Construction Manager’s Win in Michigan after Michigan Supreme Court Finds a Subcontractor’s Unintended Faulty Work is an ‘Occurrence’ Under CGL
August 03, 2020 —
Gabrielle Szlachta-McGinn - Newmeyer DillionOn June 29, 2020, the Michigan Supreme Court overturned a longstanding precedent that commercial general liability (“CGL”) insurers have historically relied upon to deny insurance coverage for claims involving pre-1986 CGL policies. See Hawkeye-Security Ins. Co. v. Vector Const. Co., 185 Mich. App. 369, 372, 460 N.W.2d 329, 331 (1990). In its recent ruling, the state Supreme Court unanimously agreed that an Insurance Services Office, Inc. (“ISO”) 1986 standard CGL policy, which is sold to construction contractors across the United States, provides coverage for property damage to a policyholder’s work product that resulted from a subcontractor’s unintended faulty workmanship. Skanska USA Bldg. Inc. v. M.A.P. Mech. Contractors, Inc., No. 159510, 2020 WL 3527909 (Mich. June 29, 2020).
In 2008, Skanska USA Building, Inc., the construction manager on a renovation project for Mid-Michigan Medical Center, signed a subcontract with defendant M.A.P. Mechanical Contractors (“MAP”) to install a new heating and cooling (“HVAC”) system. Id. During the renovation, MAP installed some of the expansion joints in the new HVAC system backwards. Id. The defective installation caused approximately $1.4 million in property damage to concrete, steel and the heating system, which Skanska discovered nearly two years after MAP completed the project. Id. After performing the repairs and replacing the damaged property, Skanska sought repayment for the repair costs from MAP and also submitted a claim to Amerisure seeking coverage as an insured under the CGL policy. Id. When Amerisure rejected Skanska’s claim, Skanska sued both parties. Id. Amerisure relied on the holding in Hawkeye and argued that MAP’s defective workmanship was not a covered “occurrence” under the CGL policy, which the policy defined as an accident. Id. at *4.
The Michigan Court of Appeals ignored the express language contained in the CGL policy and applied a prior appellate court precedent from Hawkeye, finding that MAP’s faulty work was not an “occurrence” and thus, did not trigger CGL coverage. Id. at *4. The Court of Appeals further reasoned that Skanska was an Amerisure policyholder and that the only property damage was to Skanska’s own work, which was not covered under the CGL policy. Id. at *5.
In a landmark decision, the Michigan Supreme Court reversed, holding unanimously that the Court of Appeals incorrectly applied the holding of Hawkeye because it failed to consider the impact of the 1986 revisions to standard CGL insurance policies. Id. at *10. Chief Justice Bridget M. McCormack explained that the Hawkeye decision rested on the 1973 version of the ISO form insurance policy, which specifically excluded certain business risks from coverage such as property damage to a policyholder’s own work. Id. The Supreme Court agreed that while Hawkeye was correctly decided, it did not apply here because the 1986 revised ISO policy includes an exception for property damage caused by a subcontractor’s unintentional faulty work. Id.
The Supreme Court said that under the plain reading of the current CGL policy language, an “accident” could include a subcontractor’s unintentional defective work that damaged a policyholder’s work product and thus, may qualify as an “occurrence” covered under the policy. Id. at *9. The Supreme Court defined an “accident” (which was not defined in the Amerisure policy) as “an undefined contingency, a casualty, a happening by chance, something out of the usual course of things, unusual, fortuitous, not anticipated, and not naturally to be expected.” Id. at *5; see Allstate Ins. Co. v. McCarn, 466 Mich. 277, 281, 645 N.W.2d 20, 23 (2002). The Supreme Court noted that there was no evidence suggesting that MAP purposefully installed the expansion joints backwards, nor was there evidence indicating that the parties affected by MAP’s negligence anticipated, foresaw, or expected MAP’s defective installation or property damage. Skanska, 2020 WL 3527909, at *4. Therefore, the Supreme Court concluded that an “occurrence” may have happened, which would trigger coverage under the CGL policy. Id. at *10.
Although this landmark decision changes Michigan law, the decision is limited to cases involving the 1986 ISO policy language revisions to CGL insurance policies. Id. The Supreme Court's decision does not overturn Hawkeye, but rather limits Hawkeye’s authority to cases involving the 1973 ISO form. Id.
Gabrielle Szlachta-McGinn was a summer associate at Newmeyer Dillion as part of the firm's 2020 summer class. You may learn more about Newmeyer Dillion's construction litigation services and find the group's key contacts at https://www.newmeyerdillion.com/construction-litigation/.
Read the court decisionRead the full story...Reprinted courtesy of
U.S., Canada, Mexico Set New Joint Clean-Energy Goal
June 30, 2016 —
Tom Ichniowski – Engineering News-RecordThe U.S., Canada and Mexico have agreed to boost their combined clean-energy generation to 50% of electricity production by 2025, from 37% last year.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, Engineering News-RecordMr. Ichniowski may be contacted at
ichniowskit@enr.com
Beware of Personal-Liability Clauses – Even When Signing in Your Representative Capacity
January 31, 2018 —
David R. Cook Jr. – Autry, Hall & Cook, LLPWhen a contract is drafted by a party, the other party expects some level of one-sidedness in favor of the drafter. But there are times when a contract goes too far. There are certain provisions that most persons in the construction industry would find unacceptable, unfair, and beyond the pale – even for a one-sided contract. Such a provision was arguably found in an electrical subcontract at issue in a 2014 opinion by a three-judge panel of the Georgia Court of Appeals. Unfortunately, due to long-standing Georgia law, the panel was forced to apply the provision as written.
In the case, a contractor hired a subcontractor to perform the electrical scope of work. When the subcontractor failed to pay a sub-subcontractor, the sub-subcontractor filed suit against the subcontractor, contractor, and the payment-bond surety. The contractor asserted a claim of indemnity against the subcontractor based on the sub-subcontractor’s claim.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Coverage Denied for Faulty Blasting and Improper Fill
October 08, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found coverage was properly denied based on the subcontractor's failure to follow contract specifications in blasting at the job site. Westfield Ins. Co. v. Carpenter Reclamation, Inc., 2014 U.S. Dist. LEXIS 130752 (S.D. W. Va. Sept. 18, 2014).
Carpenter was hired by the Board of Education (BOE) to perform preliminary site clearing, demolition, rock excavation, and establishment of sub-grade for a building. Carpenter was to excavate to 3.5 feet below the floor subgrade so that plumbing and other utilities could be installed.
Carpenter, however, blasted to depths deeper than required, including some areas that were up to nine feet. The BOE sued, alleging over-blasting and having to pay the cost of remediating the problem, along with breach of contract issues.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
United States Supreme Court Grants Certiorari in EEOC Subpoena Case
March 29, 2017 —
Jeffrey M. Daitz & Rashmee Sinha - Peckar & Abramson, P.C.On September 29, 2016, the United States Supreme Court granted certiorari in McLane Co. Inc. v. EEOC, case number 15-1248, a case that asks the Court to resolve a split in the Circuit Courts of Appeals on the proper standard of review applied to a district court decision to quash or enforce a subpoena issued by the United States Equal Employment Opportunity Commission ("EEOC"). The decision by our highest court on the correct standard of review will have important implications for businesses, because if a litigant is displeased with a lower court's decision, it may get two bites at the apple. Such an outcome will likely encourage more appeals, drawn-out investigations and increase legal fees.
On the other hand, if the Supreme Court decides that the Ninth Circuit was wrong and that a deferential standard of review (as opposed to a de nova standard) is appropriate, the losing side in future cases is more likely to accept the decision of the lower district court, knowing its chances of winning on appeal are slim.
Reprinted courtesy of
Jeffrey M. Daitz, Peckar & Abramson, P.C. and
Rashmee Sinha, Peckar & Abramson, P.C.
Mr. Daitz may be contacted at jdaitz@pecklaw.com
Ms. Sinha may be contacted at rsinha@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Sustainable, Versatile and Resilient: How Mass Timber Construction Can Shake Up the Building Industry
April 10, 2023 —
Cait Horner, Adam J. Weaver & Allan C. Van Vliet - Gravel2Gavel Construction & Real Estate Law BlogDesign professionals, real estate developers and builders alike are advocating for a relatively new way of using one of the world’s oldest building materials—wood—in large-scale commercial and residential construction projects. Mass timber, or structural timber, touts such benefits as carbon reduction and seismic durability—all with a lower construction time. With ESG on the minds of clients, investors and tenants, mass timber projects present an attractive construction option for the integration of sustainable resources and these various benefits.
The most common and popular form of mass timber, cross-laminated timber (CLT), has been recently gaining popularity in the U.S. after widespread adoption in Europe over the past 20 years. CLT consists of layers of trimmed and kiln-dried lumber boards, usually three, five or seven across, stacked and glued crosswise at 90-degree angles. These stacked lumber boards create large slabs that are used to build floors, walls and ceilings—put those fabricated pieces together, and you have a whole building constructed of CLT.
Reprinted courtesy of
Cait Horner, Pillsbury,
Adam J. Weaver, Pillsbury and
Allan C. Van Vliet, Pillsbury
Ms. Horner may be contacted at cait.horner@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Mr. Van Vliet may be contacted at allan.vanvliet@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Delaware District Court Finds CGL Insurer Owes Condo Builder a Duty to Defend Faulty Workmanship Claims — Based on the Subcontractor Exception to the Your Work Exclusion
October 04, 2021 —
Anthony L. Miscioscia & Laura Rossi - White and WilliamsOn September 7, 2021, in one of the few decisions addressing the scope of coverage for faulty workmanship under Delaware law, the Delaware District Court denied an insurer’s motion seeking a declaration that it neither needed to defend nor indemnify an insured-builder under a commercial general liability policy.
In this declaratory judgment action, Pennsylvania National Mutual Casualty Insurance Company v. Zonko Builders, the insurer argued that the ongoing underlying action failed to properly plead an “occurrence” in a case alleging damages to a condominium caused by faulty workmanship involving subcontractors.* Zonko Builders (Zonko) served as the general contractor, supervising subcontractors. The Condominium Association sued Zonko for damages allegedly resulting from design and construction deficiencies. The motion was opposed by the Condominium Association, which cross-moved for partial judgment on the pleadings.
In AE-Newark Associates, L.P. v. CNA Insurance Companies, 2001 Del. Super. LEXIS 370 (Del. Super. Ct. Oct. 2, 2001), the Delaware Superior Court found that an insured was entitled to coverage for damages arising from a faulty roof system installed by a subcontractor on behalf of the insured general contractor.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Laura Rossi, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Rossi may be contacted at rossil@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Insurance Coverage Debate on Construction Defects Continues
February 05, 2015 —
Craig Martin – Construction Contractor AdvisorNew Hampshire is the first court of 2015 to weigh in on construction defect coverage issues. The case, Cogswell Farm Condominium Association v. Tower Group, involved a typical situation. Lemery Building Company was hired to build 24 residential condominium units. After construction, the condominium association sued the builder asserting that the weather barrier, including the water/ice shield, flashing, siding, and vapor barrier, was defectively constructed and resulted in damage to the units due to water leaks. The condominium association also sued Lemery’s insurer for a determination as to whether the builder’s Commercial General Liability (CGL) insurer had to provide coverage for the claim.
The trial court ruled against the condominium association, finding that the “your work” exclusion applied. The exclusion in the builder’s CGL policy provided that there was no coverage for property damage to “[t]hat particular part of any property that must be restored, repaired or replaced because ‘your work’ was incorrectly performed on it.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com