Quick Note: Not In Contract With The Owner? Serve A Notice To Owner.
August 13, 2019 —
David Adelstein - Florida Construction Legal UpdatesA subcontractor or supplier not in direct contract with an owner must serve a Notice to Owner within 45 days of initial furnishing to preserve construction lien rights. Of course, the notice of commencement should be reviewed to determine whether the subcontractor or supplier has construction lien or payment bond rights so that it knows how to best proceed in the event of nonpayment. Serving a Notice to Owner should be done as a matter of course — a standard business operation; no exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?
January 27, 2020 —
Ted R. Gropman & Christine Z. Fan - ConsensusDocsConstruction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays to a project’s completion date. Depending on the nature of the delay and the jurisdiction where the project is located, the contractual prohibition against delay damages may well be enforceable. This article will explore whether an enforceable no-damage-for-delay clause is also a bar to recovery of “acceleration” damages, i.e., the costs incurred by the contractor in its attempt to overcome delays to the project’s completion date.
Courts are split as to whether damages for a contractor’s “acceleration” efforts are distinguishable from “delay” damages such that they may be recovered under an enforceable no-damage-for-delay clause. See, e.g., Siefford v. Hous. Auth. of Humboldt, 223 N.W.2d 816 (Neb. 1974) (disallowing the recovery of acceleration damages under a no-damage-for-delay clause); but see Watson Elec. Constr. Co. v. Winston-Salem, 109 N.C. App. 194 (1993) (allowing the recovery of acceleration damages despite a no-damage-for-delay clause). The scope and effect of a no-damage-for-delay clause depend on the specific laws of the jurisdiction and the factual circumstances involved.
There are a few ways for a contractor to circumvent an enforceable no-damage-for-delay clause to recover acceleration damages. First, the contractor may invoke one of the state’s enumerated exceptions to the enforceability of the clause. It is helpful to keep in mind that most jurisdictions strictly construe a no-damage-for-delay clause to limit its application. This means that, regardless of delay or acceleration, courts will nonetheless permit the contractor to recover damages if the delay is, for example, of a kind not contemplated by the parties, due to an unreasonable delay, or a result of the owner’s fraud, bad faith, gross negligence, active interference or abandonment of the contract. See Tricon Kent Co. v. Lafarge N. Am., Inc., 186 P.3d 155, 160 (Colo. App. 2008); United States Steel Corp. v. Mo. P. R. Co., 668 F.2d 435, 438 (8th Cir. 1982); Peter Kiewit Sons’ Co. v. Iowa S. Utils. Co., 355 F. Supp. 376, 396 (S.D. Iowa 1973).
Reprinted courtesy of
Ted R. Gropman, Pepper Hamilton LLP and Christine Z. Fan, Pepper Hamilton LLP
Mr. Gropman may be contacted at gropmant@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Provides Independant Counsel When Conflict Arises Between Insurer and Insured
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Nevada Supreme Court, responding to certified questions, determined that an insurer must provide independent counsel for its insured when a conflict of interest arises between the insurer and insured. State Farm Mut. Auto. Ins. Co. v. Hansen, 2015 Nev. LEXIS 86 (Nev. Sept. 24, 2015).
The insured struck the vehicle of another driver, Hansen. Hansen sued the insured alleging both negligence and various intentional torts. State Farm agreed to defend under a reservation of rights. The reservation of rights letter reserved the right to deny coverage for liabiltiy resulting from intentional acts and punitive damages.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (08/15/23) – Manufacturing Soars with CHIPS Act, New Threats to U.S. Infrastructure and AI Innovation for One Company
September 25, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, wildfires wreak havoc in Maui, JLL unveils an AI specifically for commercial real estate, the lasting effects of the CHIPS ACT, and more!
- So far, 11,000 JLL employees have used the company’s new proprietary large language model that has generative AI capabilities specifically for the commercial real estate industry. (Lindsey Wilkinson, Construction Dive)
- Since the enactment of the CHIPS Act, manufacturing activity has boomed with a nearly 80% increase from June 2022. (Sebastian Obando and Julia Himmel, Construction Dive)
- Construction-tech-focused investors among others have poured $35 million into an Israeli startup that develops leakage detection technology using artificial intelligence to prevent water damage. (Sharon Wrobel, Times of Israel)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Subcontractor Not Liable for Defending Contractor in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe California Court of Appeals has ruled on January 9, 2012 in Hensel Phelps Construction Company v. Urata & Sons Cement, upholding the judgment of the lower court.
Hensel Phelps was the general contractor for a high-rise in Sacramento. They were sued by the owners of the building after problems were discovered in the concrete slabs of the building’s parking garage. Instead of welded steel wire mesh, the slabs had been constructed with fiber mesh. Hensel Phelps filed a cross-complaint against Urata Cement, the subcontractor that had performed the cement work. Urata refused to defend Hensel Phelps. The owners’ case was subsequently dismissed due to the statute of limitations.
Although the original case was over, Hensel Phelps continued in their claims against Urata. “Urata argued that a handwritten interlineation required Hensel Phelps to prove Urata was at fault for the injury alleged in the building owners’ complaint before Urata was obliged to defend Hensel Phelps in that action.”
The lower court concluded that Urata would have been obligated to defend Hensel Phelps if the owners’ lawsuit had alleged that the damage was due to the subcontractor’s work or if evidence at trial established this. The lower court found neither of these true. Instead, the use of the fiber mesh was a design issue and “that decision was outside the scope of the subcontractor’s work.”
During the trial, Hensel Phelps conceded that Urata was not at fault. The appeals court could find no reading of the contract that would cause Urata to be obligated to defend Hensel Phelps, calling Hensel Phelps’s reading of the contact as “grammatically infeasible.”
Judges Nicholson, Raye, and Butz upheld the decision of the lower court and awarded costs on appeal to Urata.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
SIG Earnings Advance 21% as U.K. Construction Strengthens
August 13, 2014 —
Benjamin Katz – BloombergSIG Plc (SHI) earnings surged 21 percent in the first half as the distributor of building products benefited from a strengthening recovery in the U.K. housing market as well as procurement savings.
Underlying operating profit rose to 47.8 million pounds ($80 million) from 39.6 million pounds a year earlier, the Sheffield, England-based company said in a statement today. Sales in the U.K. and Ireland from continuing operations climbed 14 percent to 650 million pounds, offsetting flat revenue in continental Europe.
“Trading conditions in the U.K. have continued to gather momentum, led by the revival in the housing market,” Chief Executive Officer Stuart Mitchell said in the statement. “The group’s first-half performance and progress on its strategic initiatives provide a strong base on which to achieve its full-year expectations.”
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin Katz, BloombergMr. Katz may be contacted at
bkatz38@bloomberg.net
Collapse Claim Fails Due To Defectively Designed Roof and Deck
May 28, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's claim for collapse of his roof and deck failed due to defective design and other exclusions under the policy. Dudar v. State Farm & Cas. Co., 2024 U.S. Dist. LEXIS 52706 (N.D. Ga. Feb. 6, 2024).
The insured submitted a claim to State Farm for damage to the roof ("Roof Claim"). State Farm's adjuster placed a ladder on the deck to access the roof and a portion of the deck collapsed. The insured then reported a claim to State Farm for damage to the deck ("Deck Claim"). The claims were denied and suit was filed.
The roof had leaked on several occasions prior to submission of the Roof Claim. On February 25, 2022, the insured discovered that a branch had cut a hole in the tarp, causing water to leak into the home. The insured performed repairs on the roof. On March 8, 2022, a storm caused more water to seep through the tarp into the ceilings and walls. Thereafter, the Roof Claim was submitted.
The damage from the leaking roof and the deck collapse were caused by rotting. The rotting, in turn, was caused by a combination of defective building design and resulting water damage from rain and storms over the years. The roof and deck were constructed to provide mutual support to one another. The roof did not contain an adequate slope, which caused water to seep down into the walls and flooring rather than to flow downward and away from the property. Over time, penetrating water caused portions of the roof, the floor, and the supporting wall between the roof and deck to rot.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Connecticut’s New False Claims Act Increases Risk to Public Construction Participants
April 02, 2024 —
Fred Hedberg & William Stoll - Construction Law ZoneAfter several decades, Governor Ned Lamont signed a bill into law, effective July 1, 2023, An Act Concerning Liability for False and Fraudulent Claims, Public Act No. 23-129, eliminating language that previously limited enforcement of Connecticut’s False Claims Act to claims relating to a state-administered health or human services program. The revisions dramatically expanded potential liability under the False Claims Act, allowing both private citizens and the Attorney General to bring actions under the Act in any context, including the construction industry. Consequently, contractors, subcontractors, suppliers and design professionals on public construction projects in Connecticut must be familiar with this newly enacted law and take steps to reduce the risks of doing business on such projects.
Reprinted courtesy of
Fred Hedberg, Robinson & Cole LLP and
William Stoll, Robinson & Cole LLP
Mr. Hedberg may be contacted at fhedberg@rc.com
Mr. Stoll may be contacted at wstoll@rc.com
Read the court decisionRead the full story...Reprinted courtesy of