Christopher G. Hill - Construction Law MusingsThis past week, the blogosphere (if that’s even the word these days) has been abuzz about green building and the value that green can add to a project. Three items in particular (among many) got my attention.
The first of these was the fact that a new private sustainability rating system is ready for launch. The Institute for Sustainable Infrastructure (or ISI) is seeking public comment on its proposed envISIon. This new system (aptly dubbed Version 1.0) will go “live” in July for comment. Why mention this new system? First of all, ISI’s founding members are the American Society of Civil Engineers (ASCE), the American Public Works Association (APWA) and the American Council of Engineering Companies (ACEC). This trio gives the new program some fairly heavy weight backing. Second, while there are rating systems aside from the ever present LEED, none have taken hold in any real way to compete with LEED. I am curious to see if the envISIon system has any better luck. Finally, this shows that sustainable building is of interest to more than the USGBC and those of us that discuss LEED on a daily basis. I find this to be a great thing that could lead to more societal acceptance of sustainable practices as a standard practice rather than a goal.
Hopefully such efforts will offset the other two notes that caught my eye recently.
The first of these is the foreclosure of the Chapel Hill, North Carolina Greenbridge project. This project is well documented at my friend Doug Reiser’s (@douglasreiser) Builders Counsel blog so I won’t further discuss the details here. However, the question that Doug asks is a good one, i. e. were the “green” elements of the project to blame?
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Awarding Insurer Summary Judgment Before Discovery Completed Reversed
August 29, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeal reversed the trial court's awarding of summary judgment to the insurer because discovery was not completed. Sacramento v. Citizens Prop. Ins. Corp., 2022 Fla. App. LEXIS 4292 (Fla. Ct. App. June 22, 2022).
The insured filed a claim under the all-risk policy for water damage caused by Hurricane Irma. Citizens denied the claim based upon a policy exclusion. The insured filed suit on March 8, 2019.
On April 24, 2020, Citizens moved for summary judgment. A hearing was set for August 10, 2020. Citizens filed a notice for a deposition of a Mitigation Company representative scheduled to occur on December 1, 2020. On August 14, 2020, the insured filed an opposition to the summary judgment motion arguing that it would be premature to grant the motion because there were still pending depositions. The insured specifically requested that the trial court not enter summary judgment until the mitigation company's representative was deposed because he was a key witness who would be testifying regarding the cause of loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Allegations That COVID-19 Was Physically Present and Altered Property are Sufficient to Sustain COVID-19 Business Interruption Suit
May 24, 2021 —
Michael S. Levine & Joseph T. Niczky - Hunton Insurance Recovery BlogOn Wednesday, a federal judge in Texas denied Factory Mutual’s Rule 12(c) motion for judgment on the pleadings, finding that the plaintiffs adequately alleged that the presence of COVID-19 on their property caused covered physical loss or damage in the case of Cinemark Holdings, Inc. v. Factory Mutual Insurance Co., No. 4:21-CV-00011 (E.D. Tex. May 5, 2021). This is the third COVID-19-related business interruption decision from Judge Amos Mazzant since March, but the first in favor of a policyholder. Taken together, the three decisions have two key takeaways and provide a roadmap for policyholders in all jurisdictions.
First, the Cinemark decision recognizes that the alleged presence of COVID-19 viral particles that physically altered the policyholder’s property is sufficient under federal pleading standards and controlling state law. In its motion, FM relied on Judge Mazzant’s recent decision in Selery Fulfillment, Inc. v. Colony Insurance Co., No. 4:20-CV-853, 2021 WL 963742 (E.D. Tex. Mar. 15, 2021), which dismissed a lawsuit alleging that the policyholder’s losses were caused by government orders that closed its business, rather than from the actual presence of the virus on its property. The Court held that government orders alone do not constitute physical loss or damage, and declined to rule on whether the physical presence of the virus does. Judge Mazzant reached the same conclusion weeks later in Aggie Investments, L.L.C. v. Continental Casualty Co., No. 4:21-CV-0013, 2021 WL 1550479 (E.D. Tex. Apr. 20, 2021).
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joseph T. Niczky, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Niczky may be contacted at jniczky@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Does the Russia Ukraine War Lead to a Consideration in Your Construction Contracts?
April 04, 2022 —
David Adelstein - Florida Construction Legal UpdatesMaterial costs are still affecting the construction industry. Supply chain impacts too. The volatility started with COVID-19 (and, in certain cases, before with the imposition of tariffs) and has continued through present date.
But what about the war between Russia and Ukraine and the impact this has had or may have on the supply chain? I think the spillover from the war (with oil, gas, the energy sector, etc.), including the imposition of any sanctions, is not fully realized other than the concern exists in an economy that is already battling through material costs and supply chain disruptions.
How does this affect you?
It may not.
Or you may regularly enter into construction contracts in which you would be smart to address material costs and supply chain impacts. The reason being is that everything from a risk standpoint should begin with your construction contract. Not addressing an issue does not actually mitigate the risk. Confronting the issue does mitigate the risk because you are contractually addressing a concern and know where the other party stands relating to that concern so that business decisions can be made.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Subcontractor Not Estopped from Enforcing Lien Not Listed In Bankruptcy Petition
March 01, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPIn Stock Building Supply, Inc. v. Platte River Insurance Co.,[1] the Court of Appeals dealt with issues of judicial estoppel, bankruptcy, retroactive application of statutory lien amendments, and the full payment defense.
The owner, Madison Retail-Suwanee, LLC (“Madison”) hired Cannon/Estapa General Contractors, Inc. (“Cannon”) to be the general contractor for the construction of a shopping center (“the Project”). Cannon subcontracted with Stock Building Supply (“Stock”) to supply labor, materials, and services for the Project. Cannon failed to complete the project and Madison had yet to pay Cannon the full contract price. In 2007, Stock timely filed a lien on the Project and obtained a judgment against Cannon for the amount due under the subcontract. Platte River Insurance Company (“Platte”), the surety, issued a bond to discharge Stock’s lien. Consequently, Stock pursued an action against Platte to collect the judgment in the amount of $93,865.27.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Waive Not, Want Not: Waivers and Releases on California Construction Projects
February 18, 2015 —
Garret Murai – California Construction Law BlogCalifornia is one of a handful of states (12 to be exact) which have statutory mandated waiver and release forms for construction projects.
So here’s what you need to know before you sign one (or two, or three).
What are California’s statutory waiver and release forms?
California has four statutory waiver and release forms for construction projects.
Which form applies depends on two things: (1) whether it is for progress payments or final payment; and (2) whether it is provided before or after you have been paid.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Law Firm Fails to Survive Insurer's and Agent's Motions to Dismiss
May 08, 2023 —
Tred R. Eyerly - Insurance Law HawaiiInterpreting New Jersey law, the federal district court dismissed without prejudice the law firm's complaint against its insurer and agent. Law Office of Drew J. Bauman v. Hanover Ins. Co., 2023 U.S. Dist. LEXIS 31844 (D. N. J. Feb. 27, 2023).
The law firm had a professional liability policy issued by Hanover. The law firm was sued in the underlying case involving a real estate transaction. The law firm tendered the defense and indemnity of the underlying complaint, but coverage was denied. The law firm sued, contending Hanover breached the policy by refusing to abide by its obligations under the policy.
In the alternative, the law firm alleged that its agent, USI Insurance Services, LLC, was liable if the policy did not require Hanover to defend and indemnify in the underlying case. It was further alleged that USI was responsible for procuring coverage for the law firm and knew of its insurance needs. USI was negligent in securing a policy with inadequate coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Packard Condominiums Settled with Kosene & Kosene Residential
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFResidents of the Packard Condominiums in Indianapolis, Indiana “have settled a two-year-old lawsuit with developer Kosene & Kosene Residential,” according to the Indianapolis Business Journal. The Homeowners association stated that “the agreement would lead to repayment of a construction loan and avoidance of a special assessment on residents.”
The association claimed to have spent “$3 million on ‘renovation and remediation’ of subpar construction of the condo building,” reported the Indianapolis Business Journal.
The article also declared that at least 25 subcontractors participated in the mediation.
Read the court decisionRead the full story...Reprinted courtesy of