It’s Getting Harder and Harder to be a Concrete Supplier in California
December 04, 2018 —
Garret Murai - California Construction Law BlogIn 2015, the California state legislature passed AB 219, which amended the state’s prevailing wage law to add Labor Code section 1720.9, which requires the payment of prevailing wages to “ready-mixed concrete” drivers on state and local public works projects.
Ready-mixed concrete suppliers filed suit in Allied Concrete and Supply Co. v. Baker (September 20, 2018) U.S. Court of Appeals for the Ninth Circuit, challenging the law on the ground that, because AB 219 singled out ready-mixed concrete drivers but not other drivers of materials on state and local public works projects, the law violated the Equal Protection Clause of the U.S. Constitution.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Washington’s Court of Appeals Protects Contracting Parties’ Rights to Define the Terms of their Indemnity Agreements
March 19, 2024 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIt has long been the law in Washington that contracting parties are free to draft contractual indemnity agreements to allocate risk arising from performance of the work, and Courts will generally enforce those agreements as written. This well-settled principle was recently reaffirmed in King County v. CPM Development Corp., dba ICON Materials[1] a decision from Division I of the Washington Court of Appeals, wherein one party to an indemnity agreement attempted to evade its contractual obligations by arguing that certain common law indemnity principles supersede the written terms. This appeal followed a multi-week jury trial from which the client and Ahlers Cressman and Sleight legal team, including Lindsay Watkins, Klien Hilliard, and Christina Granquist, obtained a seven-figure judgment in the client’s favor, including an award of all attorneys’ fees and costs.
ICON was the general contractor on a Vashon Island Highway Pavement project for King County. Part of the work on the project involved hauling away and disposing of ground milled asphalt (the “millings”) at King County-approved sites. ICON and D&R Excavating Inc., (“D&R”) executed a subcontract for D&R to perform that work. The subcontract incorporated the contract between ICON and King County, including the obligation to stockpile millings only at approved sites. D&R, however, did not obtain the requisite approvals from King County, and placed the millings at various sites on the Island, including locations that King County explicitly rejected.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
High Attendance Predicted for West Coast Casualty Seminar
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFWith the diverse speakers and topics planned for this year’s West Coast Casualty Seminar in Anaheim, California on May 15th and 16th, attendance should be high. In 2013, there were approximately 1600 attendees coming from across the country as well as the United Kingdom. The event planners recently added additional blocks of rooms, as the Disneyland Hotel has sold out 90% of the previously allotted room blocks. The planners urge attendees to book their rooms soon.
Seminar and panel topics have been announced. Thomas J. Halliwell, Esq. and Barry Vaughan, Esq. will be starting the seminar off with a discussion of “Recent California, Arizona and Nevada Court Decisions that Impact Construction Litigation and Defect Claims.” May 16th will feature a number of interesting break-out sessions including “Working Smarter with Technology” with speakers Brian Kahn, Esq., Paul R. Kiesel, Esq., Hon. Peter Lichtman (ret), Hon. Nancy Wieben Stock (ret), Peter S. Curry and Don MacGregor (Bert L. Howe & Associates, Inc.).
Download Invitation and Register for Seminar... Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects not Creating Problems for Bay Bridge
July 31, 2013 —
CDJ STAFFThere might have been a number of problems with San Francisco’s new Bay Bridge, but despite all that, the Contra-Costa Times says that the experts say that there is no reason for panic. And although the chair of the Senate Transportation Committee, Mark DeSaulnier, has been a critic of the bridge, he says that he is “convinced the old bridge is unsafe.”
Although DeSaulnier wants an independent review, construction of the bridge has been investigated by what the Times refers to as “dozens of internationally renowned bridge engineers and other experts.” According to the experts, the problems with the bridge fall in to three categories, ranging from the fixable, through the fixed, to those that were never actual problems.
Of the last category, the Oakland Tribune reported in 2005 that construction workers claimed they were told to “conceal shoddy welds to speed up construction,” but the Federal Highway Administration outside experts found no evidence of bad welds. In another case, bad welds were discovered at the factory where a span was being constructed. The process was changed and the bad welds repaired.
Caltrans has delayed the opening of the Bay Bridge to December 10. Earlier plans were to open the bridge in September.
Read the court decisionRead the full story...Reprinted courtesy of
Statutory Time Limits for Construction Defects in Massachusetts
November 27, 2013 —
CDJ STAFFConstruction defect claims are governed by a section of the Massachusetts laws and allow for three years after the work was completed, unless the defect is “inherently unknowable,” according to a post by John Shaffer on the web site of his firm, Marcus, Errico, Emmer & Brooks, a New England law firm that specializes in condominium law. Those “inherently unknowable” defects fall into the six-year statute of repose.
If, for example, a roof doesn’t show “significant water leakage” until after the end of the statutory period, “the association is out of luck and the responsible parties are off the hook,” writes Mr. Shaffer. “Even if the association could prove conclusively that the roof was improperly constructed and caused significant damage, the association’s claim will be barred.”
One problem condominium associations can face is that defects in the earliest phases of building can sometimes become apparent while the developer still controls the board. “While a developer in control of a board has the same fiduciary obligation as owner-elected trustees to protect the association’s interests, it is probably safe to assume that few developers will be inclined to sue themselves.” Here, Mr. Shaffer notes that owners can join together and either “hasten the transition to owner control of the association” or “convince them to correct the identified deficiencies.”
Mr. Shaffer notes that some questions concerning the statute of repose haven’t been answered by the Massachusetts courts. He does assure readers that “developers will no doubt argue that the statute of limitations has expired on defects because the association discovered or ‘should have discovered’ their existence more than three years before the lawsuit was started.” He advises condominium associations to calculate “their filing deadlines as conservatively as possible.”
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Remember to Timely Foreclose Lien Against Lien Transfer Bond
July 09, 2019 —
David Adelstein - Florida Construction Legal UpdatesWhen a construction lien is transferred to a lien transfer bond pursuant to Florida Statute s. 713.24, instead of foreclosing the lien against the real property, you are foreclosing the lien against the lien transfer bond. This is not a bad deal and, oftentimes, is probably ideal. Remember, however, just because a construction lien was transferred to a lien transfer bond (pre-lawsuit) does not mean you get more time to file your lien foreclosure lawsuit. A lawsuit must still be filed within one year (short of that period being specifically shortened under operation of the law).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Carbon Sequestration Can Combat Global Warming, Sometimes in Unexpected Ways
April 02, 2024 —
Michael S. McDonough, Robert A. James & Amanda G. Halter - Gravel2Gavel Construction & Real Estate Law BlogWhether by land, by sea or through human innovation, carbon sequestration is likely coming to (or already happening in) a destination near you. As our planet, overdosed on greenhouse gases, battles climate disasters, a logical solution is to simply stop pumping carbon dioxide into the air. Legislation worldwide is aimed at that target, but reducing output alone may not be enough. There are still billions of tons of extra CO2 already in the atmosphere—this crossroads is where sequestration comes into play.
Carbon sequestration is exactly what it sounds like—the storage of CO2. Once carbon is sucked out of the air, or in some cases pulled directly from industrial smokestacks, sequestration can be undertaken in a lot of different ways. Carbon storage happens naturally, when forests and oceans absorb and convert CO2 into organic matter, but carbon dioxide can also be artificially injected into deep underground rock formations (or wells), or in some cases technological approaches repurpose carbon into a resource like concrete, or as a catalyst in a closed-loop industrial system. However it’s accomplished, the point of sequestration is to stabilize carbon and ensure it doesn’t creep back into our atmosphere. Researchers, like those at the United Nations’ Intergovernmental Panel on Climate Change, now say that CO2 removal is vital to keeping global warming to 1.5 degrees Celsius (past that threshold, climate change could reach catastrophic levels). A 2023 University of Oxford study estimated that, currently, about two billion metric tons of carbon dioxide are being removed each year, primarily through land management (i.e., planting trees), and suggested that we need to double that amount to avoid dangerous global warming levels.
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Robert A. James, Pillsbury and
Amanda G. Halter, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. James may be contacted at rob.james@pillsburylaw.com
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Los Angeles Recovery Crews Begin to Mobilize as Wildfires Continue to Burn
January 21, 2025 —
Scott Blair, Aileen Cho, & C.J. Schexnayder - Engineering News-RecordMore than a week since wildfires broke out in the Los Angeles area stoked by hurricane-force Santa Ana winds, officials are hoping that a change in the weather will soon allow the long process of recovery to begin.
Reprinted courtesy of
Scott Blair, ENR,
Aileen Cho, ENR and
C.J. Schexnayder, ENR
Mr. Blair may be contacted at blairs@enr.com
Ms. Cho may be contacted at choa@enr.com
Mr. Schexnayder may be contacted at schexnayderc@enr.com