Insured's Claim for Water Damage Dismissed with Leave to Amend
August 12, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss the insured's claim for water damage under a homeowners' policy, but granted leave to amend. Thompson v. State Farm Gen. Ins. Co., 2024 U.S. Dist. LEXIS 98486 (C.D. Cal. June 3, 2024).
The insureds' first amended complaint alleged they "suffered a sudden and accidental water loss below their slab in their home." A plumber hired by the insureds discovered "a copper pipe burst inside a structural concrete footing between a manifold in the living room and the water heater." The insureds notified their insurer, State Farm.
Claim adjuster Andrea Acevedo conducted a visual inspection. The complaint alleged she did not "inspect or view the pipe, or have a testing conducted on the pipe." Acevedo sent a letter denying the insureds' claim based upon her finding that "because the loss was caused by a slab leak, there is no coverage available for the loss." The letter explained that the hot water supply line under the home failed due to wear, tear, deterioration and/or electrolysis. The predominant cause of loss to the failed pipe was due to one or a combination of rust, electrolysis, corrosion, wear, tear and/or deterioration. The policy did not cover water damage caused by water from below the surface of the ground. Further coverage for wear, tear, deterioration, rot, mold, maintenance, water from below the surface of the ground and a continuous or repeated seepage or leakage of water was excluded.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insured’s Bad Faith Insurance Claim Evaporates Before its Eyes
August 03, 2020 —
Garret Murai - California Construction Law BlogSometimes it’s right there before your eyes. Then, poof, it’s gone. This was the experience of one insured, who brought a bad faith insurance denial claim against his insurer thinking that the facts were in his favor, only to discover they were not.
The 501 E .51st Street Case
The Water Main Break and AGI’s Report
The owner of a 10-unit apartment building built in 1963, 501 East 51st Street, Long Beach-10 LLC (just rolls off the tongue doesn’t it?), filed a bad faith action against its insurer Kookmin Best Insurance Co., Ltd., after it denied 501 East’s insurance tender following a water main break that caused the building’s foundation to subside.
The water main break occurred sometimes between December 31, 2015 and January 2, 2016 next to the southwest side of the building. 501 East tendered its insurance claim to Kookmin on March 8, 2016, and in April 2016, presented a report prepared by American Geotechnical, Inc. (“AGI”) concerning damage to the building. According to the report prepared by AGI, AGI conducted a “limited geotechnical investigation” to “evaluate site conditions relating to the reported building distress following a waterline breach near the south end of the building.” The scope of AGI’s investigation was limited to “observation, photo documentation of the site conditions, [and[ floor-level survey of the interior of the first level units.” AGI’s investigation did not involve any subsurface investigation or soil testing.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Florida Self-Insured Retention Satisfaction and Made Whole Doctrine
March 11, 2014 —
Scott Patterson – CD CoverageIntervest Construction of Jax, Inc. v. General Fidelity Insurance Co., * So.2d * (Fla. 2014), the issue was whether the insured general contractor could satisfy the SIR in its CGL policy with funds it received from the insurer of a subcontractor in settlement of the general contractor’s contractual indemnity claim against that subcontractor. ICI was the general contractor for a residence sold to Ferrin. Several years after completion, Ferrin suffered injuries in a fall while using attic stairs installed by ICI’s subcontractor Custom Cutting. Ferrin sued ICI but not Custom Cutting. ICI was insured by General Fidelity with a $1M SIR. ICI sought contractual indemnity from Custom Cutting. The Ferrin suit was ultimately settled for $1.6M. Custom Cutting’s CGL insurer paid $1M to ICI to resolve ICI’s contractual indemnity claim. Using the $1M paid on behalf of Custom Cutting and $300K of its own funds, ICI paid $1.3M to Ferrin. General Fidelity paid the remaining $300K with an agreement with ICI that each was entitled to seek reimbursement of $300K from the other. ICI filed suit in Florida state court. General Fidelity removed to federal court. The Eleventh Circuit certified the relevant questions to the Supreme Court of Florida.
The Florida Supreme Court first held that the General Fidelity SIR allowed ICI to satisfy the SIR through indemnification payments received from a third party. While the SIR provision stated that it must be satisfied by the insured, it did not include any language proscribing the source of the funds used by the insured to satisfy the SIR. The court distinguished other decisions where the SIR endorsement expressly stated that payments by others, including other insurers, could not satisfy the SIR. The court also relied on the fact that ICI “hedged its retained risk” by paying for its entitlement to contractual indemnification from its subcontractor years prior to purchasing the General Fidelity policy.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Patterson, CD Coverage
One Sector Is Building Strength Amid Slow Growth
November 18, 2019 —
Michael Msika - BloombergIf you had to guess which stocks are posting top gains given this year’s gloomy economic outlook, you might be surprised by the answer.
Construction and material shares, despite most macro indicators pointing to slowing global growth, are now leading the pack in Europe. The sector’s up 32% already this year, knocking food-and-drinks stocks off the pedestal, and there appear few signs of the rally stopping anytime soon.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Msika, Bloomberg
Partners Jeremy S. Macklin and Mark F. Wolfe Secure Seventh Circuit Win for Insurer Client in Late Notice Dispute
November 12, 2019 —
Jeremy S. Macklin & Mark F. Wolfe - Traub Lieberman PerspectivesIn a written decision dated August 12, 2019, authored by Chief Judge Diane P. Wood, the U.S. Court of Appeals for the Seventh Circuit ruled in favor of Traub Lieberman’s insurer client, affirming the District Court’s grant of summary judgment in the insurer’s favor. Partners, Jeremy S. Macklin and Mark F. Wolfe, represented the insurer client in the District Court and before the Seventh Circuit. Macklin argued the case before the Seventh Circuit on behalf of the insurer on May 28, 2019.
The insurer client issued an excess liability policy to Deerfield Construction, a telecommunications construction company, which incorporated the notice requirements of the primary liability insurance policy issued by American States Insurance Company. The insured’s employee was involved in an automobile accident in 2008, during the effective dates of the excess liability policy. A lawsuit arising from the accident was filed and served in 2009. While Deerfield Construction, through its retained insurance intermediary, provided immediate notice of the accident and lawsuit to the primary liability insurer, the insurer client did not receive notice of either the accident or the lawsuit from any source until December 2014, approximately six weeks before trial.
Following a $2.3 million judgment, the insurer client filed a complaint for declaratory judgment seeking a finding that Deerfield Construction materially breached the excess liability policy by not providing reasonable notice of the accident or the lawsuit, as required by the policy. The District Court found that the notice given to the insurer client was unreasonable as a matter of law. The District Court rejected Deerfield Construction’s argument that an insurance broker involved in the purchase of the excess liability policy, Arthur J. Gallagher, was the insurer client’s apparent agent for purposes of accepting notice. The District Court also rejected Deerfield Construction’s argument that the insurer client’s acts of requesting discovery, reviewing trial reports, and participating in settlement discussions raised equitable estoppel concerns.
Reprinted courtesy of
Jeremy S. Macklin, Traub Lieberman and
Mark F. Wolfe, Traub Lieberman
Mr. Macklin may be contacted at jmacklin@tlsslaw.com
Mr. Wolfe may be contacted at mwolfe@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Motion for Summary Judgment to Dispose of Hail Damage Claim Fails
November 25, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer's motion for summary judgment seeking to dismiss the insured's complaint requesting coverage for hail damage and a claim for bad faith. Rodriquez v. State Farm Lloyds, 2024 U.S. Dist. LEXIS 160007 (W.D. Tex. Sept. 5, 2024).
Mr. Rodriquez sought coverage under his homeowners policy after a hail and wind storm damaged his roof. After inspection, State Farm agreed that some minimal loss caused by hail was covered, but determined that the covered loss was less than the amount of the deductible. State Farm further determined that any hail damage to the roof was excluded by an endorsement, Exclusion of Cosmetic Loss to Metal Roof Coverings Caused by Hail. State Farm also determined that some damage was caused by previous faulty workmanship or wear and tear, both of which were excluded from coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
More Money Down Adds to U.S. First-Time Buyer Blues: Economy
August 20, 2014 —
Michelle Jamrisko and Alexis Leondis – BloombergThe challenges facing prospective buyers of the least expensive homes in the U.S. are getting harder to overcome.
Already beset by stagnant wages, growing student debt and competition from investors who are snapping up listings, those looking to purchase moderately priced houses must also provide more cash up front. The median down payment for the cheapest 25 percent of properties sold in 2013 was $9,480 compared with $6,037 in 2007, the last year of the previous economic expansion, according to data from 25 of the largest metro areas compiled by brokerage firm Redfin Corp.
The higher bar is a symptom of still-tight credit that is crowding out first-time buyers even as interest rates remain near historical lows. Younger adults, who would normally be making initial forays into real estate, are among those most affected, weakening the foundations of the housing market and limiting its contribution to economic growth.
Ms. Jamrisko may be contacted at mjamrisko@bloomberg.net; Ms. Leondis may be contacted at aleondis@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko and Alexis Leondis, Bloomberg
What Every Project Participant Needs to Know About Delay Claims
August 05, 2024 —
Andrew G. Vicknair - The Dispute ResolverA “delay” on a construction project is defined as the stretching out of the time for completion of certain key milestone scopes of work which can impact the completion date of an entire project, due to some circumstances or events that were not reasonably anticipated when the project began. 2 Construction Law ¶ 6.01 (Matthew Bender, 2024). While delays can be caused by any number of events, the most common are defective plans and specifications; design changes; severe weather and other, similar unforeseeable events; unforeseen or differing site conditions; unavailability of materials or labor; labor inefficiencies or stoppages; contractor negligence; and owner influences, including construction changes or outright interference by the owner or its agents. If the project schedule is not recovered following a delay, then the project schedule will likely be extended, resulting in an increase in the contractor’s costs of performance. A contractor that has experienced a delay on a project can take certain actions to pursue recovery of any damages the contractor may have incurred. However, to do so it is important to understand the different types of delays and the methods for establishing the delays.
I. Types of Delays
Delays may be categorized as (1) critical versus non-critical delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable delays. A critical delay is a delay that affects the project completion date and delays the entire project. In essence, a critical delay is one that will extend the critical path of a project. A non-critical delay is a delay that has no effect on the project’s critical path. Courts have recognized that delays to work not on the critical path will generally not delay the completion of a project. G.M. Shupe, Inc. v U.S., 5 Cl. Ct. 662, 728 (1984). Such a non-critical delay may affect the completion of certain activities, but does not affect the completion date of the entire project. In order for a delay to provide the basis for a claim for additional time or money, the delay must impact critical path activities on the project schedule.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com