Design and Construction Defects Not a Breach of Contract
February 14, 2013 —
CDJ STAFFThe California Court of Appeals tossed out a breach of contract award in Altman v. John Mourier Construction. The decision, which was issued on January 10, 2013, sent the construction defect case back to a lower court to calculate damages based on the conclusions of the appeals court.
The case involved both design issues and construction issues. According to the plaintiffs’ expert, the design plans did not make the buildings sufficiently stiff to resist the wind, and that the framing was improperly constructed, further weakening the structures, and leading to the stucco cracking. Additionally, it was alleged that the roofs were improperly installed, leading to water intrusion. The contractor’s expert “agreed the roofs needed repair, but disputed what needed to be done to repair the roofs and the cost.”
The jury rejected the plaintiffs’ claims of product liability and breach of warranty, but found in their favor on the claims of breach of contract and negligence. The plaintiffs were awarded differing amounts based on the jury’s conclusions about their particular properties.
Both sides sought new trials. JMC, the contractor, claimed that the jury’s verdicts were “inconsistent in that the relieved JMC of liability for strict products liability and breach of warranty, but found JMC liable for breach of contract and negligence.” The plaintiffs “opposed the setoff motion on the ground that the jury heard evidence only of damages not covered by the settlements.” Both motions were denied. After this, the plaintiffs sought and received investigative costs as damages. JMC appealed this amended judgment.
The appeals court rejected JMC’s claims that evidence was improperly excluded. JMC sought to introduce evidence concerning errors made by the stucco subcontractor. Earlier in the trial, JMC had insisted that the plaintiffs not be allowed to present evidence concerning the stucco, as that had been separately settled. When they wished to introduce it themselves, they noted that the settlement only precluded the plaintiffs from introducing stucco evidence, but the trial court did not find this persuasive, and the appeals court upheld the actions of the trial court. Nor did the appeals court find grounds for reversal based on claims that the jury saw excluded evidence, as JMC did not establish that the evidence went into the jury room. Further, this did not reach, according to the court, a “miscarriage of justice.”
The court rejected two more of JMC’s arguments, concluding that the negligence award did not violate the economic loss rule. The court also noted that JMC failed to prove its contention that the plaintiffs were awarded damages for items that were covered in settlements with the subcontractors.
The appeals court did accept JMC’s argument that the award for breach of contract was not supported by evidence. As the ruling notes, “plaintiffs did not submit the contracts into evidence or justify their absence; nor did plaintiffs provide any evidence regarding contract terms allegedly breached.”
The court also did not allow the plaintiffs to claim the full amount of the investigative costs. Noting that the trial court had rational grounds for its decision, the appeals court noted that “the jury rejected most of the damages claimed by plaintiffs, and the trial court found that more than $86,000 of the costs itemized in plaintiffs’ invoices ‘appear questionable’ as ‘investigation’ costs/damages and appeared to the trial court to be litigation costs nonrecoverable under section 1033.5.”
Read the court decisionRead the full story...Reprinted courtesy of
Idaho Federal Court Rules Against Sacketts After SCOTUS Decided Judicial Review of an EPA Compliance Order was Permissible
May 13, 2019 —
Anthony B. Cavender - Gravel2GavelIn a decision released on March 31, in Sackett v. EPA, the U.S. District Court for Idaho held, without benefit of oral argument, that the Environmental Protection Agency’s (EPA) motion for summary judgment should be granted, and accordingly, the Sacketts had violated the Clean Water Act (CWA) by making improvements to 0.63 acres of land they owned without a required CWA permit when the land qualified as a “wetlands.”
The EPA had determined the Sacketts’ “property is subject to the CWA because it contains wetlands adjacent to Priest Lake, a traditionally ‘navigable water,’ and, additionally, their property is wetland adjacent to a tributary and similarly situated to other wetlands and has a significant nexus to Priest Lake.” The District Court rejected the Sacketts’ arguments that their property was not a “wetlands” subject to the CWA.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
White and Williams Earns Tier 1 Rankings from U.S. News "Best Law Firms" 2017
November 03, 2016 —
White and Williams LLPWhite and Williams received one National Tier 1 ranking and four Metropolitan Tier 1 rankings in U.S. News - Best Lawyers® "Best Law Firms" for 2017. Firms included in the “Best Law Firms” list are recognized for professional excellence with persistently impressive ratings from clients and peers. Achieving a tiered ranking signals a unique combination of quality law practice and breadth of legal experience.
National Tier 1
Insurance Law
Metropolitan Tier 1
Boston
Insurance Law
Product Liability Litigation - Defendants
Philadelphia
Real Estate Law
Tax Law
Metropolitan Tier 2
Boston
Mergers and Acquisitions Law
Philadelphia
Construction Law
Insurance Law
Tax and Estates Law
Metropolitan Tier 3
Boston
Employment Law - Management
Labor Law - Management
Litigation - Labor and Employment
Philadelphia
Patent Law
Read the court decisionRead the full story...Reprinted courtesy of
Orange County Team Obtains Unanimous Defense Verdict in Case Involving Failed Real Estate Transaction
March 25, 2024 —
Lewis Brisbois NewsroomOrange County, Calif. (March 4, 2024) - Orange County Partners Esther P. Holm and Alexandra Anast obtained a unanimous defense verdict in a real estate matter involving a failed real estate transaction. The property at issue, which was located in the West Hollywood Hills and had beautiful views, was undergoing extensive remodeling. There were several bids for its purchase. Ultimately, the plaintiff, a real estate investor, was awarded the purchase.
The plaintiff and the seller entered into a real estate purchase agreement, but the plaintiff failed to release the physical contingencies within the 17-day period prescribed by the contract. Instead, the plaintiff demanded a reduction in price, which the seller rejected. The plaintiff then filed a lis pendens on the property, clouding the title and making it impossible for the sellers to sell the property to anyone else. The buyer and seller subsequently engaged counsel. The plaintiff filed the lawsuit against the seller as well as the real estate company and its agents. Prior to trial, the plaintiff and the seller reached a settlement.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
When Subcontractors Sue Only the Surety on Payment Bond and Tips for General Contractors
August 13, 2019 —
Ira M. Schulman & Emily D. Anderson - ConsensusDocsPayment bonds have been a staple of public construction projects since 1874, when the U.S. Congress first passed the Heard Act, which required that contractors obtain payment bonds for public projects to ensure that subcontractors and material suppliers have a way to recover their damages if an upstream contractor fails to pay for work performed and materials furnished on the project. The 1874 Heard Act has since been replaced by the 1935 Miller Act, and the concept has been expanded to construction projects funded by the states through state statutes known as “Little Miller Acts.” But the structure remains the same: On most public projects where the project’s cost exceeds $100,000, the prime contractor (the bond principal) is required to obtain a payment bond from a surety equal to the contract price to guarantee to subcontractors and material suppliers (the bond obligees) that the surety will pay for labor and materials under certain statutory or contractual conditions should the contractor fail to make payment.
A surety is jointly and severally liable with the contractor to the subcontractor, which means that the subcontractor may seek recovery against either the contractor or the surety or both, and the contractor and surety will be liable for the damages together. Put another way, in most states and in federal court, an unpaid subcontractor has the right to sue only the surety on the payment bond without joining the contractor because a contract of suretyship is a direct liability of the surety to the subcontractor.1 When the contractor fails to perform, the surety becomes directly responsible at once — it is unnecessary for the subcontractor to establish that the contractor failed to carry out its contract before the obligation of the surety becomes absolute.
Reprinted courtesy of
Ira M. Schulman, Pepper Hamilton LLP and
Emily D. Anderson, Pepper Hamilton LLP
Mr. Schulman may be contacted at schulmani@pepperlaw.com
Ms. Anderson may be contacted at andersone@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Choice of Laws Test Mandates Application of California’s Continuous and Progressive Trigger of Coverage to Asbestos Claims
June 01, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Textron v. Travelers Casualty and Surety Co. (No. B262933, filed 2/25/20), a California appeals court held that the Restatement’s choice of laws factors mandated application of California’s continuous and progressive trigger of coverage to asbestos claims, overcoming an argument that a manifestation trigger should apply under Rhode Island law.
Travelers insured Textron from 1966 to 1987. In 2011, Textron was sued by a California resident, Esters, for damages caused by mesothelioma resulting from asbestos exposure in California. The action was defended and settled by Travelers and other insurers under reservations of rights. Textron sued Travelers in California for a declaration that Travelers owed duties to defend and indemnify the Esters action. Travelers cross-complained, seeking reimbursement.
The case turned on choice of law for trigger of coverage as between California and Rhode Island. Citing Montrose Chemical Corp. v. Admiral Ins. Co. (1995) 10 Cal.4th 645 and Armstrong World Industries, Inc. v. Aetna Casualty & Surety Co. (1996) 45 Cal.App.4th 1, the Textron court noted that California applies a continuous trigger to continuous or progressively deteriorating injury. By contrast, in Rhode Island a covered occurrence exists “when the damage … manifests itself, … is discovered or, … in the exercise of reasonable diligence is discoverable.” (Citing Textron, Inc. v. Aetna Cas. and Sur. Co. (R.I. 2002) 754 A.2d 742.) According to Travelers, the Esters action was not covered under Rhode Island law because the plaintiff’s mesothelioma was not diagnosed until 2010, after Travelers was off the risk.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Latin America’s Biggest Corporate Crime Gets a Worthy Epic
January 04, 2021 —
Mac Margolis - BloombergAs much as pouring cement and building towers, Brazilian construction dynasty Odebrecht was famed for its political panache. “I get down in the mud with the pigs but come out the other side clean in my white suit,” Norberto Odebrecht, founder of the legacy contractor, liked to boast back in the 1970s and 1980s. The catchphrase was shorthand for what became a patently Brazilian way of doing business – the art of buying influence and coming away unsoiled, or at least unincarcerated – among porcine politicians and bribe-truffling officials.
In half a century and over three generations, the family firm from northeast Brazil grew into a multinational engineering colossus, hurling up grand public works from the Andes to Angola. Shady pacts with political grifters and bagmen were just part of the deal behind the build-up and seemingly nothing a little Brazilian bonhomie and contract skimming couldn’t tidy up. Until it didn’t.
Read the court decisionRead the full story...Reprinted courtesy of
Mac Margolis, BloombergMr. Margolis may be contacted at
mmargolis14@bloomberg.net
What Makes Building Ventilation Good Enough to Withstand a Pandemic?
January 11, 2021 —
Linda Poon - BloombergIn October, students at the University of Illinois, Urbana-Champaign, held an intimate jazz concert at a bar downtown, with an audience of about 20 peers and faculty members — all of whom held digital passes indicating they’d recently tested negative for Covid-19. Two jazz ensembles performed, sometimes with masks and coverings for their instruments, and other times without.
Behind the scenes, mechanical engineering professor Ty Newell tinkered with the airflow, turning the exhaust and recirculation fans on and off at different points during the night. His students monitored for changes in the air quality, using a special instrument to measure the concentrations of carbon dioxide and fine particulate matter, both key to determining if a building is well ventilated.
The experiment sought to highlight the significance of proper ventilation, something that Newell said hadn’t been paid enough attention, until now. As evidence suggesting Covid-19 can spread through aerosol transmission continues to mount, health experts are focused less on sanitizing surfaces and more on improving indoor air quality. In December, the U.S. Centers for Disease Control and Prevention finally put out its ventilation recommendations to combat Covid-19, based on standards set by ASHRAE, or the American Society of Heating, Refrigerating and Air-Conditioning Engineers.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Poon, Bloomberg