Platinum Parking LLC and First Financial Company, are “accused of permitting standing water to dampen the pathway leading to the elevator bank, failing to dry the pathway, failing to warn of the hazard, failing to properly inspect the area in question, failing to provide a safe means of exit and entrance, being careless and negligent under the circumstances, failing to properly identify and correct defects in design and failing to properly supervise and train employees,” reports the Louisiana Record.
Unkauf is seeking an “unspecified amount in damages” for “medical expenses, physical pain, loss of function, mental anguish, emotional distress, loss of enjoyment of life and permanent partial disability.”
Read the court decisionRead the full story...Reprinted courtesy of