Notice of Claim Sufficient to Invoke Coverage
August 06, 2014 —
Tred R. Eyerly – Insurance Law HawaiiIndirect notice to the insurer was sufficient to trigger coverage for the additional insured under a liability policy. Spoleta Constr., LLC v. Aspen Ins. UK Ltd., 2014 N.Y. App. Div. LEXIS 5174 (N.Y. App. Div. July 11, 2014).
An employee of the subcontractor was injured at the construction project on October 20, 2008. The general contractor was named as an additional insured on the subcontractor's CGL policy with Aspen. Under the subcontract, the subcontractor also agreed to defend and indemnify the general contractor for all claims arising out of the subcontractor's work.
The general contractor did not receive notice of the accident until late December 2009 in a letter from the injured employee's attorney. On January 27, 2010, the general contractor's liability carrier sent a letter to the subcontractor giving notice of the employee's claim and requesting that the subcontractor put its carrier on notice. On February 9, 2010, the subcontractor sent to Aspen a claim form with the January 2010 letter attached.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Private Works: Preliminary Notice | Are You Using the Correct Form?
August 20, 2019 —
William L. Porter, Esq. - Porter Law GroupThe Private Works – Preliminary Notice form which contractors, subcontractors and suppliers had become accustomed to using for many years changed in 2004. Despite this change in law, many in the construction industry have still not started using the correct new form. Changes in the law, championed by the American Subcontractors’ Association, gave a significant new benefit to subcontractors and suppliers by giving the subcontractor or supplier some expectation of actually receiving notice of when a Notice of Completion or a Notice of Cessation has been recorded on many private works projects. The law also changed the language of the California Preliminary Notice that subcontractors and suppliers must use to protect their mechanics’ lien, bond claim and stop payment notice rights. If Owners do not send out the Notice of Completion as required by law they incur a diminishing of the protections afforded to them when they record a Notice of Completion or Notice of Cessation on many private works projects.
The revised law requires private project owners to notify all subcontractors and suppliers within 10 days after recording a Notice of Completion or Notice of Cessation that a Notice of Completion or a Notice of Cessation has actually been recorded. In order to receive such notice, the subcontractor or supplier must properly serve the new form of Preliminary Notice. If this properly occurs and the private project owner provides the required notice, then the subcontractor or supplier will have 30 days to record a Mechanics’ Lien. However, if an owner under such circumstances fails to properly notify a subcontractor or supplier within 10 days after recording a Notice of Completion or Notice of Cessation, then the Subcontractor or supplier will have 90 days to record a Mechanics’ Lien. The details of the law can be found in California Civil Code sections 8190, 8414 and 8416.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Esq., Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Why Builders Should Reconsider Arbitration Clauses in Construction Contracts
October 21, 2019 —
David M. McLain – Colorado Construction LitigationMy advice to home builders has long been to arbitrate construction defect claims instead of litigating them in front of juries. Based on my experience and watching others litigate claims, I have learned that home builders usually fare better in arbitration than in jury trials, both in terms of what they have to pay the homeowners or HOAs and also in what they recover from subcontractors and design professionals. Because of these dynamics, conventional wisdom has been that builders should arbitrate construction defect claims. For several reasons, I am now questioning whether the time is right to consider a third option.
First, plaintiffs’ attorneys dislike arbitration and will continue their attempts to do away with arbitration for construction defect claims. In 2018, the Colorado Legislature considered HB 18-1261 and HB 18-1262. While both bills were ultimately killed, they showed the plaintiffs’ attorneys disdain for arbitration, and serve as a warning that attempts to prevent arbitration legislatively will continue. If the legislature does away with the ability to arbitrate construction defect claims, and that is the only means of dispute resolution contained in a builder’s contracts, that builder may find itself in front of a jury.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
4 Breakthrough Panama Canal Engineering Innovations
October 11, 2017 —
Hobbes S. Sujith - Construction InformerThrough the rainforest of Central America stretches one of the seven wonders of the modern world. It’s the mother of all shortcuts – the Panama Canal. Over 300 million tons of cargo pass through its gates every year. Stretching through the heart of the Americans, this canal has changed the face of global trade. Ships traveling between the Atlantic and Pacific used to sail thousands of kilometers around Cape Horn. So in 1879 engineers planned to cut a channel through the Isthmus of Panama. And that, was going to become the history of Panama Canal engineering.
To understand how the Panama Canal can carry such a huge amount of cargo, we need to travel back in time to 17th century France. There, engineers building the Briare Canal (Canal de Briare) faced an big problem. How to make water flow up a hill?
Read the court decisionRead the full story...Reprinted courtesy of
Hobbes S. Sujith, Construction Informer
Did You Really Accept That Bid? – How Contractors Can Avoid Post-Acceptance Bid Disputes Over Contract Terms
July 28, 2016 —
David A. Harris & Steven M. Cvitanovic – Haight Brown & Bonesteel LLPWhen California general contractors submit bids to an owner, can they force their subcontractors to honor their bids? Can they recover damages if the subcontractor later refuses to do so?
While the general rule in California is that a general contractor who reasonably relies on a subcontractor’s bid may recover damages when the subcontractor reneges, the Court of Appeal for the Second Appellate District recently held that there is a substantial and important exception to the general rule.
In Flintco Pacific, Inc. v. TEC Management Consultants, Inc. (LASC No. YC067984), the Court of Appeal held that where a general contractor requires a subcontractor to enter into a “standard-form subcontract” which materially differs from the subcontractor’s bid, the general contractor has rejected the subcontractor’s bid and has instead issued a counteroffer. The subcontractor is thereafter free to walk, or accept the new terms. If the subcontractor walks, the general contractor may not seek to enforce the terms of the subcontract or seek reliance damages.
Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLP and
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Imposes New Disabled Access Obligations on Commercial Property Owners
October 07, 2016 —
Garret Murai – California Construction Law BlogThe following article was written by my colleague
David Goldman on the new ADA accessibility legislation which was signed into law this past month by Governor Brown.
Since July 1, 2013, California Civil Code section 1938 has required commercial property owners to disclose in every commercial lease whether the property being leased has been inspected by a Certified Access Specialist (“CASp”). A CASp is an individual certified by the State of California as qualified and knowledgeable of construction-related access to public accommodations by persons with disabilities. In addition to disclosing whether or not the property being leased has been CASp inspected, if a CASp inspection has occurred, the commercial lessor must disclose in the lease whether the premises has or has not met all the applicable construction-related accessibility standards established by law. These lease requirements, along with other disability access obligations, were discussed in an
earlier article written in 2012.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
How to Build a Water-Smart City
August 23, 2021 —
Chris Malloy - BloombergCities across time have stretched to secure water. The Romans built aqueducts, the Mayans constructed underground storage chambers, and Hohokam farmers dug more than 500 miles of canals in what is now the U.S. Southwest.
Today’s cities use portfolios of technologies to conserve supply — everything from 60-story dams and chemicals to centrifugal pumps and special toilets. And yet, the cities of tomorrow will have to do more.
A recent United Nations report on drought says climate change is increasing the frequency, severity and duration of droughts, which contribute to food insecurity, poverty and inequality. The report also asserts that “drought has been the single longest-term physical trigger of political change in 5,000 years of recorded human history.” It calls for urgent action and a transformation in governance to manage modern drought risk more effectively.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Malloy, Bloomberg
Reminder: Quantum Meruit and Breach of Construction Contract Don’t Mix
July 30, 2015 —
Christopher G. Hill – Construction Law MusingsConstruction contracts (preferably written ones) are near and dear to my heart here at Construction Law Musings. In a world where the contract is king, having a written construction agreement is a key component of any properly run construction project. However, even with the best construction contract there are claims (Murphy was an optimist after all).
When making these claims, we construction lawyers tend to plead both the breach of contract and quantum meruit (or in non lawyer speak- unjust enrichment) when drafting a complaint in a construction dispute. A recent case out of the Western District of Virginia federal district court reminds us all that these two counts must be plead alternatively because they simply cannot exist in a lawsuit from beginning to end.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com