Harmon Towers Duty to Defend Question Must Wait, Says Court
March 01, 2012 —
CDJ STAFFThe Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
How Will Today’s Pandemic Impact Tomorrow’s Construction Contracts?
October 26, 2020 —
Levi W. Barrett, Nathan A. Cohen & Mark A. Snyder - Peckar & AbramsonThe emergence of COVID-19 has created a new set of challenges in the already complex world of negotiating construction contracts. In the pre-COVID-19 era, general contractors, construction managers and those negotiating on their behalf, needed to balance a variety of fairly well-established legal risks and exposures and commercial realities with the need to maintain a positive relationship with their counterparty. While many are rightfully concerned with addressing the impacts of COVID-19 to their on-going projects, those negotiating new contracts now are undoubtedly cognizant that they are negotiating in the midst of an unpredictable future that is tipping the historical negotiating balance. The following presents some crucial areas to focus on when negotiating and drafting your contracts in this new era.
Contract Terms Through the COVID-19 Lens
Contractors should examine proposed new contracts carefully to identify rights that afford COVID-19 protections and identify contractual obligations that create COVID-19 commercial risks.
Specific attention should be paid to those sections relating to force majeure/excusable delay, emergencies, changes (including changes in law), contingency, suspension and termination, site investigation as well as all representations and warranties. The paramount concern in examining these provisions is to ensure that they not only entitle the contractor to relief for those unknown events, emergencies and changes, but that they also contain sufficient entitlement for the contractor to obtain both time extensions and financial compensation for unknown impacts of a known event – the COVID-19 pandemic.
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Nathan A. Cohen, Peckar & Abramson, P.C.and
Mark A. Snyder, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Cohen may be contacted at ncohen@pecklaw.com
Mr. Snyder may be contacted at msnyder@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
CDJ’s Year-End Review: The Top 10 CD Topics of 2014
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFConstruction Defect Journal’s year-end review presents the top ten most popular topics featured in the journal in 2014. Some of the topics involved analysis of important construction defect cases, while others covered current events such as proposed state legislation. Most issues were heavily discussed on CDJ as well as in board rooms and during teleconferences. We hope you enjoy the look-back at 2014 interspersed throughout the issue, and we wish you and yours a prosperous 2015!
CDJ’s #1 Topic of the Year: Indalex Inc. v. National Union Fire Ins. Co. of Pittsburgh, PA, 2013 Pa. Super 311 (Dec. 3, 2013)
According to Darrin J. McMullen of Anderson Kill, “[t]he Indalex decision reverses a nearly decade-long trend of Pennsylvania decisions narrowing the scope of insurance coverage for construction and defect-related claims under commercial general liability insurance policies. Equally important, the Indalex ruling dealt a blow to the insurance industry’s continual efforts to win overbroad expansion of the rulings in Kvaerner Metals Div. of Kvaerner U.S., Inc. v. Commercial Union Ins. Co., Millers Capital Ins. Co. v. Gambone Bros. Dev. Co., and Erie Ins. Exchange v. Abbott Furnace Co., which found that claims of faulty workmanship in some circumstances may not constitute coverage-triggering ‘occurrences.’”
Read the court decisionRead the full story...Reprinted courtesy of
How Does Your Construction Contract Treat Float
November 08, 2017 —
David Adelstein - Florida Construction Legal UpdatesAlthough there are different types of construction schedule float and more technical definitions, the definition that makes sense to me is that float is the amount of time a particular activity can be delayed without that activity delaying the project’s completion date (substantial completion date). In looking at a construction schedule, this determination is made from looking at the difference between the early start date for an activity and the late start date for that activity or the difference between the early finish date for that activity and the late finish date for that activity in your CPM schedule (which should be the same amount of time). This is often referred to as “total float” and is the float that I usually focus on since it may pertain to a delay to the substantial completion date of the project and can trigger either the assessment of liquidated damages and/or the contractor’s extended general conditions, whatever the case may be.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Did New York Zero Tolerance Campaign Improve Jobsite Safety?
December 13, 2021 —
Neil Flynn - Construction ExecutiveConstruction work is one of the most dangerous jobs in America, accounting for 19% of all workplace deaths in 2019. In New York City, that number is almost 50% higher, with construction accidents accounting for a quarter of all workplace deaths. One of the most positive developments in this area, despite the presence of COVID-19, has been the recent implementation of the “Zero Tolerance” campaign by the New York City’s Department of Buildings.
The goal of the DOB’s latest construction safety campaign was to reduce the number of building site injuries and fatalities by implementing a zero-tolerance standard. While it is too premature to measure the program’s efficiency, a
preliminary analysis of the first three months’ results appear to be nothing short of impressive.
Reprinted courtesy of
Neil Flynn, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Flynn may be contacted at
nf@plattalaw.com
Courthouse Reporter Series - How to Avoid Having Your COVID-19 Expert Stricken
September 25, 2023 —
Andrew G. Vicknair - The Dispute ResolverExpert witnesses play a key role in litigation, especially when dealing with construction issues. The testimony of an expert at trial can be a deciding factor in helping persuade a jury or judge in your client’s favor. Thus, it is imperative that your expert’s opinion meet the proper legal standard.
In Polaris Engineering, Inc. v. Texas International Terminals, LTD, the United States District Court for the Southern District of Texas reiterated the importance of an expert’s opinion complying with the applicable legal standards governing expert testimony. 2023 U.S. Dist. LEXIS 109413 (S.D. Tex. June 26, 2023).
The legal standard at issue in Polaris was Rule 702 of the Federal Rules of Evidence. Polaris involved a suit arising from a contract related to the design, engineering, and construction of a terminal and crude-oil processing facility for Texas International Terminals in Galveston, Texas. There were four separate contracts that governed the Project. One of the contracts governed the creation of the 50,000 barrel per day crude processing unit. Because the parties wanted to move quickly, they agreed to certain assumptions about the Project and specifically designed a change order process whereby the price and schedule could be adjusted if the agreed upon assumptions were incorrect.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
Staten Island Villa Was Home to Nabisco 'Nilla' Wafer Inventor
July 09, 2014 —
Laura Vecsey – BloombergThe imposing and historic Staten Island mansion that once belonged to Gustav A. Mayer — the 19th century inventor who cooked up the recipe for the Nabisco “Nilla” wafer — has been listed for sale for $1.79 million.
Although the estate has been rumored to be haunted, listing broker Jungho Kim of the Level Group confirmed, “This is not a haunted house.”
In fact, the only spirits that have inhabited this mansion are the models and photographers who have used portions of the Gustav Mayer House as a spectacular setting for photo shoots.
The mansion rents out about 3,000 square feet of the 7,700-square-foot home for photo shoots that wind up in the pages of Vogue, Harper’s Bazaar, W, Elle and New York Magazine.
Read the court decisionRead the full story...Reprinted courtesy of
Laura Vecsey, Bloomberg
CDC Issues Moratorium on Residential Evictions Through 2020
October 05, 2020 —
Steven E. Ostrow, C. Jason Kim, & Marissa Levy - White and Williams LLPOn September 1, 2020, the Centers for Disease Control and Prevention (CDC) announced that it was issuing an order (CDC Order) to temporarily halt residential evictions to prevent the further spread of COVID-19. The CDC Order became effective on September 4, 2020 and will remain in effect through December 31, 2020.
The purpose of the CDC Order is to keep tenants in their residences to reduce crowding in shelters or other shared housing and to reduce the number of unsheltered homeless, as those conditions have been shown to increase the spread of COVID-19.
APPLICABILITY & PROTECTIONS
The CDC Order is broader than the previous eviction moratorium under the Coronavirus Relief and Economic Security Act (CARES Act), which applied only to federally-funded housing and expired on July 24, 2020. Eligible renters include those who qualified for a stimulus check under the CARES Act and individuals who expect to make less than $99,000 this year or a joint-filing couple that expects to make less than $198,000.
Reprinted courtesy of
Steven E. Ostrow, White and Williams LLP,
C. Jason Kim, White and Williams LLP, and
Marissa Levy, White and Williams LLP
Mr. Ostrow may be contacted at ostrows@whiteandwilliams.com
Mr. Kim may be contacted at kimcj@whiteandwilliams.com
Ms. Levy may be contacted at levymp@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of