Suing the Lowest Bidder on Public Construction Projects
September 17, 2015 —
Craig Martin – Construction Contractor AdvisorThe California Court of Appeals has allowed the second lowest bidders on public construction projects to sue the lowest bidder where it appears that the lowest bidder was only the lowest because it paid its employees less than the established prevailing wage. This is a novel theory for recovery, but may provide for an opportunity to challenge improperly low bids.
Background
Between 2009 and 2012, American Asphalt outbid two asphalt companies on 23 public works projects, totaling nearly $15 million. The two asphalt companies sued American Asphalt alleging that they were the second lowest bidder all 23 construction projects and they would have been the lowest had American Asphalt paid its employees the required prevailing wage. Importantly, the municipality awarding the contracts was not sued by the second lowest bidders. Instead, the second lowest bidders alleged that American Asphalt intentionally interfered with a business expectancy and sought damages from American Asphalt, specifically the profit that they lost by not performing these contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
The Importance of a Notice of Completion to Contractors, Subcontractors and Suppliers
August 12, 2024 —
William L. Porter - Porter Law GroupThe recording of a valid “Notice of Completion” with the County Recorder is an event of significance to owners, contractors, subcontractors and suppliers alike. The recording of a Notice of Completion is one of several methods used to trigger the time period for the recording of mechanics liens and service of stop payment notices. Although the recording of a Notice of Completion is not absolutely required on any given project, all those working in the construction industry should understand its significance.
When a valid Notice of Completion has not been recorded in relation to a construction project, a contractor, subcontractor, or supplier might from ninety to one hundred fifty days after completion of the project to record a mechanics lien or serve a stop payment notice to secure payment for their services on the project, depending on the facts. However, if a valid Notice of Completion is recorded, then the deadline under most circumstances accelerates and subcontractors and suppliers must record a mechanics lien or serve a stop payment notice within only thirty days thereafter. Under the same circumstances, a prime contractor has only sixty days after the recording of a valid Notice of Completion to record a mechanics’ lien. Failure to meet these deadlines often results in loss of the right to a mechanics lien or stop payment notice. There are limited exceptions to these general deadlines, depending on the facts. If you believe you may have missed an important deadline to seek collection of a construction debt, you should consult with a construction attorney immediately to secure your avenues of collection, including the mechanics lien and stop payment notice remedies, if still available.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
A Closer Look at an HOA Board Member’s Duty to Homeowners
August 27, 2013 —
Derek Lindenschmidt — Higgings, Hopkins, McLain & Roswell, LLCWhenever a homeowner association (HOA) starts thinking in terms of a construction defect lawsuit against its developer and/or builder, its board members will inevitably be confronted with the purported risk and liability to their homeowners if they do not pursue the alleged defects and deficiencies brought to their attention.
Not surprisingly, the board members are on occasion led to believe that pursuing such claims is synonymous with acting in the homeowners’ “best interests.” Further—and unfortunately—board members often feel as though they will breach their obligation to the homeowners if theydon’t agree to proceed with such claims.
Nevertheless, how well do we really know what the board members’ duty actually consists of, when it applies, and what potential liability exists for a board member’s breach of same? The answers might surprise you.
Read the court decisionRead the full story...Reprinted courtesy of
Derek LindenschmidtDerek Lindenschmidt can be contacted at
lindenschmidt@hhmrlaw.com
How I Prevailed on a Remote Jury Trial
March 04, 2024 —
Samuel Yu - Kahana FeldAre you crazy? That is what I asked my client when he asked me to conduct a jury trial remotely. At the time, I did not even know if it was feasible. While I figured that most courtrooms had remote capabilities, I was not sure whether anyone was crazy enough to do a jury trial remotely and whether a courtroom would accommodate it. Would I be able to truly connect with the jurors? Would the jurors hold it against me that I am appearing remotely while they have to be there in person? I told my client that this was a terrible idea but that I would at least see if it was an option.
At the Final Status Conference, the Court confirmed that it could accommodate a remote appearance for both the party and the party’s counsel and gave its permission to do so. It was also clear that I would be the only attorney exercising this option, and the judge remarked that this would be a first for him. Appearing remotely while other attorneys appear in person is not something I would normally consider. However, this case presented a unique set of circumstances.
Read the court decisionRead the full story...Reprinted courtesy of
Samuel Yu, Kahana FeldMs. Yu may be contacted at
syu@kahanafeld.com
Bertha – The Tunnel is Finished, but Her Legacy Continues
September 28, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCThe Tunnel Boring Machine (“TBM”) known as “Bertha,” built by Hitachi Zosen Corp in Osaka, Japan, was the world’s largest TBM at 57.5 ft. in diameter. The TBM was built to drill the Seattle SR 99 Viaduct replacement tunnel. Seattle Tunnel Partners (“STP”) has a contract with the Washington State Department of Transportation (WSDOT) to dig the two-mile tunnel which is now complete.
In December of 2013, tunneling was stopped ostensibly because a 119 ft.-long, eight-inch diameter steel well casing halted the TBM. See 2/15 Blog “Bertha is Stuck and She Remains Mired in Controversy.” Reports are that WSDOT installed the pipe in 2002 to measure groundwater levels and the pipe was allegedly mentioned in the reference material provided to bidders. STP had assumed that the pipe had been removed until the steel casing got stuck in Bertha’s cutting teeth, halting progress. See 1/30/14 Blog “Big Bertha Stuck: Differing Site Condition Principles Revisited.” STP had a design-build contract with WSDOT. The contract contains a Differing Site Conditions (“DSC”) clause pursuant to which if the contractor can prove that the eight-inch pipe was an unforeseen condition (not disclosed in the contract documents), and that the unforeseen condition caused the TBM’s failure, STP is entitled to an equitable adjustment of its contract.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Philadelphia Enacts Commercial Property Assessed Clean Energy (C-PACE) Program
October 21, 2019 —
Timothy Davis & Willliam Johnston - White and Williams LLPOn August 14, 2019, Mayor Jim Kenney signed a bill authorizing, through C-PACE loans, the financing of clean energy, alternative energy and water conservation projects for eligible commercial properties in Philadelphia. Philadelphia City Council unanimously voted to approve the C-PACE program on June 20, 2019. The program will be administered by the Philadelphia Energy Authority. Third-party capital providers (not the Philadelphia Energy Authority) will originate C-PACE financings for qualified projects.
C-PACE “assessments” will encumber the applicable property in a first lien position akin to a real estate tax. Documentation among the property owner, the City of Philadelphia, and the third party capital provider (identified in the ordinance as the “financial institution”) will provide, among other things, that the assessments will be payable and fully amortize over the term of the financing (i.e., 30 years) and will not be accelerated during its term. Importantly, before a C-PACE financing can be originated and the underlying property assessed, notice of the property owner’s desire to secure C-PACE financing under the program must be provided to the holder of a mortgage on the subject property and the holder of the mortgage must provide the property owner and the City of Philadelphia with its written consent. Without the mortgage lender’s consent, the C-PACE financing cannot be consummated.
Reprinted courtesy of
Timothy Davis, White and Williams LLP and
William Johnston, White and Williams LLP
Mr. Davis may be contacted at davist@whiteandwilliams.com
Mr. Johnston may be contacted at johnstonw@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Assembly Sends Construction Defect Bill to Senate
June 06, 2011 —
CDJ STAFFIn a 26 to 16 vote, the Nevada Assembly has passed Assembly Bill 401, which extends the time limit for legal action over home construction defects. According to the Las Vegas Sun, Assembly member Marcus Conklin, Democrat of Las Vegas, said the bill was about “keeping the consumer whole.” However, Ira Hansen, Republican of Sparks, told the sun that suits are happening before contractors can make repairs. The bill would allow attorney fees even if repairs are made.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
DOE Abruptly Cancels $13B Cleanup Award to BWXT-Fluor Team
February 01, 2021 —
Mary B. Powers & Debra K. Rubin - Engineering News-RecordThe U.S. Energy Dept. has cancelled a $13-billion, 10-year contract awarded just a few months ago to a team led by BWXT Technical Services and Fluor Federal Services to manage millions of gallons of radioactive waste stored underground at its Hanford, Wash., former weapons site—confirming plans for a major scope expansion and lengthy reprocurement but sharing few details.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of