COVID-19 Damages and Time Recovery: Contract Checklist and Analysis
April 27, 2020 —
Patrick J. Greene, Jr. - Peckar & AbramsonThis Alert explores the contract provisions and related rights that are likely to govern time and compensation adjustments for COVID-19 impacts. As parties begin analyzing such rights, this is intended to serve as a useful guide and checklist.
Analysis of relevant contract provisions should start with careful consideration of the specific impacts that have been experienced and the causes of those impacts. The nature of the impact (delay, extra work, disruption, etc.) and the causes of such impacts (owner direction, government order, etc.) will generally govern the analysis and resulting course of action. Listing or creating a matrix of impacts and their causes may be an effective working tool.
Essentially, there are five primary impacts that will likely require critical analysis under the relevant contract provisions, and notably, more than one impact may be present:
a) complete or partial suspension of work,
b) additional work or requirements,
c) added cost,
d) delay, and
e) disruption.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick J. Greene, Jr., Peckar & AbramsonMr. Greene may be contacted at
pgreene@pecklaw.com
Paycheck Protection Flexibility Act Of 2020: What You Need to Know
July 20, 2020 —
Amy R. Patton & Rana Ayazi - Payne & FearsOn June 5, 2020, President Trump signed into legislation the bipartisan bill titled the Paycheck Protection Program Flexibility Act of 2020 (PPPFA). The PPPFA modifies the Paycheck Protection Program, which was first introduced under the Coronavirus Aid, Relief, and Economic Security Act (CARES Act). The modifications provide borrowers more control over the use of funds and make it easier to obtain forgiveness. The following is a summary of the key changes.
1. Extended Maturity Date From 2 Years to 5 Years
Under the CARES Act, the minimum maturity date for loan amounts after the forgiveness period was not defined. The Small Business Administration (SBA) then released an Interim Final Rule clarifying that the minimum maturity date was two years. The PPPFA has extended the term to five years: “The covered loan shall have a minimum maturity of 5 years and a maximum maturity of 10 years from the date on which the borrower applies for loan forgiveness under that section.”
2. Extension of Covered Period From Eight Weeks to a Maximum of 24 Weeks
Under the CARES Act, the covered period of the loan (i.e., the time period in which you may spend the loan funds) was February 15, 2020 to June 30, 2020, an eight-week period. The PPPFA extended the covered period to 24 weeks from the origination date of the loan, or December 31, 2020, whichever is earlier.
Reprinted courtesy of
Amy R. Patton, Payne & Fears and
Rana Ayazi, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Recommendations for Property Owners After A Hurricane: Submit a Claim
October 04, 2021 —
Kelly A. Johnson, Stephanie A. Giagnorio & Gregory D. Podolak - Saxe Doernberger & Vita, P.C. If you suffered damage as a result of a hurricane, you should submit a claim under any insurance policy you have that might apply. This includes:
- Flood insurance
- Homeowner’s insurance
- Renter’s insurance
- Condo insurance
- Auto insurance
Steps for Handling Your Hurricane Insurance Claim
- Submit Your Claim. As soon as possible, provide a written notice of claim to your insurer according to the notice provision of your policy. Keep a copy for your records. If you don’t have a copy of your policy, call the insurance company, ask them how to submit your claim, and request a copy of your policy.
Reprinted courtesy of
Kelly A. Johnson, Saxe Doernberger & Vita,
Stephanie A. Giagnorio, Saxe Doernberger & Vita and
Gregory D. Podolak, Saxe Doernberger & Vita
Ms. Johnson may be contacted at KJohnson@sdvlaw.com
Ms. Giagnorio may be contacted at SGiagnorio@sdvlaw.com
Mr. Podolak may be contacted at GPodolak@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
NJ Condo Construction Defect Case Dismissed over Statute of Limitations
June 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to an article by Matthew D. Stockwell of the firm Pillsbury Winthrop Shaw Pittman, LLP published in Lexology, “a trial court in Bergen County, New Jersey dismissed a condominium association's construction defect claims against several construction entities for failure to comply with the applicable statute of limitations.”
Stockwell stated that the “aftermath will be interesting to follow, because the trial court stripped away some of the protection that New Jersey's discovery rule affords to property owners who become aware of latent defects well after a project is substantially completed.”
Read the court decisionRead the full story...Reprinted courtesy of
Mortgage Interest Rates Increase on Newly Built Homes
April 30, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the National Association of Home Builders’ (NAHB) Eye on Housing, while the Federal Housing Financing Agency (FHFA) reported a decrease in mortgage interest rates for existing homes, there was an increase in mortgage rates on newly built homes: “The average contract interest rate on conventional mortgages used to purchase newly built homes actually increased in March, from 3.91 to 4.21 percent, reversing an anomalous drop to under 4 percent that occurred in February.”
“The average price and loan size on conventional mortgages used to purchase newly built homes also reversed previous month declines in March,” reported Eye on Housing. “The average price increased 5.4 percent to $427,200—the second highest number on record.”
Read the court decisionRead the full story...Reprinted courtesy of
Defense Victory in Breach of Fiduciary Action
February 26, 2015 —
Beverley BevenFlorez-CDJ STAFFEarlier this month, Scott Calkins and Anthony Gaeta of Collinsworth, Specht, Calkins & Giampaoli, LLP obtained a defense verdict in a breach of fiduciary duty action involving a high-rise condominium in downtown San Diego, California. The Association asked for excess of over $3 million, however, the jury returned with a 10-2 defense verdict in favor of K. Hovnanian.
Cortez Blu Community Association, Inc. v. K. Hovnanian at Cortez Hill, LLC, et al. initially involved construction defect claims against the developer, K. Hovnanian, and the general contractor, Turner Construction, as well as a claim of breach of fiduciary duty. However, the construction defect claims settled prior to trial leaving only the breach of fiduciary claim.
“While it is now becoming ever more common for attorneys representing homeowners associations to allege a breach of fiduciary duty by the developer, there has been little actual litigation of the issues surrounding those claims which test the viability of the allegations or the defenses to them,” defense attorney Anthony Gaeta stated. “A breach of a fiduciary duty by a developer, which is demonstrated to damage the viability of an HOA either to perform regularly scheduled maintenance, or replace building components from its reserves, has the potential in economic terms to surpass the damages from purported construction defects.
The Plaintiff argued that K. Hovnanian breached its fiduciary duty to the Association by failing to set adequate reserves within the initial Department of Real Estate budget (“DRE”) for painting, caulking, and power washing the exterior of the building, referencing Raven’s Cove Townhomes, Inc. v. Knuppe Development Co., Inc. (1981) 114 Cal. App. 3d 783. In response, K. Hovnanian stated that in part, the initial reserves as set forth in the DRE budget were adequate, good faith estimates and, therefore, there was no liability for breach of fiduciary duty.
“Our case was exclusively concerned with the duties of the developer when forming the initial HOA, preliminary budgets, and reserves,” Gaeta said. “We litigated the duties and responsibilities of the initial board and whether a developer may rely on reports prepared by third-parties during the formation of a common interest development. The jury found our client’s actions and reliance on third-parties was reasonable and, thus, no breach of fiduciary duty occurred.”
Collinsworth, Specht, Calkins & Giampaoli is a general civil litigation firm representing clients throughout California and Arizona. You may learn more about the firm at www.cslawoffices.com
Read the court decisionRead the full story...Reprinted courtesy of
Denial of Motion to Dissolve Lis Pendens Does Not Automatically Create Basis for Certiorari Relief
November 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate decision out of Florida’s Sixth District Court of Appeal holds that a trial court’s denial of motion to dissolve a lis pendens does NOT automatically give a basis for a petition for a writ of certiorari. Generalized allegations of “irreparable harm” to support the basis for the petition for writ of certiorari are insufficient. Rather, the party moving for the petition MUST clearly demonstrate the irreparable harm; otherwise, the petition for writ of certiorari will fail.
A lis pendens has legal significance. It is a recorded document that notifies the world that there is a pending lawsuit dealing with the real property at issue. This is important because who wants to buy a piece of property that is subject to litigation – that would be a risky transaction!
In CPPB, LLC v. Taurus Apopka City Center, LLC, 48 Fla.L.Weekly D1837a (Fla. 6th DCA 2023), a dispute arose as to a real estate transaction. The owner sold a parcel to a buyer. The owner also owned three adjacent parcels. As part of the transaction, the buyer agreed to perform certain improvements to all of the parcels including those adjacent parcels owned by the owner. The owner deposited funds in escrow for purposes of its share of the improvements. A payment dispute arose regarding the improvements and the buyer sued the seller. The seller filed a counterclaim to rescind the transaction along with a recorded lis pendens on the parcel purchased by the buyer. The buyer moved to dissolve the lis pendens which the trial court denied. This prompted the appeal – a petition for a write of certiorari based on the trial court’s denial of the motion to dissolve the lis pendens.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Think Before you Execute that Release – the Language in the Release Matters!
June 17, 2024 —
David Adelstein - Florida Construction Legal UpdatesIf you execute a release in exchange for payment or other consideration, remember the language in the release means something. THE RELEASE LANGUAGE MATTERS! And the meaning in the release may be way more than you intended so please make sure you truly digest and consider release language before executing.
This sentiment could not be truer than in the 2009 decision Bell BCI Company v. United States, 570 F.3d 1337 (Fed. Cir. 2009). In this case, a contractor entered into a modification (change order) with the government. The modification included the following language:
increase the contract amount by $2,296,963 … as full and equitable adjustment for the remaining direct and indirect costs of the Floor 4 Fit-out (EWO 240–R1) and full and equitable adjustment for all delays resulting from any and all Government changes transmitted to the Contractor on or before August 31, 2000.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com