N.J. Appellate Court Applies Continuous Trigger Theory in Property Damage Case and Determines “Last Pull” for Coverage
November 15, 2017 —
K. Alexandra Byrd – Saxe Doernberger & Vita, P.C.The New Jersey Superior Court, Appellate Division, published an important decision addressing several fundamental issues regarding how a commercial general liability (CGL) policy applies to long-term property damage. The court held that: (1) a continuous trigger theory of coverage may be applied to third-party liability claims involving progressive property damage caused by an insured’s allegedly defective work; (2) the “last pull” (i.e., the cutoff point) of the continuous trigger is when the “essential nature and scope” of the property damage first becomes known or could reasonably be known; and (3) the “last pull” is not when the property damage is “attributed” to the insured’s faulty work.
The underlying action in Air Master & Cooling Inc. v. Selective Ins. Co., et al. 1 concerned property damage arising out of the construction of a seven-story, 101-unit condominium building in Montclair, New Jersey. The project’s construction manager hired Air Master & Cooling, Inc. (Air Master) to perform HVAC work on the project, including installing individual HVAC equipment in each resident’s unit from 2005 to 2008. In early 2008, unit owners began complaining about water infiltration and damage to their windows, ceilings, and other portions of their units. The general contractor and developer began assessing the damage and making repairs. Eventually, in April 2010, an expert consultant performed a moisture survey of the roof and discovered 111 areas that were damaged by water infiltration. The expert report indicated that “it [was] impossible to determine when [the] moisture infiltration occurred.”
Read the court decisionRead the full story...Reprinted courtesy of
K. Alexandra Byrd, Saxe Doernberger & Vita, P.C.Ms. Byrd may be contacted at
kab@sdvlaw.com
Revolutionizing Buildings with Hybrid Energy Systems and Demand Response
January 08, 2024 —
Aarni Heiskanen - AEC BusinessA recent study conducted by the Finnish Building Services 2030 group explores the potential technologies and business prospects for adaptable energy systems within buildings.
Building Services 2030 is a Finnish consortium of Aalto University, Tampere University, and 14 industry partners. The consortium has defined a shared vision for the Finnish building service sector and researches topics that help reach the vision. My company is responsible for the group’s communication, so I eagerly read the research reports as they come out.
One of the new reports I found very timely is about the energy flexibility of buildings. The authors are Senior Researcher Juha Jokisalo and Professor Matti Lehtonen from Aalto University. They highlight how the contemporary energy landscape is undergoing a significant transformation.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Partner Jonathan R. Harwood Obtained Summary Judgment in a Case Involving a Wedding Guest Injured in a Fall
December 30, 2019 —
Jonathan R. Harwood - Traub Lieberman PerspectivesOn September 30, 2019, Traub Lieberman partner Jonathan Harwood obtained summary judgment in an action involving a guest injured in a fall at a wedding. Traub Lieberman’s client owned the property where the fall occurred. Plaintiff fell while exiting a row of seats after the bridal party had recessed down the aisle. Plaintiff claimed that she tripped over the raised side of a paper runner that had been placed in the aisle at the property. Plaintiff brought an action against Traub Lieberman’s client (the owner of the building) and the florist that had provided the runner. The owner had provided the bridal party with access to the property but did not assist in the set up for the wedding or have any employees present during the ceremony. The florist had supplied the runner for the wedding. The florist commenced a third-party action against the bride, whose wedding party had actually placed the runner in the aisle. Plaintiff asserted that the runner had become bunched and crumpled during the ceremony, creating a dangerous condition. She further asserted that the owner was responsible for her injuries since the dangerous condition existed on its property and it should have an employee present to insure no dangerous conditions existed.
During the course of discovery, Mr. Harwood established that no one representing the owner was present during the wedding, had any involvement in the placement of the runner or had received any complaints about the runner. In support of the motion for summary judgment Mr. Harwood introduced pictures showing, in conjunction with deposition testimony, that there were no problems with the runner minutes before plaintiff’s fall. Mr. Harwood also argued that the alleged defect did not involve the property itself, absolving the owner of any obligation to plaintiff. In granting the motion for summary judgment, the court held that evidence and testimony showed that the owner neither created the condition nor had actual or constructive notice that any dangerous condition existed. The court also held that there the owner did not have any duty to have a representative present during the wedding since the property itself was not dangerous or defective. Finally, the court held that the condition of the runner was open and obvious and not inherently dangerous.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan R. Harwood, Traub LiebermanMr. Harwood may be contacted at
jharwood@tlsslaw.com
Deadline Nears for “Green Performance Bond” Implementation
December 03, 2024 —
Christopher G. Hill - Construction Law MusingsFor this weeks Guest Post Friday at Musings, we welcome Surety Bonds.com, a leading online surety provider. SuretyBonds.com specializes in educating current and prospective business owners about local surety requirements. To keep up with surety bond trends, follow and Surety Bonds Insider blog and @suretybond on Twitter.
Professionals who work in the construction industry know the laws that regulate the market change constantly. Unfortunately, even government agencies are flawed, which means they sometimes establish nonsensical, arbitrary regulations that leave construction professionals even more confused as to how they’re expected to do their jobs.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Miller Act and “Public Work of the Federal Government”
March 01, 2017 —
David Adelstein – Florida Construction Legal UpdatesThe Miller Act applies to the “construction, alteration, or repair of any public building or public work of the Federal Government.” 40 U.S.C. s. 3131.
A recent opinion out of the Northern District of Oklahoma sheds light on what the Miller Act means regarding its application to any public work of the Federal Government. See U.S. v. Bronze Oak, LLC, 2017 WL 190099 (N.D.Ok. 2017). If the project is not a public works project of the Federal Government, the Miller Act does not apply.
In this case, the Department of Transportation entered into an agreement with the Cherokee Nation where the Department would provide lump sum funding and the Nation would use the money to fund transportation projects. Based on the federal funding, the Nation issued a bid for a transportation project in Mayes County, Oklahoma and the project was awarded to a prime contractor. The prime contractor provided a payment bond that identified the United States as the obligee (as a Miller Act payment is required to do) and stated that it was issued per the Miller Act. Thereafter, the Nation and Mayes County, Oklahoma entered into a Memorandum of Understanding where the County would assume responsibility for the construction and maintenance of the project and the Nation would pay the County an agreed amount upon the completion of the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Subsurface Water Exclusion Found Unambiguous
July 14, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Eighth Circuit rejected the policyholder's appeal on the ambiguity of a subsurface water exclusion. Bull v. Nationwide Mut. Fire Ins. Co., 2016 U.S. App. LEXIS 9703 (8th Cir. May 27, 2016).
Michael Bull, the insured, experienced a leak from a buried pipe beneath his garage slab. The leak caused settling and mold, including the settling and cracking of his foundation, a brick walkway, and interior walls.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
EPA and the Corps of Engineers Repeal the 2015 “Waters of the United States” Rule
January 13, 2020 —
Anthony B. Cavender - Gravel2GavelThe pre-publication version of the final rule to be promulgated by EPA and the U.S. Army Corps of Engineers (ACOE) to repeal the 2015 redefinition of the Clean Water Act’s term “Waters of the United States” which is the linchpin of these agencies’ regulatory power under the CWA, was made available on September 12, 2019. The rule should be published in the Federal Register in the next few weeks, and it will be effective 60 days thereafter. Many challenges are expected to be filed in the federal courts.
The 2015 rule was very controversial, and petitions challenging the rule were filed in many federal district courts, several courts of appeal, and finally in the Supreme Court (see NAM v. Department of Defense), which held that all initial challenges must be filed in the federal district courts. The upshot of these challenges is that, at this time, the 2015 rule has been enjoined in more than half the states while the other states are bound by the 2015 rule, a situation which is frustrating for everyone.
In addition to repealing the 2015 rule, the agencies also restored the pre-2015 definition had had been in place since 1986. As a result, the pre-2015 definition of waters of the U.S. will again govern the application of the following rules: (a) the ACOE’s definition of “waters of the U.S.” at 33 CFR Section 328.3; (b) EPA’s general Oil Discharge rule at 40 CFR Section 110; (c) the SPCC rules at 40 CFR Part 112; (d) EPA’s designation of hazardous substances at 40 CFR Part 116; (e) EPA’s hazardous substance reportable quantity rule at 40 CFR Part 117; (f) the NPDES permitting rules at 40 CFR Part 122; (g) the guidelines for dredged or fill disposal sites at 40 CFR Part 230; (g) Exempt activities not requiring a CWA 404 permit (guidelines for 404 disposal sites at 40 CFR Part 232); (h) the National Contingency Plan rules at 40 CFR Part 300; (i) the designation of reportable quantities of hazardous substances at 40 CFR Part 302; and (j) EPA’s Effluent Guidelines standards at 40 CFR Part 401.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Hawaii Appellate Court Finds Duty to Defend Group Builders Case
May 10, 2013 —
Tred EyerlyOn May 19, 2010, the Hawaii Intermediate Court of Appeals determined construction defect claims did not constitute an occurrence under a CGL policy.Group Builders, Inc. v. Admiral Ins. Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010) ("Group Builders I"). The appeal in Group Builders I, however, only addressed the duty to indemnify. The ICA has now issued a second decision (unpublished), holding that there is was duty to defend Group Builders on the construction defect claims under Hawaii law, based upon the policy language and the allegations in the underlying complaint. Group Builders, Inc. v. Admiral Ins. Co., 2013 Haw.App. LEXIS 207 (Haw. Ct. App. April 15, 2013).
The underlying suit involved allegations by Hilton Hotels Corp. that Group Builders, a subcontractor working on an addition to the hotel, was responsible for mold found after completion of the project. Hilton alleged that the "design, construction, installation, and/or selection of the . . . building exterior wall finish . . . did not provide an adequate air and/or moisture barriers." The counts alleged against Group Builders included breach of contract and negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyMr. Eyerly can be contacted at