Judgment for Insured Upheld After Insurer Rejects Claim for Hurricane Damage
April 15, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Texas Court of Appeals affirmed a trial court's judgment as modified against Lloyds for improperly denying a claim for damage caused by Hurricane Ike. Nat'l Lloyds Ins. Co. v. Lewis, 2015 Tex. App. LEXIS 1573 (Tex. Ct. App. Feb. 19, 2015).
Lewis sued Lloyds, alleging that, although her home and personal property were seriously damaged by Hurricane Ike, her claim was denied. At trial, Lloyds testified that the damage to Lewis' home had been previously caused by Hurricane Rita and Lloyds had already paid for repair of the roof. Nevertheless, Lewis had not used the payment for roof repairs. Lewis admitted that she used some of the payment after Hurricane Rita to purchase a generator and for evacuation expenses, but the majority of the payment was used for roof repairs.
Lewis' expert engineer testified that the damage to Lewis' home was caused by wind and water intrusion through a hole caused by a tree limb that fell during Hurricane Ike. The expert further opined that the cost to mitigate the damage to the home and bring it up to livable standard was $156,155. Further, the home was a constructive total loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Vietnam Expands Arrests in Coffee Region Property Probe
February 19, 2024 —
Mai Ngoc Chau - BloombergVietnam authorities detained the Communist Party chief of coffee-producing province Lam Dong as they expand an investigation into alleged bribery tied to a tourist and residential project, the public security ministry said in a website statement.
Party chief Tran Duc Quan was arrested for allegedly abusing his power and position, according to the statement. Quan allegedly violated the law while giving instructions to the Dai Ninh property project in the province, causing severe consequences, it said.
A Lam Dong Provincial Party Committee representative declined to provide a comment about the arrest. A representative for Quan was not available.
Read the court decisionRead the full story...Reprinted courtesy of
Mai Ngoc Chau, Bloomberg
Coverage Rejected Under Owned Property and Alienated Property Exclusions
June 06, 2011 —
Tred R. EyerlyThe insured’s request for a defense when sued in a construction defect action was denied under the owned property exclusion and the alienated property exclusion in1777 Lafayette Partners v. Golden Gate Ins. Co., 2011 U.S. Dist. LEXIS 48562 (N.D. Cal. April 29, 2011).
In 1999, Lafayette Partners purchased an abandoned walnut processing factory to convert into living and working units. The property was developed into a rental property from 2000-2001, and thereafter rented. In May 2003, Lafayette Partners entered into a sales agreement with Wolff Enterprises LLC. The sale closed in February 2005. Wolff then converted the rental units into condominiums.
In December 2007, the Walnut Factory Owners Association sued Wolff for construction defects. In Lafayette Partners was added to the suit in 2009. The suit alleged a variety of defective conditions, including the roofs, exteriors, windows, electrical , plumbing, and mechanical components and systems.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
When OSHA Cites You
April 22, 2024 —
Michael Metz-Topodas - Construction ExecutiveWith the strong bonds that form among construction project teams, workers looking out for each other helps keep safety foremost in everyone’s mind. But sometimes, even the very best intentions alone can’t prevent an occasional misstep—a forgotten hard hat, a sagging rope line—which can and often does result in an OSHA citation. These regulatory reminders can bring unfortunate consequences: penalties, higher insurance premiums, potential worker injury claims, loss of bidding eligibility, loss of reputation and even public embarrassment, because citations are published on OSHA’s website.
Due to citations’ adverse effects, contractors have incentives to minimize them. They can do this by asserting available defenses, because a citation is only an alleged violation, not a confirmed one. But making defenses available begins well before a citation is issued, well before OSHA arrives to a construction site and well before a violation even occurs. Instead, contractors’ ongoing safety programs should incorporate the necessary measures to preserve OSHA citation defenses in three key areas: lack of employee exposure, lack of employer knowledge and impossibility.
EMPLOYEE EXPOSURE
To sustain a citation against an employer, OSHA must not only identify an applicable standard that the company violated but also show that the violation exposed employees to hazards and risk of injury. Absent evidence of actual exposure, OSHA often makes this showing by asserting that performing job functions necessarily exposes employees to the cited hazard.
Reprinted courtesy of
Michael Metz-Topodas, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Metz-Topodas may be contacted at
michael.metz-topodas@saul.com
Subcontract Should Flow Down Delay Caused by Subcontractors
December 21, 2020 —
David Adelstein - Florida Construction Legal UpdatesA general contractor’s subcontract with its subcontractor should include a provision that entitles it to flow down liquidated damages assessed by the owner stemming from delays caused by the subcontractor. Such a provision does not mean the general contractor does not have to prove delays caused by the subcontractor or can arbitrarily allocate the amount or days it claims the subcontractor is liable. The general contractor still will need to reasonably establish the delays the subcontractor caused the critical path of the schedule, i.e., delayed the job. In addition to the right to flow down liquidated damages, the subcontract should also entitle the general contractor to recover its actual extended general conditions caused by the subcontractor’s delays (regardless of whether the owner assesses liquidated damages). The objective is that if the subcontractor delays the job, the subcontractor is liable for liquidated damages the general contractor is liable to the owner for in addition to the general contractor’s own delay damages. This is an important subcontractual provision so that the risk of delay caused by subcontractors is clearly flowed down to them in the subcontract.
In a 1987 case, Hall Construction Co., Inc. v. Beynon, 507 So.2d 1225 (Fla. 5th DCA 1987), the subcontract at-issue contained language that stated, “The parties hereto agree that a supplier who delays performance beyond the time agreed upon in this Purchase Order shall have caused [general contractor] liquidated damages in the amount required of [general contractor] by their contract per day for each day such delay continues which sum the supplier hereby agrees to pay.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Anti-Concurrent Causation Clause Preserves Possibility of Coverage
January 15, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's anti-concurrent causation clause preserved the possibility of coverage when the insurer's motion for summary judgment to disclaim its indemnity obligation for damage caused by Hurricane Sandy was overturned by the Second Circuit. Madelaine Chocolate Novelties, Inc. v. Great Northern Ins. Co., 2018 U.S. App. LEXIS 29821 (Oct. 23, 2018 2nd Cir. )
In 2012, Madelaine Chocolate suffered significant damage to its business due to storm surges created by Hurricane Sandy. Madelaine Chocolate had an "all-risk" policy issued by Great Northern. Madelaine Chocolate filed a claim for property damage of approximately $40 million and business income loss and extra operation expenses of $13.5 million. Great Northern denied most of the claim, reasoning that the storm surge damage was excluded under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
2023 West Coast Casualty Construction Defect Seminar
March 27, 2023 —
Beverley BevenFlorez – CDJ StaffThe 29th annual West Coast Casualty Construction Defect Seminar will return to the Disneyland Hotel in May. The event covers topics of interest to those in the construction defect field including prosecution, defense, insurance coverage, and science and technology. The seminar will also have networking opportunities. Attendees every year include professionals “from the legal, insurance, builder, contractor, subcontractor and numerous other communities.”
May 18th-19th, 2023
Disneyland Hotel
1150 Magic Way
Anaheim, CA 92802
Read the court decisionRead the full story...Reprinted courtesy of
2019 Legislative Changes Affecting the Construction Industry
July 09, 2019 —
Melinda S. Gentile & Cadian T. Baker - Peckar & Abramson, P.C.The 2019 Florida Legislative Session recently concluded and a number of important construction-related House Bills (HB) and Senate Bills (SB) were presented during the Session. Below is a summary of those construction-related bills set to become law in 2019.
Bills Becoming Law in 2019
HB 1247: Relating to Construction Bonds. This bill passed both the House and the Senate and is awaiting the Governor’s signature. Once the Governor has approved the bill it becomes effective as of October 1, 2019.
This bill addresses how to properly perfect a claim against a contractor’s payment bond.
(1) The Notice of Nonpayment that must be served on the contractor and the surety, must be made under oath and include the following provisions:
The nature of the labor or services performed or to be performed;
The materials furnished or to be furnished;
The amount paid on the account; and if known, the amount owed and the amount to become due.
A Notice of Nonpayment that includes the sums for retainage must specify the portion of the amount claimed for retainage.
(2) A subcontractor, laborer, or material supplier (claimant) who files a fraudulent Notice of Nonpayment loses their rights under the bond. The filing of a fraudulent notice is a complete defense to claimant’s claim against the bond. A notice is fraudulent if the claimant willfully exaggerated the amount due, willfully included a claim for work not performed or materials not furnished or prepared the notice with willful and gross negligence, which resulted in willful exaggeration. However, a minor mistake in the notice, or a good faith dispute as to the amount due, is not considered fraudulent. Please note that this provision mirrors the existing statute relative to a fraudulent lien.
Read the court decisionRead the full story...Reprinted courtesy of
Melinda S. Gentile, Peckar & Abramson, P.C.Ms. Gentile may be contacted at
mgentile@pecklaw.com