Two Injured in Walkway Collapse of Detroit Apartment Complex
May 30, 2018 —
Beverley BevenFlorez-CDJ STAFFABC WXYZ Local News reported that a balcony collapsed at the Anthoes Garden Apartments in Detroit, Michigan. Two people were witnessed falling from the upper walkway through the second and third floors, landing on the cement, sidewalk below. Neighbors pulled the thirty-something woman out of the debris, but the sixty-something man remained trapped under cement chunks and told the rescuers that he could not breathe. The neighbors used car jacks to raise the cement blocks to relieve pressure while waiting for help to arrive.
Firefighters rescued residents from the apartments. The fire marshall condemned the building. However, according to ABC News, "people who live in apartments nearby are afraid to leave because of the walkway's instability."
Read the court decisionRead the full story...Reprinted courtesy of
Jason Feld Awarded Volunteer of the Year by Claims & Litigation Management Alliance
April 15, 2024 —
Linda Carter - Kahana FeldOn April 3, 2024, Kahana Feld’s Co-Founding Partner, Jason Feld was honored by the Claims & Litigation Management Alliance (CLM) with the Inaugural Volunteer of the Year award.
The CEO of CLM, Ronna Ruppelt stated, “The new CLM Volunteer of the Year award honors dedicated members who passionately serve the CLM community. Jason’s service spans over a decade as both the President and Director of Events for the Orange County Chapter. Under his guidance, this chapter has flourished – not only educating and connecting the CLM community but rallying members to give back to the local community through service events in the process. Jason is also a frequent writer, speaker, and contributor for CLM events, and we are proud to honor him as our inaugural CLM Volunteer of the Year.”
Mr. Feld is a renowned nationwide construction claims leader who actively speaks at industry events. He serves as panel counsel for many prominent insurance carriers and provides personal counsel for multiple national and regional builders, developers, and contractors. With his vast experience and expertise, Mr. Feld is a trusted authority in the field and is highly regarded for his legal representation.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
NYC-N.J. Gateway Rail-Tunnel Work May Start in 2023
March 28, 2022 —
Elise Young - BloombergThe $12.3 billion Gateway rail tunnel linking New York City and New Jersey has reached a major preconstruction milestone with the completion of geotechnical studies necessary for the engineering phase.
The analysis of rock and silt from 75 earth samples on both sides of the Hudson River marks the latest in a series of swift leaps toward a potential 2023 start date. The project had been delayed years by former President Donald Trump, who had argued that costs should be covered solely by the states, not U.S. taxpayers.
The samples, from depths of 48 feet to 505 feet (14.6 meters to 154 meters), will guide design, according to the Gateway Development Commission, the project’s overseer. Some areas of particular interest to the researchers were on Manhattan’s West Side, parts of which were underwater before landfill was added many years ago.
Read the court decisionRead the full story...Reprinted courtesy of
Elise Young, Bloomberg
Appeals Court Finds Manuscript Additional Insured Endorsements Ambiguous Regarding Completed Operations Coverage for Additional Insured
September 07, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Pulte Home Corp. v. American Safety Indemnity Co. (No. D070478; filed 8/30/17), a California appeals court found that manuscript additional insured endorsements on construction subcontractors’ policies were ambiguous regarding additional insured coverage for the developer, and that substantial evidence supported a finding that the insurer’s refusal to defend the developer was in bad faith. The court also approved awarding punitive damages on a one-to-one basis with the general damages. But the appeals court remanded the case for a further determination on the amount of Brandt fees, based on the developer’s change from a contingency to an hourly agreement.
The Pulte case arose from the development of two residential housing projects beginning in 2003 and sold in 2005-2006. Subcontractors were required to name Pulte as additional insured on their policies, some of them issued by American Safety. In 2013, homeowners sued Pulte based in part on the work of subcontractors insured by American Safety, which then denied coverage to Pulte because the construction had taken place years earlier.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Appellate Court Addresses “Trigger of Coverage” for Asbestos Claims and Other Coverage Issues
November 30, 2020 —
Paul A. Briganti - Complex Insurance Coverage ReporterOn October 9, 2020, the New York Supreme Court, Appellate Division, Fourth Department, decided an appeal from a trial court’s 2018 summary judgment ruling on a number of coverage issues arising out of asbestos-related bodily injury claims against plaintiffs Carrier Corporation (Carrier) and Elliott Company (Elliott). See Carrier Corp. v. Allstate Ins. Co., No. 396 CA 18-02292, Mem. & Order (N.Y. Sup. Ct. App. Div. 4th Dep’t Oct. 9, 2020).
The Fourth Department reversed the trial court’s ruling that, under New York’s “injury in fact trigger of coverage,” injury occurs from the first date of exposure to asbestos through death or the filing of suit as a matter of law. The parties agreed that, because the policy language at issue required personal injury to take place “during the policy period,” “the applicable test in determining what event constitutes personal injury sufficient to trigger coverage is injury-in-fact, ‘which rests on when the injury, sickness, disease or disability actually began.’” Id. at 3 (quoting Cont’l Cas. Co. v. Rapid-American Corp., 609 N.E.2d 506, 511 (N.Y. 1993)). The Fourth Department concluded that, in resolving the issue, the trial court erred by relying on inapposite decisions in other cases where: (1) the parties had stipulated or otherwise not disputed that first exposure triggered coverage[1]; or (2) the issue had not been resolved on summary judgment, but rather at trial based on expert medical evidence[2]. The Fourth Department further explained that, even if plaintiffs here had met their initial burden on summary judgment by submitting admissible evidence that asbestos-related injury actually begins upon first exposure, the defendant-insurer’s opposition – which included affidavits of medical experts contradicting that evidence and averring instead that “harm occurs only when a threshold level of asbestos fiber or particle burden is reached that overtakes the body’s defense mechanisms” – raised a triable issue of fact. Id. at 4. The Fourth Department also rejected plaintiffs’ argument that the defendant-insurer was collaterally estopped on the “trigger” issue by a California appellate court’s decision in Armstrong World Industries, Inc. v. Aetna Casualty & Surety Co., 52 Cal. Rptr. 2d 690 (Cal. Ct. App. 1996). The Fourth Department reasoned that the issues litigated in the two cases were not identical because, among other things, California and New York “apply different substantive law in determining when asbestos-related injury occurs.” Carrier, Mem. & Order at 4.
Read the court decisionRead the full story...Reprinted courtesy of
Paul A. Briganti, White and Williams LLPMr. Briganti may be contacted at
brigantip@whiteandwilliams.com
Second Circuit Upholds Constitutionality of NY’s Zero Emissions Credit Program
November 21, 2018 —
Anthony B. Cavender - Gravel2GavelOn September 27, the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s ruling that the “Zero Emissions Credit” (ZEC) program of the New York Public Service Commission is not unconstitutional. The case is Coalition for Competitive Electricity, et al. v. Zibelman, Chair of the New York Public Service Commission, et al.
In effect, the ZEC program provides subsidies to qualifying New York nuclear power plants as a way to reduce greenhouse gas emissions. The ZEC program is intended to prevent nuclear plants from being prematurely retired from generating power until suitable replacement facilities are operating.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Court Says KBR Construction Costs in Iraq were Unreasonable
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFMike Bosse of Bernstein Shur, analyzed a case involving Kellogg Brown and Root Services Inc. (KBR) and the U.S. Army for services that KBR provided during Operation Iraqi Freedom, according to JDSupra Business Advisor: “The court case involved KBR’s construction of dining facility services near Mosul, Iraq under a cost-plus fee arrangement. Under this contractual arrangement, all allowable costs were reimbursed by the government plus the contractor was paid an additional fee.”
KBR first started on a prefabricated metal dining hall that would serve 2,500 people, but part way into building they were told to stop construction and to instead start on a new reinforced concrete building that would serve almost three times as many people.
“After construction was finished, a defense contract auditing agency suspended some of the payments to KBR and instead of the $12.5 million it expected to receive, KBR was paid only $6.7 million,” reported JDSupra Business Advisor. “After trial, the court concluded KBR did not meet its burden to show the costs it incurred were reasonable under the circumstances.”
Read the court decisionRead the full story...Reprinted courtesy of
Candlebrook Adds Dormitories With $230 Million Purchase
November 05, 2014 —
John Gittelsohn - BloombergCandlebrook Properties LLC, a closely held company with about 5,000 apartments in the eastern U.S., is diversifying into student housing with the $230 million acquisition of five off-campus properties.
Candlebrook joined with Lubert-Adler Partners on the purchase of buildings with about 3,400 beds near colleges in Georgia, Indiana, Kentucky and Virginia. Formerly known as Vantage Properties LLC, Candlebrook began as an investor in New York City apartments in 2005 and later expanded to New Jersey and the Philadelphia area.
“Student housing is a natural extension of our pre-existing business line,” Neil Rubler, president of New York-based Candlebrook, said in a telephone interview. It’s “a business that’s far less crowded than multifamily, which has been our core business.”
Capitalization rates on apartments, a measure of profitability, have dropped as investors drive up property prices. Student housing has become an attractive alternative, luring homebuilder Toll Brothers Inc. (TOL) and private-equity firm Colony Capital LLC to an industry already home to real estate investment trusts American Campus Communities Inc. (ACC), Campus Crest Communities Inc. (CCG) and Educational Realty Trust Inc. (EDR)
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelsohn may be contacted at
johngitt@bloomberg.net